641-641 1/2 E 21ST ST 90011

Certificate Information: 641-641 1/2 E 21ST ST 90011

Application / Permit
21010-10000-01806
Plan Check / Job No.
B21LA06752
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX (FRONT)
Permit Issued
Issued on 1/28/2022
Issuing Office
Current Status
CofO Issued on 8/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 KHEDER ALRAZAA
Corrections Issued 5/17/2021 KHEDER ALRAZAA
Quality Review Completed 5/26/2021 JASON HEALEY
Applicant returned to address corrections 12/15/2021 KHEDER ALRAZAA
Plan Check Approved 1/4/2022 KHEDER ALRAZAA
Issued 1/28/2022 APPLICANT
Building Plans Picked Up 2/17/2022 APPLICANT
CofO in Progress 8/2/2023 ALEJANDRO DE ARTOLA
Permit Finaled 8/6/2023 DEROLD HAUFF
CofO Issued 8/6/2023 DEROLD HAUFF
Permit Finaled 8/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/21/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/25/2021 CELINA MORENO
Highway dedication Cleared 6/3/2021 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 7/7/2021 MIGUEL GAMBOA
Sewer availability Cleared 7/8/2021 CELINA MORENO
Hydrant and Access approval Cleared 7/21/2021 MATTHEW CRAIG
Low Impact Development Cleared 10/6/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 10/7/2021 WALLIE JONG

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 669 N THIRD AVENUE      UPLAND, CA 91786
Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Landscape Architect Macias,, Jaime; Lic. No.: LA5870 953 FLORE STREET      ANAHEIM, CA 92802

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/17/2022 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 3/2/2022 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/8/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 4/13/2022 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/29/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Rough 10/28/2022 Corrections Issued ANTHONY EGSON
HVAC-Rough 10/28/2022 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 11/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 11/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/10/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/10/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 11/10/2022 Approved ALIZAH MAYAGOITIA
HVAC-Rough 11/10/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 11/10/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 11/10/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/16/2022 Corrections Issued SCOTT FINNILA
Insulation 11/16/2022 Conditional Approval SCOTT FINNILA
BUILDING-Rough-Frame 11/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 11/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 11/23/2022 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 11/29/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 12/8/2022 Approved ALEJANDRO DE ARTOLA
Insulation 12/8/2022 Approved ALEJANDRO DE ARTOLA
Sewer 3/8/2023 Approved BRENDAN MORELLI
Verify Rec and Parks Fee Memo 6/13/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 7/20/2023 Approved BRENDAN MORELLI
Gas Test 7/20/2023 Approved BRENDAN MORELLI
Green Building Final 7/20/2023 Approved BRENDAN MORELLI
HVAC-Final 7/20/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 7/20/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 7/20/2023 SGSOV Not Ready BRENDAN MORELLI
Service/Power Release 7/20/2023 Approved BRENDAN MORELLI
Smoke Detectors 7/20/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 7/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 7/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 7/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/25/2023 SGSOV Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 7/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/28/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/1/2023 Approved ALEJANDRO DE ARTOLA
Final 8/1/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
PLUMBING-Final 8/1/2023 Approved ALEJANDRO DE ARTOLA