641-641 1/2 E 21ST ST 90011
Certificate Information: 641-641 1/2 E 21ST ST 90011
- Application / Permit
- 21010-10000-01806
- Plan Check / Job No.
- B21LA06752
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX (FRONT)
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- CofO Issued on 8/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | KHEDER ALRAZAA |
| Corrections Issued | 5/17/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 5/26/2021 | JASON HEALEY |
| Applicant returned to address corrections | 12/15/2021 | KHEDER ALRAZAA |
| Plan Check Approved | 1/4/2022 | KHEDER ALRAZAA |
| Issued | 1/28/2022 | APPLICANT |
| Building Plans Picked Up | 2/17/2022 | APPLICANT |
| CofO in Progress | 8/2/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
| CofO Issued | 8/6/2023 | DEROLD HAUFF |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2021 | CELINA MORENO |
| Highway dedication | Cleared | 6/3/2021 | WALLIE JONG |
| Frnt yard landscape/Water mgmt | Cleared | 7/7/2021 | MIGUEL GAMBOA |
| Sewer availability | Cleared | 7/8/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 7/21/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/6/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | WALLIE JONG |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Landscape Architect | Macias,, Jaime; Lic. No.: LA5870 | 953 FLORE STREET ANAHEIM, CA 92802 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/17/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/2/2022 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 3/8/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/29/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 10/28/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 10/28/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 11/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 11/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/10/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 11/10/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/10/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 11/10/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/10/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 11/10/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/16/2022 | Corrections Issued | SCOTT FINNILA |
| Insulation | 11/16/2022 | Conditional Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 11/21/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/21/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/23/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/29/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/29/2022 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 3/8/2023 | Approved | BRENDAN MORELLI |
| Verify Rec and Parks Fee Memo | 6/13/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 7/20/2023 | Approved | BRENDAN MORELLI |
| Gas Test | 7/20/2023 | Approved | BRENDAN MORELLI |
| Green Building Final | 7/20/2023 | Approved | BRENDAN MORELLI |
| HVAC-Final | 7/20/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 7/20/2023 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 7/20/2023 | SGSOV Not Ready | BRENDAN MORELLI |
| Service/Power Release | 7/20/2023 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 7/20/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/25/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/28/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/28/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/1/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/1/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/1/2023 | Approved | ALEJANDRO DE ARTOLA |