127 N MANSFIELD AVE 90036

Certificate Information: 127 N MANSFIELD AVE 90036

Application / Permit
21010-10000-01905
Plan Check / Job No.
B21LA07233
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONCERT (E) 2 CAR GARAGE WITH GROUND FLOOR AND 2ND STORY ADU ADDITION THAT INCLUDES A TRELLIS AND COVERED ROOF DECK PER LAMC 12.22A33(c) - (d)
Permit Issued
Issued on 12/20/2021
Issuing Office
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 KHEDER ALRAZAA
Corrections Issued 4/30/2021 KHEDER ALRAZAA
Quality Review Completed 5/6/2021 JASON HEALEY
Building Plans Picked Up 5/12/2021 APPLICANT
Applicant returned to address corrections 6/14/2021 KHEDER ALRAZAA
Applicant returned to address corrections 11/3/2021 KHEDER ALRAZAA
Plan Check Approved 12/15/2021 KHEDER ALRAZAA
Issued 12/20/2021 APPLICANT
CofO in Progress 8/30/2023 ROY SPAULDING
CofO in Progress 8/31/2023 DONALD CRICHLOW
CofO in Progress 8/31/2023 ROY SPAULDING
Permit Finaled 9/5/2023 DEROLD HAUFF
Permit Finaled 9/5/2023 DEROLD HAUFF
CofO Issued 9/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/24/2021 STEVE MELGAR
Tenant Habitability Plan Cleared 5/26/2021 MICHAEL SOTO
Eng Process Fee Ord 176,300 Cleared 6/21/2021 STEVE MELGAR
Sewer availability Cleared 6/21/2021 STEVE MELGAR
Construction within easement Cleared 8/19/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 9/18/2021 ROBERT DUFF
Low Impact Development Cleared 11/17/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/22/2021 AMAAN MALIK

Contact Information

Architect Phakos,, Cynthia; Lic. No.: C23352 9010 RANGELY AVE      WEST HOLLYWOOD, CA 90048
Contractor Zetterberg Bjorn Erik; Lic. No.: 412420-B 89 UPPER LAKE ROAD      LAKE SHERWOOD, CA 91361
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/6/2022 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 2/10/2022 Not Ready for Inspection CRAIG DAVIS
METHANE-Barrier 2/10/2022 Not Ready for Inspection CRAIG DAVIS
METHANE-Subgrade 2/10/2022 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 3/9/2022 Partial Approval ARTHUR SARGSYAN
METHANE-Barrier 3/9/2022 Partial Approval ARTHUR SARGSYAN
METHANE-Subgrade 3/9/2022 Partial Approval ARTHUR SARGSYAN
Deputy Methane Barrier 3/15/2022 Approved ARTHUR SARGSYAN
METHANE-Rough 3/16/2022 Partial Approval CRAIG DAVIS
Deputy Methane Barrier 3/17/2022 Approved ARTHUR SARGSYAN
Deputy Methane Barrier 3/18/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 3/22/2022 Not Ready for Inspection ARTHUR SARGSYAN
Drywall Nailing 3/22/2022 Not Ready for Inspection ARTHUR SARGSYAN
Final 3/22/2022 Not Ready for Inspection ARTHUR SARGSYAN
Footing/Foundation/Slab 3/22/2022 Approved ARTHUR SARGSYAN
Green Building Final 3/22/2022 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Rough 3/22/2022 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Barrier 3/22/2022 Approved ARTHUR SARGSYAN
METHANE-Final 3/22/2022 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Rough 3/22/2022 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Subgrade 3/22/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Not Ready ARTHUR SARGSYAN
Smoke Detectors 3/22/2022 Not Ready for Inspection ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Approved ARTHUR SARGSYAN
Sewer 4/27/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 6/24/2022 Not Ready for Inspection ADAM ESCOTO
PLUMBING-Rough 6/24/2022 Approved ADAM ESCOTO
Underground Mechanical 6/24/2022 Approved ADAM ESCOTO
ELECTRICAL-Rough 8/10/2022 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Partial Approval JOSEPH MCGARRY
HVAC-Rough 8/10/2022 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 8/24/2022 Corrections Issued JEFFREY MEAD
Green Building Rough 8/24/2022 Partial Approval JEFFREY MEAD
METHANE-Rough 8/24/2022 Approved JEFFREY MEAD
HVAC-Rough 9/8/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/14/2022 Approved JOSEPH MCGARRY
Green Building Rough 9/14/2022 Approved JOSEPH MCGARRY
Insulation 9/14/2022 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 9/14/2022 Partial Approval JOSEPH MCGARRY
Drywall Nailing 9/19/2022 Approved JOSEPH MCGARRY
Gas Test 9/19/2022 Approved JOSEPH MCGARRY
Green Building Rough 9/19/2022 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 12/27/2022 Approved JOSEPH MCGARRY
Final 8/17/2023 Corrections Issued STUART CHAPMAN
Green Building Final 8/17/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 8/17/2023 Approved STUART CHAPMAN
Final 8/22/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Approved LILIANA PORTILLO
ELECTRICAL-Final 8/25/2023 Approved LILIANA PORTILLO
Final 8/25/2023 Conditional Approval LILIANA PORTILLO
HVAC-Final 8/25/2023 Approved LILIANA PORTILLO
MERV13>=Final 8/25/2023 Approved LILIANA PORTILLO
PLUMBING-Final 8/25/2023 Approved LILIANA PORTILLO
Service/Power Release 8/25/2023 Approved LILIANA PORTILLO
Final 8/29/2023 OK to Issue CofO ROY SPAULDING
Service/Power Release 8/31/2023 Approved ROY SPAULDING