14674 1/2 W REX ST 91342
Certificate Information: 14674 1/2 W REX ST 91342
- Application / Permit
- 21010-10000-01848
- Plan Check / Job No.
- B21LA06895
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: New detached 2-story ADU with attached 2-car garage per ordinance.
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | MICHAEL LOPEZ |
| Corrections Issued | 5/28/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 6/6/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/4/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 1/5/2022 | MICHAEL LOPEZ |
| Issued | 1/24/2022 | APPLICANT |
| CofO in Progress | 2/10/2023 | MICHEL ABAJAN |
| CofO Issued | 2/14/2023 | MICHAEL SMITH |
| Permit Finaled | 2/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/14/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 8/19/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/28/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/28/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong Lap; Lic. No.: NA70784 | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/14/2022 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 2/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 2/22/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 2/28/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 2/28/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 2/28/2022 | Approved | JOHN HAYES |
| Underground Mechanical | 2/28/2022 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 3/3/2022 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 3/3/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 3/21/2022 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/22/2022 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 4/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 4/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 4/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Deputy Wood Construction | 6/24/2022 | No Result Entered | KENNETH KUROWSKI |
| BUILDING-Rough-Frame | 7/1/2022 | Corrections Issued | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 7/1/2022 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 7/1/2022 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 7/1/2022 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 7/20/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/3/2022 | Not Ready for Inspection | ROBERT GOLD |
| Green Building Rough | 8/3/2022 | Not Ready for Inspection | ROBERT GOLD |
| Interior/Exterior Lathing | 8/15/2022 | Conditional Approval | WILLIAM WREN |
| Special/Order Compliance | 8/31/2022 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 9/7/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/7/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 9/13/2022 | Approved | ARAM AVEDISIAN |
| Shower Pan | 9/16/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 9/19/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 11/30/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 11/30/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/30/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 11/30/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 2/10/2023 | Approved | MICHEL ABAJAN |
| Final | 2/10/2023 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 2/10/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 2/10/2023 | Approved | MICHEL ABAJAN |