11100 W PEORIA ST 91352

Certificate Information: 11100 W PEORIA ST 91352

Application / Permit
21010-10000-01829
Plan Check / Job No.
B21LA06831
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Sound Stage
Work Description
NEW 4 STORY MOTIION PICTURE & SOUND STAGE & OFFICE BUILDING. ( BUILDING #1)
Permit Issued
Issued on 5/17/2022
Issuing Office
Metro
Current Status
CofO Corrected on 9/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 GARO TELMI
Corrections Issued 5/5/2021 GARO TELMI
Quality Review Completed 5/12/2021 MICHAEL PEREZ
Building Plans Picked Up 5/14/2021 APPLICANT
Applicant returned to address corrections 7/29/2021 GARO TELMI
Applicant returned to address corrections 8/17/2021 GARO TELMI
Applicant returned to address corrections 8/23/2021 GARO TELMI
Applicant returned to address corrections 8/24/2021 GARO TELMI
Applicant returned to address corrections 11/15/2021 GARO TELMI
Applicant returned to address corrections 12/13/2021 GARO TELMI
Applicant returned to address corrections 4/29/2022 GARO TELMI
Plan Check Approved 5/11/2022 GARO TELMI
Plan Check Approved 5/17/2022 MICHAEL IRIGOYEN
Issued 5/17/2022 APPLICANT
TCO Issued (Expire Date: 10-15-2024) 4/18/2024 RICKEY JACKSON
TCO Issued (Expire Date: 04-09-2025) 10/11/2024 JEFFREY DURAN
CofO in Progress 12/17/2024 DANNY RODRIGUEZ
CofO Issued-Status Void 12/19/2024 RICKEY JACKSON
Permit Finaled-Status Void 12/19/2024 RICKEY JACKSON
Re-Activate Permit 9/4/2025 RICKEY JACKSON
Permit Finaled 9/4/2025 RICKEY JACKSON
CofO Corrected 9/4/2025 RICKEY JACKSON
Permit Finaled 9/4/2025 RICKEY JACKSON

Permit Application Clearance Information

Internal circulation Cleared 5/11/2021 DURRE SHAMSI
Address approval Cleared 5/13/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/13/2021 LEE GUILBEAUX
Flood clearance Cleared 6/22/2021 BRYAN GATHUKA
Drainage to Storm Drain Cleared 7/8/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/8/2021 LEE GUILBEAUX
Construction within easement Cleared 7/21/2021 RIDWAN HARDY
Stormwater Pollution Mitigatn Cleared 8/6/2021 ORVAL HERNANDEZ-MARCI
Permit Cleared 8/24/2021 LEE GUILBEAUX
Sewer availability Cleared 8/24/2021 LEE GUILBEAUX
Trees in Parkway Cleared 9/21/2021 ADRIAN SANCHEZ
Clean Up Green Up Cleared 9/23/2021 ANNA VIDAL
ZA Case Cleared 9/23/2021 ANNA VIDAL
ZA Case Cleared 9/23/2021 ANNA VIDAL
ZI Cleared 9/23/2021 ANNA VIDAL
Low Impact Development Cleared 9/27/2021 ORVAL HERNANDEZ-MARCI
Transportation Demand Ord. Cleared 9/28/2021 DURRE SHAMSI
Haul Route Cleared 10/1/2021 VERONICA LOPEZ
Highway dedication Cleared 11/30/2021 LEE GUILBEAUX
Hydrant and Access approval Cleared 2/24/2022 MATTHEW CRAIG
Green Code Cleared 3/4/2022 GARO TELMI
Fire Marshal Fire Life Safety Cleared 3/24/2022 VIDAL GARCIA
Motion picture studio Cleared 3/24/2022 VIDAL GARCIA
DAS Clearance Cleared 4/11/2022 GARO TELMI
CPC Cleared 4/21/2022 ANNA VIDAL
Frnt yard landscape/Water mgmt Cleared 4/21/2022 ANNA VIDAL
Miscellaneous Cleared 4/21/2022 ANNA VIDAL
Miscellaneous Cleared 4/21/2022 ANNA VIDAL
Miscellaneous Cleared 4/21/2022 ANNA VIDAL
Prkng lot landscape/Water mgmt Cleared 4/21/2022 ANNA VIDAL
Site Plan review Cleared 4/21/2022 ANNA VIDAL
Building over 36-ft Cleared 5/11/2022 CALOSHA APPROVED

Contact Information

Architect Bastien,, Gary L; Lic. No.: C11164 15661 RED HILL AVENUE SUITE 150      TUSTIN, CA 92780
Contractor Snyder Langston Llc; Lic. No.: 1019188-B 17962 COWAN      IRVINE, CA 92614
Engineer Benson,, Thomas Clifford; Lic. No.: GE2091 645 W LA CROSSE ST      GLENDORA, CA 91741
Engineer Cocke,, David Winbern; Lic. No.: S3005 19210 S VERMONT AVENUE BLDNG B SUITE 210      GARDENA, CA 90248
Engineer Rieke,, Axel Dieter; Lic. No.: C71407 2900 22ND ST 13      SAN FRANCISCO, CA 94110
Engineer Vandervis,, Jacob; Lic. No.: C46301 701 NORTH PARKCENTER DR      SANTA ANA, CA 92705

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/19/2022 Partial Approval DANNY RODRIGUEZ
METHANE-Barrier 5/19/2022 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Subgrade 5/19/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 6/3/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/3/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 6/3/2022 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 6/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 6/8/2022 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 6/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 6/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Barrier 6/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Subgrade 6/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 6/15/2022 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 6/21/2022 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 6/22/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Other (see comments) 6/23/2022 Approved DANNY RODRIGUEZ
Deputy Other (see comments) 6/29/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 6/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Barrier 6/29/2022 Approved DANNY RODRIGUEZ
METHANE-Subgrade 6/29/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/6/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/15/2022 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 7/15/2022 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 7/18/2022 Conditional Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 7/20/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/21/2022 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 7/22/2022 Partial Inspection GREGORY POMISH
Insulation 7/27/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/29/2022 Approved DANNY RODRIGUEZ
Insulation 8/2/2022 Partial Inspection DANNY RODRIGUEZ
Insulation 8/3/2022 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/5/2022 Conditional Approval DANNY RODRIGUEZ
Structural Steel Frame 8/10/2022 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/11/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 8/12/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 8/15/2022 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 8/15/2022 Partial Approval GREGORY POMISH
Insulation 8/15/2022 Partial Approval GREGORY POMISH
Structural Steel Frame 8/15/2022 Partial Inspection GREGORY POMISH
Insulation 8/22/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/29/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/31/2022 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 9/1/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/2/2022 Approved DANNY RODRIGUEZ
Deputy Wood Construction 9/2/2022 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/20/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/22/2022 Approved DANNY RODRIGUEZ
Structural Steel Frame 9/26/2022 Not Ready for Inspection ANDREW DORSO
Structural Steel Frame 9/28/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 9/29/2022 Partial Approval DANNY RODRIGUEZ
Structural Steel Frame 9/29/2022 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/4/2022 Partial Approval DANNY RODRIGUEZ
Structural Steel Frame 10/4/2022 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/5/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/6/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/11/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 10/11/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/12/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/14/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 10/17/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/19/2022 Approved DANNY RODRIGUEZ
Wood Frame 10/24/2022 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/25/2022 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/25/2022 Corrections Issued DANNY RODRIGUEZ
Wood Frame 10/26/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 10/27/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/28/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 11/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 11/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Partial Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 11/10/2022 Approved DANNY RODRIGUEZ
Wood Frame 11/10/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 11/14/2022 Partial Inspection DANNY RODRIGUEZ
Wall Anchors 11/16/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/18/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 11/21/2022 Partial Inspection DANNY RODRIGUEZ
METHANE-Rough 11/21/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/22/2022 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 11/22/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/23/2022 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 11/23/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/29/2022 Conditional Approval JEFFREY DURAN
Light Gage Steel Frame 11/29/2022 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 11/29/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 12/2/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/5/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/6/2022 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/7/2022 Approved DANNY RODRIGUEZ
Drywall Nailing 12/7/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/8/2022 Conditional Approval DANNY RODRIGUEZ
Insulation 12/9/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/12/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Wood Construction 12/12/2022 Approved DANNY RODRIGUEZ
Deputy Wood Construction 12/13/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/14/2022 Approved DANNY RODRIGUEZ
Deputy Wood Construction 12/14/2022 Approved DANNY RODRIGUEZ
Deputy Wood Construction 12/15/2022 Approved DANNY RODRIGUEZ
Wood Frame 12/15/2022 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/16/2022 Approved DANNY RODRIGUEZ
Deputy Wood Construction 12/16/2022 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 12/19/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/21/2022 Conditional Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 12/22/2022 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 12/23/2022 Partial Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 12/23/2022 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 12/27/2022 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 12/28/2022 Conditional Approval ANDREW DORSO
Insulation 12/28/2022 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 12/29/2022 Conditional Approval BRUCE CAMPBELL
Deputy Reinf. Concrete 12/30/2022 Conditional Approval ANDREW DORSO
Drywall Nailing 12/30/2022 Partial Inspection ANDREW DORSO
Drywall Nailing 1/3/2023 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 1/4/2023 Conditional Approval DANIEL VARNUM
Drywall Nailing 1/4/2023 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 1/13/2023 Conditional Approval DANIEL VARNUM
Light Gage Steel Frame 1/13/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 1/18/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 1/23/2023 Partial Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 1/25/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/26/2023 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 1/31/2023 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 1/31/2023 Partial Approval STEVEN LEVITT
Deputy Reinf. Concrete 2/1/2023 Conditional Approval DANNY RODRIGUEZ
Special/Order Compliance 2/1/2023 Conditional Approval STEVEN LEVITT
Deputy Reinf. Concrete 2/3/2023 Approved DANNY RODRIGUEZ
Drywall Nailing 2/3/2023 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 2/3/2023 Partial Approval STEVEN LEVITT
Deputy Reinf. Concrete 2/6/2023 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 2/6/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/7/2023 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 2/7/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/9/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/10/2023 Conditional Approval ANDREW DORSO
Insulation 2/10/2023 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 2/10/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 2/14/2023 Partial Approval DANNY RODRIGUEZ
Insulation 2/14/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 2/14/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/15/2023 Approved DANNY RODRIGUEZ
Drywall Nailing 2/16/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 2/16/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/17/2023 Conditional Approval DANIEL VARNUM
Drywall Nailing 2/17/2023 Partial Approval DANIEL VARNUM
Footing/Foundation/Slab 2/17/2023 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 2/21/2023 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 2/21/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/22/2023 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 2/22/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/3/2023 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 3/3/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 3/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 3/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 3/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 3/8/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 3/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/9/2023 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 3/9/2023 Partial Approval DANNY RODRIGUEZ
Insulation 3/13/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 3/14/2023 Partial Approval DANNY RODRIGUEZ
Insulation 3/15/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 3/15/2023 Partial Approval DANNY RODRIGUEZ
Insulation 3/16/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 3/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 3/16/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/20/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 3/20/2023 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 3/20/2023 Partial Approval STEVEN LEVITT
Wood Frame 3/20/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 3/22/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 3/22/2023 Partial Approval DANNY RODRIGUEZ
Insulation 3/23/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/24/2023 Conditional Approval ANDREW DORSO
Green Building Rough 3/24/2023 Not Ready for Inspection ANDREW DORSO
Drywall Nailing 3/29/2023 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 3/29/2023 Partial Approval DANNY RODRIGUEZ
Insulation 3/30/2023 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 3/30/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/31/2023 Approved DANNY RODRIGUEZ
Insulation 3/31/2023 Partial Approval DANNY RODRIGUEZ
Deputy Other (see comments) 4/3/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/3/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/3/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/4/2023 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 4/4/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/5/2023 Approved DANNY RODRIGUEZ
Drywall Nailing 4/5/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/10/2023 Conditional Approval RICKEY JACKSON
Insulation 4/10/2023 Not Ready for Inspection STEVEN LEVITT
Insulation 4/11/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/13/2023 Conditional Approval DANIEL VARNUM
Insulation 4/13/2023 Approved DANIEL VARNUM
Deputy Reinf. Concrete 4/14/2023 Conditional Approval DANIEL VARNUM
Insulation 4/14/2023 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 4/14/2023 Partial Approval DANIEL VARNUM
Drywall Nailing 4/18/2023 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 4/19/2023 Conditional Approval JOHN KITCKO
Green Building Rough 4/20/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 4/20/2023 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 4/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/24/2023 Approved DANNY RODRIGUEZ
Insulation 4/27/2023 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 4/28/2023 Partial Approval DANNY RODRIGUEZ
METHANE-Final 4/28/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 5/1/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 5/5/2023 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 5/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 5/12/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 5/12/2023 Partial Approval DANNY RODRIGUEZ
T-Bar Ceiling 5/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 5/15/2023 Partial Approval JOHN KITCKO
Insulation 5/17/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 5/17/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/18/2023 Partial Approval DANNY RODRIGUEZ
Insulation 5/18/2023 Partial Approval DANNY RODRIGUEZ
Insulation 5/22/2023 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 5/23/2023 Partial Inspection ANDREW DORSO
Insulation 5/24/2023 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 5/25/2023 Not Ready for Inspection ANDREW DORSO
Deputy Reinf. Concrete 5/26/2023 Conditional Approval JEFFREY DURAN
Drywall Nailing 5/26/2023 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 5/26/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 5/30/2023 Partial Inspection ANDREW DORSO
Insulation 5/30/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 5/31/2023 Partial Inspection ANDREW DORSO
T-Bar Ceiling 6/1/2023 Corrections Issued ANDREW DORSO
Light Gage Steel Frame 6/2/2023 Partial Inspection ANDREW DORSO
Insulation 6/5/2023 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 6/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 6/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 6/7/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/8/2023 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 6/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 6/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 6/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 6/8/2023 Partial Approval DANNY RODRIGUEZ
METHANE-Final 6/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 6/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 6/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/8/2023 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 6/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/8/2023 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 6/9/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/12/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/14/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 6/15/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/16/2023 Approved DANNY RODRIGUEZ
Drywall Nailing 6/20/2023 Corrections Issued DANNY RODRIGUEZ
Light Gage Steel Frame 6/20/2023 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 6/22/2023 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 6/23/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/26/2023 Approved DANNY RODRIGUEZ
Insulation 6/26/2023 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 6/26/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 6/28/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 6/28/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/29/2023 Partial Approval DANNY RODRIGUEZ
Insulation 6/29/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 6/30/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/5/2023 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 7/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 7/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/11/2023 Partial Approval CAMERON CHABAN
Insulation 7/11/2023 Partial Approval CAMERON CHABAN
T-Bar Ceiling 7/11/2023 Not Ready for Inspection CAMERON CHABAN
Light Gage Steel Frame 7/12/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/14/2023 Partial Approval DANNY RODRIGUEZ
Insulation 7/14/2023 Partial Approval DANNY RODRIGUEZ
T-Bar Ceiling 7/15/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/26/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 7/26/2023 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 7/27/2023 No Access for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/28/2023 Approved DANNY RODRIGUEZ
Green Building Rough 7/28/2023 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 7/28/2023 Partial Approval DANNY RODRIGUEZ
METHANE-Rough 7/28/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 7/28/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/28/2023 Partial Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 8/2/2023 Partial Inspection DANNY RODRIGUEZ
T-Bar Ceiling 8/2/2023 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 8/8/2023 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/10/2023 Partial Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 8/10/2023 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 8/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/15/2023 Approved DANNY RODRIGUEZ
Insulation 8/15/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 8/15/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/16/2023 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 8/17/2023 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/18/2023 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 8/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 8/23/2023 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 8/23/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/25/2023 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 8/25/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/1/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/5/2023 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 9/5/2023 Not Ready for Inspection ANDREW DORSO
Drywall Nailing 9/6/2023 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 9/6/2023 Not Ready for Inspection ANDREW DORSO
Drywall Nailing 9/7/2023 Partial Inspection ANDREW DORSO
Insulation 9/7/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 9/8/2023 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 9/8/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 9/11/2023 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 9/11/2023 Partial Approval GREGORY POMISH
Light Gage Steel Frame 9/11/2023 Partial Approval GREGORY POMISH
Insulation 9/13/2023 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 9/14/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/15/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 9/15/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 9/15/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/21/2023 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/21/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/22/2023 Partial Approval DANNY RODRIGUEZ
T-Bar Ceiling 9/22/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/25/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 9/25/2023 Partial Approval DANNY RODRIGUEZ
T-Bar Ceiling 10/2/2023 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 10/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 10/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 10/13/2023 Partial Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 10/23/2023 Partial Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 10/26/2023 Partial Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 10/30/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 10/31/2023 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 10/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Final 10/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 10/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 10/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/31/2023 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 10/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 11/14/2023 Partial Approval DANNY RODRIGUEZ
Structural Steel Frame 12/5/2023 Partial Approval DANNY RODRIGUEZ
Structural Steel Frame 12/7/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/11/2023 Approved DANNY RODRIGUEZ
Structural Steel Frame 12/13/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 12/19/2023 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 12/19/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 12/19/2023 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Final 12/19/2023 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 12/19/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/19/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Approved DANNY RODRIGUEZ
Smoke Detectors 12/19/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/19/2023 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 1/5/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 1/22/2024 Not Ready for Inspection ANDREW DORSO
Wood Frame 1/23/2024 Partial Approval DANNY RODRIGUEZ
Final 1/26/2024 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 1/29/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 1/29/2024 Partial Inspection DANNY RODRIGUEZ
Wood Frame 1/30/2024 Partial Inspection DANNY RODRIGUEZ
Wood Frame 1/31/2024 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 2/1/2024 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 3/1/2024 Corrections Issued DANNY RODRIGUEZ
Special/Order Compliance 3/5/2024 Partial Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Partial Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Not Ready for Inspection DANNY RODRIGUEZ
Final 3/26/2024 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 3/28/2024 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 3/28/2024 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 3/29/2024 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 3/29/2024 Not Ready for Inspection DANNY RODRIGUEZ
Final 4/2/2024 Partial Inspection DANNY RODRIGUEZ
Structural Steel Frame 4/2/2024 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 4/3/2024 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 4/3/2024 Not Ready for Inspection DANNY RODRIGUEZ
Final 4/11/2024 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 4/11/2024 Approved DANNY RODRIGUEZ
Green Building Final 4/11/2024 Approved DANNY RODRIGUEZ
METHANE-Final 4/11/2024 Approved DANNY RODRIGUEZ
METHANE-Rough 4/11/2024 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 4/11/2024 Approved DANNY RODRIGUEZ
Smoke Detectors 4/11/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/11/2024 Approved DANNY RODRIGUEZ
Special/Order Compliance 4/12/2024 Corrections Issued DANNY RODRIGUEZ
Special/Order Compliance 4/18/2024 Partial Inspection DANNY RODRIGUEZ
Final 5/23/2024 OK to Issue CofO DANNY RODRIGUEZ
Smoke Detectors 5/23/2024 Approved DANNY RODRIGUEZ