10218 N STANWIN AVE 91331

Certificate Information: 10218 N STANWIN AVE 91331

Application / Permit
21010-10000-01871
Plan Check / Job No.
B21LA07035
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU conversion. CONVERT EXISTING 1 STORY DETACHED RECREATION ROOM TO 1 STORY DETACHED ADU PER PER GCS 65852.2(e)(1)(A) AND PER WFPP
Permit Issued
Issued on 5/20/2021
Issuing Office
Current Status
CofO Issued on 10/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/19/2021 CRYSTEL MAALOUF
Corrections Issued 4/19/2021 CRYSTEL MAALOUF
Plan Check Approved 5/11/2021 CRYSTEL MAALOUF
Issued 5/20/2021 APPLICANT
CofO in Progress 10/27/2021 THOMAS WOODS
Permit Finaled 10/28/2021 DAVID JAMES
CofO Issued 10/28/2021 DAVID JAMES
Permit Finaled 10/28/2021 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 4/22/2021 ADRIAN CASTRO
Sewer availability Cleared 4/22/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/23/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/10/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/17/2021 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 6/17/2021 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 6/17/2021 Approved MICKEY YAMASHITA
PLUMBING-Rough 6/17/2021 Corrections Issued MICKEY YAMASHITA
Sewer 6/17/2021 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 7/6/2021 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 7/6/2021 Approved MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Approved MICKEY YAMASHITA
Green Building Rough 7/6/2021 Corrections Issued MICKEY YAMASHITA
Interior/Exterior Lathing 7/6/2021 Partial Approval MICKEY YAMASHITA
METHANE-Rough 7/6/2021 Approved MICKEY YAMASHITA
PLUMBING-Rough 7/6/2021 Approved MICKEY YAMASHITA
Sewer 7/6/2021 Approved MICKEY YAMASHITA
Underground Mechanical 7/6/2021 Approved MICKEY YAMASHITA
BUILDING-Rough-Frame 9/7/2021 No Access for Inspection MICKEY YAMASHITA
Green Building Rough 9/7/2021 No Access for Inspection MICKEY YAMASHITA
BUILDING-Rough-Frame 9/14/2021 Partial Approval THOMAS WOODS
Green Building Rough 9/14/2021 Not Ready for Inspection THOMAS WOODS
Drywall Nailing 10/14/2021 Approved THOMAS WOODS
Interior/Exterior Lathing 10/14/2021 Partial Approval THOMAS WOODS
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Approved THOMAS WOODS
Sewer 10/14/2021 Approved THOMAS WOODS
Shower Pan 10/14/2021 Approved THOMAS WOODS
BUILDING-Rough-Frame 10/27/2021 Approved THOMAS WOODS
ELECTRICAL-Final 10/27/2021 Approved THOMAS WOODS
Final 10/27/2021 OK to Issue CofO THOMAS WOODS
Gas Test 10/27/2021 Approved THOMAS WOODS
Green Building Final 10/27/2021 Approved THOMAS WOODS
Green Building Rough 10/27/2021 Approved THOMAS WOODS
HVAC-Final 10/27/2021 Approved THOMAS WOODS
HVAC-Rough 10/27/2021 Approved THOMAS WOODS
Insulation 10/27/2021 Approved THOMAS WOODS
PLUMBING-Final 10/27/2021 Approved THOMAS WOODS
Smoke Detectors 10/27/2021 Approved THOMAS WOODS