210-210 1/2 W 105TH ST 90003

Certificate Information: 210-210 1/2 W 105TH ST 90003

Application / Permit
21010-10000-01811
Plan Check / Job No.
B21LA06757
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW DUPLEX WITH ATTACHED GARAGE.
Permit Issued
Issued on 9/17/2021
Issuing Office
Current Status
CofO Issued on 2/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 KEVIN MORALES
Corrections Issued 4/30/2021 KEVIN MORALES
Quality Review Completed 5/3/2021 EUGENE BARBEAU
Plan Check Approved 9/15/2021 KEVIN MORALES
Issued 9/17/2021 APPLICANT
Building Plans Picked Up 9/20/2021 APPLICANT
CofO in Progress 2/23/2022 JOHN KLARIN
Permit Finaled 2/24/2022 DEROLD HAUFF
CofO Issued 2/24/2022 DEROLD HAUFF
Permit Finaled 2/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/2/2021 JEANIE LAM
Sewer availability Cleared 6/3/2021 JEANIE LAM
Hydrant and Access approval Cleared 8/16/2021 ROBERT DUFF
Low Impact Development Cleared 9/2/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/8/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/9/2021 JEANIE LAM

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/13/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval EUGENE CASSIDY
Underground Mechanical 10/27/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Partial Approval EUGENE CASSIDY
Insulation 10/28/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 12/7/2021 Approved EUGENE CASSIDY
Green Building Rough 12/7/2021 Approved EUGENE CASSIDY
MERV13>=Rough 12/7/2021 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 12/7/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 12/7/2021 Approved EUGENE CASSIDY
Insulation 12/8/2021 Approved EUGENE CASSIDY
Drywall Nailing 12/15/2021 Approved ANSON MAGLASANG
Interior/Exterior Lathing 12/15/2021 Approved ANSON MAGLASANG
ELECTRICAL-Final 2/9/2022 Conditional Approval JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 2/17/2022 SGSOV Not Ready ANSON MAGLASANG
ELECTRICAL-Final 2/22/2022 Approved JOHN KLARIN
Final 2/22/2022 OK to Issue CofO JOHN KLARIN
Green Building Final 2/22/2022 Approved JOHN KLARIN
HVAC-Final 2/22/2022 Approved JOHN KLARIN
MERV13>=Final 2/22/2022 Approved JOHN KLARIN
PLUMBING-Final 2/22/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 2/22/2022 SGSOV Approved JOHN KLARIN
Service/Power Release 2/22/2022 Approved JOHN KLARIN
Smoke Detectors 2/22/2022 Approved JOHN KLARIN
Special/Order Compliance 2/22/2022 Approved JOHN KLARIN
Service/Power Release 2/24/2022 Approved JOHN KLARIN