1130 W 41ST PL 90037

Certificate Information: 1130 W 41ST PL 90037

Application / Permit
21010-10000-01875
Plan Check / Job No.
B21LA07039
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU (1-STORY) PER ODINANCE
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 7/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 CARLOS MONTES
Corrections Issued 5/1/2021 CARLOS MONTES
Quality Review Completed 5/10/2021 WING SUEN
Applicant returned to address corrections 6/30/2021 CARLOS MONTES
Applicant returned to address corrections 10/26/2021 CARLOS MONTES
Applicant returned to address corrections 12/10/2021 CARLOS MONTES
Plan Check Approved 2/18/2022 CARLOS MONTES
Issued 3/2/2022 APPLICANT
CofO in Progress 7/10/2024 SABAS ALONSO
CofO Issued 7/10/2024 DEROLD HAUFF
Permit Finaled 7/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/26/2021 CECILIO NAVARRO
Sewer availability Cleared 5/27/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 7/23/2021 KURT CORRAL
Low Impact Development Cleared 11/12/2021 LONDY ALVARADO
Address approval Cleared 11/24/2021 CINDY QI
Roof/Waste drainage to street Cleared 12/10/2021 CINDY QI

Contact Information

Contractor Adu Guys.Com Inc The; Lic. No.: 1071442-B 512 N AVALON BLVD      WILMINGTON, CA 90744

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/7/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 3/16/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 3/23/2022 Approved SABAS ALONSO
Underground Mechanical 3/23/2022 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Partial Approval HORACE FULTZ
BUILDING-Rough-Frame 4/25/2022 Approved SABAS ALONSO
Green Building Rough 4/25/2022 Approved SABAS ALONSO
Rough-Elec/Plmb/HVAC 4/25/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 4/25/2022 Approved SABAS ALONSO
Insulation 5/3/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 5/3/2022 Corrections Issued SABAS ALONSO
Drywall Nailing 5/12/2022 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 5/12/2022 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 5/17/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 5/17/2022 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 6/2/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 6/2/2022 Approved SHAVONNE ESPINOZA
Shower Pan 6/2/2022 Approved LILIANA PORTILLO
Underground Mechanical 6/23/2022 Partial Approval SABAS ALONSO
Service/Power Release 6/30/2022 Corrections Issued SABAS ALONSO
Final 8/17/2022 Not Ready for Inspection SABAS ALONSO
Green Building Final 8/17/2022 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 8/17/2022 SGSOV Not Ready SABAS ALONSO
Service/Power Release 8/17/2022 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 8/17/2022 Approved SABAS ALONSO
Final 8/26/2022 Corrections Issued STUART CHAPMAN
Green Building Final 8/26/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/26/2022 SGSOV Not Ready STUART CHAPMAN
Service/Power Release 8/26/2022 Not Ready for Inspection STUART CHAPMAN
Final 9/12/2022 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/12/2022 SGSOV Approved SABAS ALONSO
Service/Power Release 9/12/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 8/10/2023 Approved SABAS ALONSO
Final 8/10/2023 Corrections Issued SABAS ALONSO
HVAC-Final 8/10/2023 Approved SABAS ALONSO
PLUMBING-Final 8/10/2023 Approved SABAS ALONSO
Service/Power Release 8/10/2023 Not Ready for Inspection SABAS ALONSO
Final 7/1/2024 Corrections Issued SABAS ALONSO
Final 7/9/2024 OK to Issue CofO SABAS ALONSO