127 N MANSFIELD AVE 90036
Certificate Information: 127 N MANSFIELD AVE 90036
- Application / Permit
- 21010-10000-01905
- Plan Check / Job No.
- B21LA07233
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONCERT (E) 2 CAR GARAGE WITH GROUND FLOOR AND 2ND STORY ADU ADDITION THAT INCLUDES A TRELLIS AND COVERED ROOF DECK PER LAMC 12.22A33(c) - (d)
- Permit Issued
- Issued on 12/20/2021
- Issuing Office
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | KHEDER ALRAZAA |
| Corrections Issued | 4/30/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 5/6/2021 | JASON HEALEY |
| Building Plans Picked Up | 5/12/2021 | APPLICANT |
| Applicant returned to address corrections | 6/14/2021 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 11/3/2021 | KHEDER ALRAZAA |
| Plan Check Approved | 12/15/2021 | KHEDER ALRAZAA |
| Issued | 12/20/2021 | APPLICANT |
| CofO in Progress | 8/30/2023 | ROY SPAULDING |
| CofO in Progress | 8/31/2023 | DONALD CRICHLOW |
| CofO in Progress | 8/31/2023 | ROY SPAULDING |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2021 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 5/26/2021 | MICHAEL SOTO |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 6/21/2021 | STEVE MELGAR |
| Construction within easement | Cleared | 8/19/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 9/18/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 11/17/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/22/2021 | AMAAN MALIK |
Contact Information
| Architect | Phakos,, Cynthia; Lic. No.: C23352 | 9010 RANGELY AVE WEST HOLLYWOOD, CA 90048 |
| Contractor | Zetterberg Bjorn Erik; Lic. No.: 412420-B | 89 UPPER LAKE ROAD LAKE SHERWOOD, CA 91361 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/6/2022 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/10/2022 | Not Ready for Inspection | CRAIG DAVIS |
| METHANE-Barrier | 2/10/2022 | Not Ready for Inspection | CRAIG DAVIS |
| METHANE-Subgrade | 2/10/2022 | Not Ready for Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 3/9/2022 | Partial Approval | ARTHUR SARGSYAN |
| METHANE-Barrier | 3/9/2022 | Partial Approval | ARTHUR SARGSYAN |
| METHANE-Subgrade | 3/9/2022 | Partial Approval | ARTHUR SARGSYAN |
| Deputy Methane Barrier | 3/15/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 3/16/2022 | Partial Approval | CRAIG DAVIS |
| Deputy Methane Barrier | 3/17/2022 | Approved | ARTHUR SARGSYAN |
| Deputy Methane Barrier | 3/18/2022 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 3/22/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Drywall Nailing | 3/22/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 3/22/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 3/22/2022 | Approved | ARTHUR SARGSYAN |
| Green Building Final | 3/22/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 3/22/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Barrier | 3/22/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Final | 3/22/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Rough | 3/22/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Subgrade | 3/22/2022 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Not Ready | ARTHUR SARGSYAN |
| Smoke Detectors | 3/22/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2022 | Approved | ARTHUR SARGSYAN |
| Sewer | 4/27/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 6/24/2022 | Not Ready for Inspection | ADAM ESCOTO |
| PLUMBING-Rough | 6/24/2022 | Approved | ADAM ESCOTO |
| Underground Mechanical | 6/24/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Rough | 8/10/2022 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 8/10/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/24/2022 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 8/24/2022 | Partial Approval | JEFFREY MEAD |
| METHANE-Rough | 8/24/2022 | Approved | JEFFREY MEAD |
| HVAC-Rough | 9/8/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/14/2022 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 9/14/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 9/14/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/14/2022 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 9/19/2022 | Approved | JOSEPH MCGARRY |
| Gas Test | 9/19/2022 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 9/19/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/27/2022 | Approved | JOSEPH MCGARRY |
| Final | 8/17/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 8/17/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 8/17/2023 | Approved | STUART CHAPMAN |
| Final | 8/22/2023 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/25/2023 | Approved | LILIANA PORTILLO |
| Final | 8/25/2023 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Final | 8/25/2023 | Approved | LILIANA PORTILLO |
| MERV13>=Final | 8/25/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 8/25/2023 | Approved | LILIANA PORTILLO |
| Service/Power Release | 8/25/2023 | Approved | LILIANA PORTILLO |
| Final | 8/29/2023 | OK to Issue CofO | ROY SPAULDING |
| Service/Power Release | 8/31/2023 | Approved | ROY SPAULDING |