849 1/2 W DICKSON ST 90292
Certificate Information: 849 1/2 W DICKSON ST 90292
- Application / Permit
- 21010-10000-01901
- Plan Check / Job No.
- B21LA07188
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY DETACHED ADU PER LAMC 12.22A.33(c)-(d).
- Permit Issued
- Issued on 10/2/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | VIVIAN LAO |
| Corrections Issued | 5/27/2021 | VIVIAN LAO |
| Quality Review Completed | 6/3/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 6/8/2021 | APPLICANT |
| Applicant returned to address corrections | 11/3/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 11/19/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 12/2/2021 | VIVIAN LAO |
| Plan Check Approved | 8/31/2023 | VIVIAN LAO |
| Issued | 10/2/2023 | APPLICANT |
| CofO in Progress | 12/31/2024 | JESUS PINEDA |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
| CofO Issued | 12/31/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/21/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/22/2021 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 9/23/2021 | ROBERT SANCHEZ |
| Low Impact Development | Cleared | 10/18/2021 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/22/2021 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 3/4/2022 | GREGORY HOERNER |
| Miscellaneous | Cleared | 8/17/2023 | DALIA MOKAYED |
| Miscellaneous | Cleared | 8/17/2023 | DALIA MOKAYED |
| Miscellaneous | Cleared | 8/17/2023 | DALIA MOKAYED |
| Miscellaneous | Cleared | 8/17/2023 | DALIA MOKAYED |
| Specific Plan | Cleared | 8/17/2023 | DALIA MOKAYED |
| Specific Plan | Cleared | 8/17/2023 | DALIA MOKAYED |
Contact Information
| Architect | Tsai,, Melissa Hon; Lic. No.: C37802 | 1107 FAIR OAKS AVE #137 SOUTH PASADENA, CA 91030 |
| Contractor | Arrowhead Remodeling & Design Inc; Lic. No.: 935108-B | 18345 VENTURA BLVD #212 TARZANA, CA 91356 |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 10/12/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Pre-Inspection | 10/12/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 3/7/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/7/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Piling/Pier/Caisson | 3/7/2024 | Approved | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 3/15/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 3/18/2024 | Partial Approval | HERBERT GIRON |
| Deputy Steel/Welding | 3/19/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 4/12/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/9/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 5/9/2024 | Approved | HERBERT GIRON |
| Deputy Wood Construction | 5/13/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/13/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/16/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/21/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 6/3/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Drywall Nailing | 6/10/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 6/10/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 7/1/2024 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/5/2024 | Partial Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 7/5/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 7/5/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/21/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 8/21/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/21/2024 | Approved | JESUS RODRIGUEZ |
| Final | 8/21/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/21/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 8/21/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/21/2024 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 8/21/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/17/2024 | Approved | JESUS PINEDA |
| Final | 9/17/2024 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Final | 9/17/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Not Ready | JESUS PINEDA |
| Service/Power Release | 9/17/2024 | Not Required | JESUS PINEDA |
| Structural Steel Frame | 9/17/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 10/17/2024 | Approved | JESUS PINEDA |
| Final | 10/17/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 10/17/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 10/17/2024 | Approved | JESUS PINEDA |
| Final | 12/19/2024 | OK to Issue CofO | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 12/19/2024 | SGSOV Approved | JESUS PINEDA |