18333 W GAULT ST 91335
Certificate Information: 18333 W GAULT ST 91335
- Application / Permit
- 21010-10000-01857
- Plan Check / Job No.
- B21LA06961
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW TRASH ENCLOSURE
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 2/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | ERIC WONG |
| Disabled Access Plans Picked Up | 5/10/2021 | APPLICANT |
| Corrections Issued | 5/19/2021 | ERIC WONG |
| Quality Review Completed | 5/24/2021 | PETER KIM |
| Building Plans Picked Up | 6/1/2021 | APPLICANT |
| Applicant returned to address corrections | 8/18/2021 | ERIC WONG |
| Plan Check Approved | 4/8/2022 | ERIC WONG |
| Issued | 4/26/2022 | APPLICANT |
| CofO in Progress | 2/14/2024 | DEANDRE HOFFMAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 1/25/2022 | SHINE LIN |
Contact Information
| Architect | Vakili,, Shabnam; Lic. No.: C26298 | KSP STUDIO 23 ORCHARD STE 200 LAKE FOREST, CA 92630 |
| Contractor | Dai General Contracting; Lic. No.: 861151-B | 26181 AVENIDA AEROPUERTO UNIT A SAN JUAN CAPISTRANO, CA 92675 |
| Engineer | Shakerin,, Kayvon; Lic. No.: C46202 | 23 ORCHARD ROAD STE 200 LAKE FOREST, CA 92630 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Masonry | 9/7/2023 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 9/8/2023 | Conditional Approval | CAMERON CHABAN |
| Final | 10/13/2023 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 10/13/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Final | 10/13/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 10/13/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/13/2023 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 10/13/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/13/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 10/13/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 11/17/2023 | Partial Inspection | CAMERON CHABAN |
| Footing/Foundation/Slab | 11/17/2023 | Approved | CAMERON CHABAN |
| Green Building Final | 11/17/2023 | Approved | CAMERON CHABAN |
| Green Building Rough | 11/17/2023 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2023 | SGSOV No Gas | CAMERON CHABAN |
| Smoke Detectors | 11/17/2023 | Approved | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 11/17/2023 | Approved | CAMERON CHABAN |
| Wood Frame | 11/17/2023 | Approved | CAMERON CHABAN |
| Final | 2/13/2024 | OK to Issue CofO | DEANDRE HOFFMAN |