3836 1/2 W SENECA AVE 90039

Certificate Information: 3836 1/2 W SENECA AVE 90039

Application / Permit
21010-10000-01874
Plan Check / Job No.
B21LA07038
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 12/10/2021
Issuing Office
Current Status
CofO Issued on 4/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 CARLOS MONTES
Corrections Issued 5/22/2021 CARLOS MONTES
Quality Review Completed 6/1/2021 WING SUEN
Applicant returned to address corrections 8/18/2021 CARLOS MONTES
Applicant returned to address corrections 10/13/2021 CARLOS MONTES
Applicant returned to address corrections 10/21/2021 CARLOS MONTES
Plan Check Approved 12/3/2021 CARLOS MONTES
Issued 12/10/2021 APPLICANT
CofO in Progress 4/20/2023 CRAIG VAUGHAN
Permit Finaled 4/29/2023 DEROLD HAUFF
Permit Finaled 4/29/2023 DEROLD HAUFF
CofO Issued 4/29/2023 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 6/14/2021 TERRI OSBORNE
Address approval Cleared 6/15/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/17/2021 STEVE MELGAR
Sewer availability Cleared 6/17/2021 STEVE MELGAR
Hydrant and Access approval Cleared 8/27/2021 GILBERT URREA
Low Impact Development Cleared 9/27/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/8/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Engineer Phillips,, Craig Richard; Lic. No.: NA69673       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/22/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 1/10/2022 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/26/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/7/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/26/2022 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 8/26/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/9/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 9/16/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/22/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 9/22/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/22/2022 Partial Approval HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 9/22/2022 Approved HAMIK HARTOUNIAN
Insulation 9/29/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 10/13/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/13/2022 Partial Approval HAMIK HARTOUNIAN
Gas Test 12/30/2022 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 12/30/2022 Partial Inspection HAMIK HARTOUNIAN
Gas Test 1/27/2023 Approved HAMIK HARTOUNIAN
Final 3/1/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 3/1/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 3/1/2023 Not Required HAMIK HARTOUNIAN
Smoke Detectors 3/1/2023 Approved HAMIK HARTOUNIAN
Final 3/6/2023 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/6/2023 SGSOV Approved HAMIK HARTOUNIAN
Final 4/5/2023 Partial Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 4/19/2023 Approved CRAIG VAUGHAN
Final 4/19/2023 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 4/19/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 4/19/2023 Approved CRAIG VAUGHAN
Service/Power Release 4/19/2023 Approved CRAIG VAUGHAN