1539 W 37TH PL 90018

Certificate Information: 1539 W 37TH PL 90018

Application / Permit
21010-10000-01929
Plan Check / Job No.
B21LA07290
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 2 CAR GARAGE 360.0 SF
Permit Issued
Issued on 2/24/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 ZAW HAN
Corrections Issued 5/5/2021 ZAW HAN
Quality Review Completed 5/11/2021 WING SUEN
Building Plans Picked Up 5/20/2021 APPLICANT
Applicant returned to address corrections 11/4/2021 ZAW HAN
Plan Check Approved 11/23/2021 ZAW HAN
Issued 2/24/2022 APPLICANT
CofO in Progress 5/9/2023 ALIZAH MAYAGOITIA
CofO in Progress 5/9/2023 ALIZAH MAYAGOITIA
Permit Finaled 5/13/2023 DEROLD HAUFF
CofO Issued 5/13/2023 DEROLD HAUFF
Permit Finaled 5/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/10/2021 STEVE MELGAR
Permit Cleared 6/10/2021 STEVE MELGAR
Sewer availability Cleared 6/10/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/9/2021 STEVE MELGAR
Certificate of Compliance Cleared 8/10/2021 DANIEL CORONADO
Abandoned oil well Cleared 10/7/2021 ROBERT DUFF
Hydrant and Access approval Cleared 10/7/2021 ROBERT DUFF
Roof/Waste drainage to street Cleared 10/12/2021 STEVE MELGAR

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/14/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 4/22/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Partial Approval HORACE FULTZ
BUILDING-Rough-Frame 9/29/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 9/29/2022 Approved SABAS ALONSO
Green Building Rough 9/29/2022 Approved SABAS ALONSO
HVAC-Rough 9/29/2022 Approved SABAS ALONSO
PLUMBING-Rough 9/29/2022 Approved SABAS ALONSO
Rough-Elec/Plmb/HVAC 9/29/2022 Approved SABAS ALONSO
Drywall Nailing 10/27/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 10/27/2022 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 11/28/2022 Approved SABAS ALONSO
Shower Pan 11/28/2022 Approved SABAS ALONSO
ELECTRICAL-Final 3/7/2023 Approved STUART CHAPMAN
Final 3/7/2023 Corrections Issued STUART CHAPMAN
Green Building Final 3/7/2023 Approved STUART CHAPMAN
HVAC-Final 3/7/2023 Approved STUART CHAPMAN
PLUMBING-Final 3/7/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Approved STUART CHAPMAN
Service/Power Release 3/7/2023 Not Required STUART CHAPMAN
Smoke Detectors 3/7/2023 Approved STUART CHAPMAN
Final 4/11/2023 Corrections Issued SABAS ALONSO
Service/Power Release 4/11/2023 Not Ready for Inspection SABAS ALONSO
Final 4/25/2023 Corrections Issued SABAS ALONSO
Final 5/8/2023 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 5/8/2023 Approved ALIZAH MAYAGOITIA