1223 1/2 W 71ST ST 90044
Certificate Information: 1223 1/2 W 71ST ST 90044
- Application / Permit
- 21010-10000-01925
- Plan Check / Job No.
- B21LA07275
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU WITH ATTACHED GARAGE PER 12.22 A33 C & D
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | STARR CHEN |
| Corrections Issued | 5/9/2021 | STARR CHEN |
| Quality Review Completed | 5/14/2021 | JASON HEALEY |
| Building Plans Picked Up | 5/20/2021 | APPLICANT |
| Applicant returned to address corrections | 1/28/2022 | STARR CHEN |
| Applicant returned to address corrections | 3/31/2022 | STARR CHEN |
| Applicant returned to address corrections | 4/7/2022 | STARR CHEN |
| Plan Check Approved | 4/20/2022 | STARR CHEN |
| No Progress | 4/20/2022 | STARR CHEN |
| Plan Check Approved | 4/20/2022 | STARR CHEN |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 3/28/2023 | ENRIQUE MIRELES |
| CofO in Progress | 3/28/2023 | ENRIQUE MIRELES |
| Permit Finaled | 4/2/2023 | DEROLD HAUFF |
| CofO Issued | 4/2/2023 | DEROLD HAUFF |
| Permit Finaled | 4/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/30/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 10/7/2021 | MATTHEW CRAIG |
| Sewer availability | Cleared | 1/12/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 1/18/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 1/19/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 1/20/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mendoza,, Fabian; Lic. No.: C90183 | PO BOX 2305 NORWALK, CA 90651 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/8/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/22/2022 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/24/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/24/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 9/6/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Partial Approval | STUART CHAPMAN |
| Deputy Wood Construction | 9/16/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 9/20/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 9/20/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/26/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 9/26/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/26/2022 | Corrections Issued | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 9/27/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 9/29/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 10/7/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/11/2022 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 10/11/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 10/13/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 10/14/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/20/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/7/2022 | Approved | ENRIQUE MIRELES |
| Final | 1/9/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/9/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/9/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 1/9/2023 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/9/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/13/2023 | OK to Issue CofO | ENRIQUE MIRELES |