12620 W GREENE AVE 90066
Certificate Information: 12620 W GREENE AVE 90066
- Application / Permit
- 21010-10000-01768
- Plan Check / Job No.
- B21LA06719
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU conversion. Convert existing garage to an A.D.U.
- Permit Issued
- Issued on 4/30/2021
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2021 | CARLOS MONTES |
| Corrections Issued | 4/14/2021 | CARLOS MONTES |
| Plan Check Approved | 4/27/2021 | CARLOS MONTES |
| Issued | 4/30/2021 | APPLICANT |
| CofO in Progress | 2/17/2023 | HERBERT GIRON |
| No Progress | 2/24/2023 | RICHARD STEINBACH |
| CofO in Progress | 2/25/2023 | RICHARD STEINBACH |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2021 | DINAH GARIN |
| Sewer availability | Cleared | 4/20/2021 | DINAH GARIN |
| Specific Plan | Cleared | 4/20/2021 | PEDRO AYALA |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2021 | DINAH GARIN |
Contact Information
| Contractor | Amelfig Builders & Remodeling Inc; Lic. No.: 1028969-B | 17216 SATICOY #318 VAN NUYS, CA 91406 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/8/2021 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/8/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/23/2021 | Conditional Approval | DONALD GALLAGHER |
| ELECTRICAL-Rough | 6/23/2021 | Approved | DONALD GALLAGHER |
| Gas Test | 6/23/2021 | Approved | DONALD GALLAGHER |
| Green Building Rough | 6/23/2021 | Approved | DONALD GALLAGHER |
| HVAC-Rough | 6/23/2021 | Approved | DONALD GALLAGHER |
| PLUMBING-Rough | 6/23/2021 | Approved | DONALD GALLAGHER |
| Rough-Elec/Plmb/HVAC | 6/23/2021 | Approved | DONALD GALLAGHER |
| Underground Mechanical | 6/23/2021 | Approved | DONALD GALLAGHER |
| BUILDING-Rough-Frame | 7/8/2021 | Partial Approval | ENRIQUE MIRELES |
| Insulation | 7/8/2021 | Approved | ENRIQUE MIRELES |
| Shower Pan | 7/8/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/16/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/16/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/16/2021 | Approved | ENRIQUE MIRELES |
| Final | 9/16/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 9/16/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 9/16/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 9/16/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/16/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/16/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/20/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 9/20/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 9/20/2021 | Approved | JOHNNY MIRANDA |
| Final | 2/17/2023 | OK to Issue CofO | HERBERT GIRON |