1130 W 41ST PL 90037
Certificate Information: 1130 W 41ST PL 90037
- Application / Permit
- 21010-10000-01875
- Plan Check / Job No.
- B21LA07039
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU (1-STORY) PER ODINANCE
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 7/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | CARLOS MONTES |
| Corrections Issued | 5/1/2021 | CARLOS MONTES |
| Quality Review Completed | 5/10/2021 | WING SUEN |
| Applicant returned to address corrections | 6/30/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 10/26/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/10/2021 | CARLOS MONTES |
| Plan Check Approved | 2/18/2022 | CARLOS MONTES |
| Issued | 3/2/2022 | APPLICANT |
| CofO in Progress | 7/10/2024 | SABAS ALONSO |
| CofO Issued | 7/10/2024 | DEROLD HAUFF |
| Permit Finaled | 7/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 5/27/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 7/23/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 11/12/2021 | LONDY ALVARADO |
| Address approval | Cleared | 11/24/2021 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 12/10/2021 | CINDY QI |
Contact Information
| Contractor | Adu Guys.Com Inc The; Lic. No.: 1071442-B | 512 N AVALON BLVD WILMINGTON, CA 90744 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/7/2022 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 3/16/2022 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 3/23/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/23/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2022 | Partial Approval | HORACE FULTZ |
| BUILDING-Rough-Frame | 4/25/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 4/25/2022 | Approved | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 4/25/2022 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 4/25/2022 | Approved | SABAS ALONSO |
| Insulation | 5/3/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/3/2022 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 5/12/2022 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 5/12/2022 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 5/17/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/17/2022 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 6/2/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/2/2022 | Approved | SHAVONNE ESPINOZA |
| Shower Pan | 6/2/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 6/23/2022 | Partial Approval | SABAS ALONSO |
| Service/Power Release | 6/30/2022 | Corrections Issued | SABAS ALONSO |
| Final | 8/17/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 8/17/2022 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 8/17/2022 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 8/17/2022 | Approved | SABAS ALONSO |
| Final | 8/26/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 8/26/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/26/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 8/26/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 9/12/2022 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/12/2022 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 9/12/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 8/10/2023 | Approved | SABAS ALONSO |
| Final | 8/10/2023 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 8/10/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 8/10/2023 | Approved | SABAS ALONSO |
| Service/Power Release | 8/10/2023 | Not Ready for Inspection | SABAS ALONSO |
| Final | 7/1/2024 | Corrections Issued | SABAS ALONSO |
| Final | 7/9/2024 | OK to Issue CofO | SABAS ALONSO |