1447-1459 W MAV DR 90732
Certificate Information: 1447-1459 W MAV DR 90732
- Application / Permit
- 21010-10000-01793
- Plan Check / Job No.
- B21LA06737
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3 STORY, 4 UNIT TOWNHOUSE STYLE APT. BUILDING. ( building #22, type 102A )
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | GARO TELMI |
| Corrections Issued | 6/25/2021 | GARO TELMI |
| Quality Review Completed | 7/6/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 8/17/2021 | GARO TELMI |
| Applicant returned to address corrections | 8/31/2021 | GARO TELMI |
| Green Plans Picked Up | 9/30/2021 | APPLICANT |
| Applicant returned to address corrections | 12/2/2021 | GARO TELMI |
| Applicant returned to address corrections | 2/7/2022 | GARO TELMI |
| Building Plans Picked Up | 4/19/2022 | APPLICANT |
| Plan Check Approved | 1/19/2023 | GARO TELMI |
| Issued | 1/23/2023 | APPLICANT |
| CofO in Progress | 11/5/2025 | RICARDO ROBLES |
| Permit Finaled | 11/18/2025 | HENRY BAGHDASSARIAN |
| CofO Issued | 11/18/2025 | HENRY BAGHDASSARIAN |
| Permit Finaled | 11/18/2025 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/26/2021 | WALTER RAMIREZ |
| Green Code | Cleared | 9/28/2021 | AARON COSTA |
| DAS Clearance | Cleared | 11/22/2021 | GARO TELMI |
| Trees in Parkway | Cleared | 11/30/2021 | ADALBERTO VERA |
| CPC | Cleared | 12/2/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 12/2/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 12/2/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 12/2/2021 | ANACANY HURTADO |
| Site Plan review | Cleared | 12/2/2021 | ANACANY HURTADO |
| Specific Plan | Cleared | 12/2/2021 | ANACANY HURTADO |
| Tract Map conditions | Cleared | 12/2/2021 | ANACANY HURTADO |
| Tract Map conditions | Cleared | 12/2/2021 | ANACANY HURTADO |
| Low Impact Development | Cleared | 12/9/2021 | AMMAR ELTAWIL |
| Grading Pre-Inspection | Cleared | 12/21/2021 | SERGIO VALENZUELA |
| Address approval | Cleared | 10/28/2022 | ANA SORIANO |
| Drainage to Storm Drain | Cleared | 10/28/2022 | ANA SORIANO |
| Highway dedication | Cleared | 10/28/2022 | ANA SORIANO |
| Miscellaneous | Cleared | 10/28/2022 | ANA SORIANO |
| Permit | Cleared | 10/28/2022 | ANA SORIANO |
| Roof/Waste drainage to street | Cleared | 10/28/2022 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2022 | ANA SORIANO |
| Sewer availability | Cleared | 11/9/2022 | ANA SORIANO |
| Hydrant and Access approval | Cleared | 12/7/2022 | JOHN CONNEALLY |
| Building over 36-ft | Cleared | 1/19/2023 | CALOSHA APPROVED |
Contact Information
| Architect | Cunningham,, Gary Lynn; Lic. No.: C29285 | 18162 LILLIAN WAY TUSTIN, CA 92780 |
| Contractor | Hillcrest Construction Group Llc; Lic. No.: 1086392-B | 1875 CENTURY PARK EAST SUITE 1130 LOS ANGELES, CA 90067 |
| Engineer | Arnet,, Beat Walter; Lic. No.: C40486 | 28496 VIA REGGIO LAGUNA NIGUEL, CA 92677 |
| Engineer | Burica,, Michael Jerome; Lic. No.: C57151 | 9283 RESEARCH DR IRVINE, CA 92618 |
| Engineer | Ho,, Patrick Pak Hei; Lic. No.: C72847 | PO BOX 143 WALNUT, CA 91788 |
| Engineer | Reed,, Ronald Albert; Lic. No.: GE2524 | 3186 AIRWAY AVE K COSTA MESA, CA 92626 |
| Geologist | Wolfe,, Theodore Marshall; Lic. No.: EG1626 | 18610 CABALLERO CT TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Pre-Stress Concrete | 4/7/2023 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/11/2023 | Approved | JOEY BUCHANAN |
| METHANE-Barrier | 4/11/2023 | Approved | JOEY BUCHANAN |
| METHANE-Subgrade | 4/11/2023 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 4/13/2023 | Approved | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2023 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2024 | Partial Approval | JOEY BUCHANAN |
| Insulation | 3/21/2024 | Partial Approval | JOEY BUCHANAN |
| Green Building Rough | 7/3/2024 | Approved | RICARDO ROBLES |
| METHANE-Rough | 7/3/2024 | Approved | RICARDO ROBLES |
| Verify Sprinkler Sign Off | 7/3/2024 | Approved | RICARDO ROBLES |
| Wood Frame | 7/3/2024 | Approved | RICARDO ROBLES |
| Insulation | 7/8/2024 | Not Ready for Inspection | JOEY BUCHANAN |
| Insulation | 7/10/2024 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 7/15/2024 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 7/17/2024 | Not Ready for Inspection | JOEY BUCHANAN |
| Drywall Nailing | 7/19/2024 | Approved | JOEY BUCHANAN |
| Final | 10/29/2024 | Not Ready for Inspection | JOEY BUCHANAN |
| Green Building Final | 10/29/2024 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 10/29/2024 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 10/29/2024 | Approved | JOEY BUCHANAN |
| Final | 10/27/2025 | OK to Issue CofO | RICARDO ROBLES |