18333 W GAULT ST 91335

Certificate Information: 18333 W GAULT ST 91335

Application / Permit
21010-10000-01856
Plan Check / Job No.
B21LA06961
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Storage Building
Work Description
NEW THREE-STORY TYPE II-B SELF STORAGE BUILDING
Permit Issued
Issued on 4/26/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 ERIC WONG
Disabled Access Plans Picked Up 5/10/2021 APPLICANT
Corrections Issued 5/19/2021 ERIC WONG
Quality Review Completed 5/24/2021 PETER KIM
Building Plans Picked Up 6/1/2021 APPLICANT
Applicant returned to address corrections 8/18/2021 ERIC WONG
Plan Check Approved 4/8/2022 ERIC WONG
Issued 4/26/2022 APPLICANT
TCO Issued (Expire Date: 05-11-2024) 11/13/2023 RICKEY JACKSON
CofO in Progress 2/15/2024 DEANDRE HOFFMAN
CofO Issued 2/27/2024 RICKEY JACKSON
Permit Finaled 2/27/2024 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 7/28/2021 CARLOS AGUILERA
Permit Cleared 7/28/2021 CARLOS AGUILERA
Sewer availability Cleared 7/29/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/31/2021 CARLOS AGUILERA
Comm Cor/Mini-Mall Cleared 10/20/2021 ANACANY HURTADO
Site Plan review Cleared 10/20/2021 ANACANY HURTADO
Building over 36-ft Cleared 10/29/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/29/2021 CALOSHA APPROVED
Low Impact Development Cleared 11/15/2021 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 11/17/2021 CARLOS AGUILERA
Green Code Cleared 1/4/2022 ERIC WONG
DAS Clearance Cleared 1/25/2022 SHINE LIN
Comm Cor/Mini-Mall Cleared 2/4/2022 ANACANY HURTADO
Prkng lot landscape/Water mgmt Cleared 2/4/2022 ANACANY HURTADO
ZA Case Cleared 2/4/2022 ANACANY HURTADO
Hydrant and Access approval Cleared 2/8/2022 KURT CORRAL
Highway dedication Cleared 3/2/2022 CARLOS AGUILERA

Contact Information

Architect Vakili,, Shabnam; Lic. No.: C26298 KSP STUDIO   23 ORCHARD STE 200    LAKE FOREST, CA 92630
Contractor Dai General Contracting; Lic. No.: 861151-B 26181 AVENIDA AEROPUERTO UNIT   A    SAN JUAN CAPISTRANO, CA 92675
Engineer Arriola,, Kirby Norman; Lic. No.: C31416 PO BOX 5566      OXNARD, CA 93031
Engineer Blunck,, Jerome Jon; Lic. No.: GE151 3595 OLD CONEJO ROAD      THOUSAND OAKS, CA 91320
Engineer Shakerin,, Kayvon; Lic. No.: C46202 23 ORCHARD ROAD STE 200      LAKE FOREST, CA 92630
Landscape Architect Freeman,, Eric Christopher; Lic. No.: LA6245 20182 E FRANK LN      ORANGE, CA 92869

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 6/28/2022 Conditional Approval JEFFREY DURAN
Pre-Inspection 6/28/2022 Partial Inspection CAMERON CHABAN
Deputy Reinf. Concrete 6/29/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/6/2022 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 7/15/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/19/2022 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Masonry 7/21/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 7/22/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 7/25/2022 Conditional Approval CAMERON CHABAN
Green Building Rough 7/25/2022 Partial Inspection CAMERON CHABAN
Reinforced Masonry Frame 7/25/2022 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 7/25/2022 Partial Inspection CAMERON CHABAN
Deputy Reinf. Masonry 7/26/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/27/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 7/28/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/29/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 7/29/2022 Conditional Approval CAMERON CHABAN
Reinforced Concrete Frame 7/29/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/1/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/2/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/3/2022 Conditional Approval CAMERON CHABAN
Green Building Rough 8/3/2022 Partial Inspection CAMERON CHABAN
Masonry Wall/Backfill 8/3/2022 Conditional Approval CAMERON CHABAN
Verify Sprinkler Sign Off 8/3/2022 Partial Inspection CAMERON CHABAN
Deputy Reinf. Masonry 8/4/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/5/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/8/2022 Conditional Approval CAMERON CHABAN
Green Building Rough 8/8/2022 Not Ready for Inspection CAMERON CHABAN
Masonry Wall/Backfill 8/8/2022 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 8/8/2022 Not Ready for Inspection CAMERON CHABAN
Deputy Reinf. Masonry 8/9/2022 Conditional Approval CAMERON CHABAN
Deputy Drilled-In Anchors 8/10/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/10/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 8/11/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/11/2022 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 8/11/2022 Partial Approval CAMERON CHABAN
Green Building Rough 8/11/2022 Not Ready for Inspection CAMERON CHABAN
Reinforced Masonry Frame 8/11/2022 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 8/11/2022 Not Ready for Inspection CAMERON CHABAN
Deputy Methane Barrier 8/12/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 8/12/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/12/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/16/2022 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Masonry 8/17/2022 Conditional Approval JEFFREY DURAN
Green Building Rough 8/17/2022 Not Ready for Inspection CAMERON CHABAN
Masonry Wall/Backfill 8/17/2022 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 8/17/2022 Not Ready for Inspection CAMERON CHABAN
Deputy Reinf. Masonry 8/18/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/19/2022 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 9/12/2022 Not Ready for Inspection CAMERON CHABAN
Footing/Foundation/Slab 9/16/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 9/20/2022 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 9/20/2022 Conditional Approval BRUCE CAMPBELL
Deputy Reinf. Masonry 9/21/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/22/2022 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 9/22/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 9/23/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/27/2022 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 9/27/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 9/28/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 9/29/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 9/30/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/3/2022 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 10/3/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/4/2022 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 10/4/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/5/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/6/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/7/2022 Conditional Approval CAMERON CHABAN
Deputy Drilled-In Anchors 10/11/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/11/2022 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 10/11/2022 Partial Approval CAMERON CHABAN
Deputy Drilled-In Anchors 10/12/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/12/2022 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 10/12/2022 Conditional Approval CAMERON CHABAN
Deputy Drilled-In Anchors 10/13/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/13/2022 Conditional Approval CAMERON CHABAN
Deputy Drilled-In Anchors 10/14/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/14/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/17/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 10/18/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/19/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/20/2022 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 10/20/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/21/2022 Conditional Approval CAMERON CHABAN
Deputy Drilled-In Anchors 10/26/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 10/26/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/26/2022 Conditional Approval CAMERON CHABAN
Deputy Drilled-In Anchors 10/27/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/27/2022 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 10/27/2022 Corrections Issued JEFFREY DURAN
Deputy Drilled-In Anchors 10/28/2022 Conditional Approval ROBERT DAVIS
Deputy Reinf. Masonry 10/28/2022 Conditional Approval ROBERT DAVIS
Masonry Wall/Backfill 10/28/2022 Not Ready for Inspection ROBERT DAVIS
Structural Steel Frame 10/28/2022 Approved ROBERT DAVIS
Structural Steel Frame 10/29/2022 No Result Entered GARY EWELL
Deputy Other (see comments) 10/31/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/31/2022 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 11/10/2022 Not Ready for Inspection CAMERON CHABAN
Masonry Wall/Backfill 11/10/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 11/15/2022 Partial Approval CAMERON CHABAN
Masonry Wall/Backfill 11/15/2022 Not Ready for Inspection CAMERON CHABAN
Deputy Reinf. Masonry 11/16/2022 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 11/16/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 11/17/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 11/18/2022 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 11/21/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 11/22/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 11/23/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 11/28/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 11/29/2022 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 11/29/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 11/30/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/6/2022 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 12/6/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/7/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/8/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/9/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/12/2022 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Masonry 12/13/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/14/2022 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/15/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/16/2022 Approved CAMERON CHABAN
Footing/Foundation/Slab 12/16/2022 Partial Approval CAMERON CHABAN
Structural Steel Frame 12/16/2022 Partial Inspection CAMERON CHABAN
Deputy Reinf. Masonry 12/27/2022 Conditional Approval ANDREW DORSO
Deputy Reinf. Masonry 12/28/2022 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 12/28/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/29/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/30/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 1/3/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 1/4/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 1/5/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 1/6/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 1/12/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 1/13/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 1/17/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 1/18/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 1/19/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 1/20/2023 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 1/20/2023 Corrections Issued DANNY RODRIGUEZ
Special/Order Compliance 1/20/2023 Approved BRIAN KELLY
Masonry Wall/Backfill 1/24/2023 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 2/14/2023 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 2/16/2023 Conditional Approval CAMERON CHABAN
Grading Pre-Inspection 2/23/2023 Partial Inspection CAMERON CHABAN
Deputy Steel/Welding 3/7/2023 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 4/18/2023 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 4/24/2023 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 4/26/2023 Conditional Approval CAMERON CHABAN
Light Gage Steel Frame 4/27/2023 Partial Approval CAMERON CHABAN
Deputy Steel/Welding 5/1/2023 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 5/2/2023 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 5/2/2023 Partial Approval CAMERON CHABAN
Drywall Nailing 5/18/2023 Partial Approval CAMERON CHABAN
Insulation 5/19/2023 Partial Approval CAMERON CHABAN
Drywall Nailing 5/23/2023 Approved KENNETH ROBERTS
Interior/Exterior Lathing 7/12/2023 Not Ready for Inspection CAMERON CHABAN
Interior/Exterior Lathing 7/20/2023 Approved CAMERON CHABAN
Footing/Foundation/Slab 8/21/2023 Not Ready for Inspection CAMERON CHABAN
Footing/Foundation/Slab 8/30/2023 Not Ready for Inspection CAMERON CHABAN
Footing/Foundation/Slab 9/21/2023 Partial Inspection DANIEL VARNUM
Final 9/26/2023 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 9/26/2023 Approved CAMERON CHABAN
Green Building Final 9/26/2023 Partial Inspection CAMERON CHABAN
Green Building Rough 9/26/2023 Approved CAMERON CHABAN
Reinforced Masonry Frame 9/26/2023 Conditional Approval CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV No Gas CAMERON CHABAN
Smoke Detectors 9/26/2023 Approved CAMERON CHABAN
Verify Sprinkler Sign Off 9/26/2023 Partial Inspection CAMERON CHABAN
Masonry Wall/Backfill 10/10/2023 Approved CAMERON CHABAN
Final 10/26/2023 Partial Inspection CAMERON CHABAN
Green Building Final 10/26/2023 Partial Inspection CAMERON CHABAN
Reinforced Masonry Frame 10/26/2023 Conditional Approval CAMERON CHABAN
Verify Sprinkler Sign Off 10/26/2023 Partial Inspection CAMERON CHABAN
Drywall Nailing 11/9/2023 Partial Inspection CAMERON CHABAN
Final 11/13/2023 OK for TCO CAMERON CHABAN
Green Building Final 11/13/2023 Approved CAMERON CHABAN
Reinforced Masonry Frame 11/13/2023 Approved CAMERON CHABAN
Verify Sprinkler Sign Off 11/13/2023 Approved CAMERON CHABAN
Final 2/13/2024 OK to Issue CofO DEANDRE HOFFMAN