809 N CHEROKEE AVE 90038
Certificate Information: 809 N CHEROKEE AVE 90038
- Application / Permit
- 21010-10000-01834
- Plan Check / Job No.
- B21LA06849
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3-Story Duplex w/Attached 2-Car Garage Each and Attached ADU 2 OF 2
- Permit Issued
- Issued on 9/23/2021
- Issuing Office
- Current Status
- CofO Issued on 10/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | DAVID CASTILLO |
| Corrections Issued | 4/26/2021 | DAVID CASTILLO |
| Quality Review Completed | 5/10/2021 | TARIK SAOUD |
| Plan Check Approved | 8/19/2021 | DAVID CASTILLO |
| Issued | 9/23/2021 | APPLICANT |
| Building Plans Picked Up | 6/30/2022 | APPLICANT |
| CofO in Progress | 8/29/2022 | BRIAN SULLIVAN |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
| CofO Issued | 10/1/2022 | DEROLD HAUFF |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2021 | WALLIE JONG |
| Sewer availability | Cleared | 7/1/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 7/15/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/4/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/10/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | WALLIE JONG |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Geologist | Siskowic,, John Gary; Lic. No.: GEO8255 | 515 S CATALINA AVE APT A REDONDO BEACH, CA 90277 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/1/2021 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 11/4/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 11/17/2021 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 11/17/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Barrier | 11/17/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Subgrade | 11/17/2021 | Approved | BRIAN SULLIVAN |
| Deputy Wood Construction | 12/2/2021 | Conditional Approval | ROBERT CORNELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Partial Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 12/8/2021 | Conditional Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2022 | Partial Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 1/6/2022 | Partial Approval | RUBEN SALAS |
| BUILDING-Rough-Frame | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Drywall Nailing | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Final | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Final | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Final | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| METHANE-Final | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| METHANE-Rough | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 1/7/2022 | SGSOV Not Ready | BRIAN SULLIVAN |
| Service/Power Release | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Smoke Detectors | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 1/10/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 1/10/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 1/10/2022 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 1/11/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 1/11/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 1/19/2022 | Corrections Issued | BRIAN SULLIVAN |
| Shower Pan | 1/19/2022 | Partial Approval | BRIAN SULLIVAN |
| Insulation | 1/20/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Wood Construction | 1/24/2022 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 1/24/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/1/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 2/1/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 2/1/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 2/1/2022 | Partial Approval | BRIAN SULLIVAN |
| METHANE-Rough | 2/1/2022 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 2/1/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 2/7/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 2/11/2022 | Approved | BRIAN SULLIVAN |
| Underground Mechanical | 4/25/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 5/31/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/31/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/31/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 6/9/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 6/9/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 6/9/2022 | Approved | BRIAN SULLIVAN |
| Final | 7/6/2022 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 7/6/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 7/6/2022 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 7/6/2022 | Approved | BRIAN SULLIVAN |
| Final | 8/29/2022 | OK to Issue CofO | BRIAN SULLIVAN |