12620 W GREENE AVE 90066

Certificate Information: 12620 W GREENE AVE 90066

Application / Permit
21010-10000-01768
Plan Check / Job No.
B21LA06719
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU conversion. Convert existing garage to an A.D.U.
Permit Issued
Issued on 4/30/2021
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2021 APPLICANT
Assigned to Plan Check Engineer 4/14/2021 CARLOS MONTES
Corrections Issued 4/14/2021 CARLOS MONTES
Plan Check Approved 4/27/2021 CARLOS MONTES
Issued 4/30/2021 APPLICANT
CofO in Progress 2/17/2023 HERBERT GIRON
No Progress 2/24/2023 RICHARD STEINBACH
CofO in Progress 2/25/2023 RICHARD STEINBACH
Permit Finaled 3/4/2023 DANIEL ORRANTE
CofO Issued 3/4/2023 DANIEL ORRANTE
Permit Finaled 3/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/20/2021 DINAH GARIN
Sewer availability Cleared 4/20/2021 DINAH GARIN
Specific Plan Cleared 4/20/2021 PEDRO AYALA
Eng Process Fee Ord 176,300 Cleared 4/22/2021 DINAH GARIN

Contact Information

Contractor Amelfig Builders & Remodeling Inc; Lic. No.: 1028969-B 17216 SATICOY #318      VAN NUYS, CA 91406

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/8/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 6/8/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 6/23/2021 Conditional Approval DONALD GALLAGHER
ELECTRICAL-Rough 6/23/2021 Approved DONALD GALLAGHER
Gas Test 6/23/2021 Approved DONALD GALLAGHER
Green Building Rough 6/23/2021 Approved DONALD GALLAGHER
HVAC-Rough 6/23/2021 Approved DONALD GALLAGHER
PLUMBING-Rough 6/23/2021 Approved DONALD GALLAGHER
Rough-Elec/Plmb/HVAC 6/23/2021 Approved DONALD GALLAGHER
Underground Mechanical 6/23/2021 Approved DONALD GALLAGHER
BUILDING-Rough-Frame 7/8/2021 Partial Approval ENRIQUE MIRELES
Insulation 7/8/2021 Approved ENRIQUE MIRELES
Shower Pan 7/8/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 7/14/2021 Approved ENRIQUE MIRELES
Drywall Nailing 7/16/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 7/16/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 9/16/2021 Approved ENRIQUE MIRELES
Final 9/16/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 9/16/2021 Approved ENRIQUE MIRELES
HVAC-Final 9/16/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 9/16/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 9/16/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 9/20/2021 Approved JOHNNY MIRANDA
HVAC-Final 9/20/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 9/20/2021 Approved JOHNNY MIRANDA
Final 2/17/2023 OK to Issue CofO HERBERT GIRON