807-807 1/2 N CHEROKEE AVE 90038

Certificate Information: 807-807 1/2 N CHEROKEE AVE 90038

Application / Permit
21010-10000-01833
Plan Check / Job No.
B21LA06849
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-Story Duplex w/Attached 2-Car Garage Each 1 OF 2
Permit Issued
Issued on 9/23/2021
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 DAVID CASTILLO
Corrections Issued 4/26/2021 DAVID CASTILLO
Quality Review Completed 5/10/2021 TARIK SAOUD
Plan Check Approved 8/19/2021 DAVID CASTILLO
Issued 9/23/2021 APPLICANT
Building Plans Picked Up 6/30/2022 APPLICANT
CofO in Progress 8/29/2022 BRIAN SULLIVAN
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/19/2021 WALLIE JONG
Sewer availability Cleared 7/1/2021 RENZ SORIANO
Hydrant and Access approval Cleared 7/15/2021 MATTHEW CRAIG
Low Impact Development Cleared 8/4/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 8/10/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/11/2021 WALLIE JONG

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Geologist Siskowic,, John Gary; Lic. No.: GEO8255 515 S CATALINA AVE APT A      REDONDO BEACH, CA 90277

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/1/2021 Partial Approval RAUL BARAJAS
Underground Mechanical 11/4/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 11/17/2021 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 11/17/2021 Approved BRIAN SULLIVAN
METHANE-Barrier 11/17/2021 Approved BRIAN SULLIVAN
METHANE-Subgrade 11/17/2021 Approved BRIAN SULLIVAN
Deputy Reinf. Concrete 11/18/2021 Conditional Approval ROBERT CORNELL
Deputy Steel/Welding 11/24/2021 Conditional Approval ROBERT CORNELL
Deputy Wood Construction 12/20/2021 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Partial Approval BRIAN SULLIVAN
Deputy Wood Construction 12/27/2021 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 12/27/2021 Conditional Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 1/5/2022 Partial Approval BRIAN SULLIVAN
Deputy Wood Construction 1/6/2022 Partial Approval RUBEN SALAS
PLUMBING-Rough 1/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/31/2022 Approved BRIAN SULLIVAN
HVAC-Rough 1/31/2022 Approved BRIAN SULLIVAN
PLUMBING-Rough 1/31/2022 Approved BRIAN SULLIVAN
Wood Frame 1/31/2022 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 2/4/2022 Conditional Approval BRIAN SULLIVAN
Deputy Wood Construction 2/4/2022 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 2/11/2022 Not Ready for Inspection BRIAN SULLIVAN
Shower Pan 2/11/2022 Approved BRIAN SULLIVAN
Insulation 2/16/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 2/16/2022 Not Ready for Inspection BRIAN SULLIVAN
Drywall Nailing 2/22/2022 Approved BRIAN SULLIVAN
Green Building Rough 2/22/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 2/24/2022 Approved ALIZAH MAYAGOITIA
Underground Mechanical 4/25/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 5/31/2022 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Final 5/31/2022 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 5/31/2022 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Final 6/9/2022 Approved BRIAN SULLIVAN
HVAC-Final 6/9/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 6/9/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 7/6/2022 Approved BRIAN SULLIVAN
Final 7/6/2022 Corrections Issued BRIAN SULLIVAN
Green Building Final 7/6/2022 Approved BRIAN SULLIVAN
METHANE-Final 7/6/2022 Approved BRIAN SULLIVAN
METHANE-Rough 7/6/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 7/6/2022 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 7/6/2022 Approved BRIAN SULLIVAN
Smoke Detectors 7/6/2022 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 7/6/2022 Approved BRIAN SULLIVAN
Final 8/29/2022 OK to Issue CofO BRIAN SULLIVAN