7034 N GEYSER AVE 91335

Certificate Information: 7034 N GEYSER AVE 91335

Application / Permit
21010-10000-01741
Plan Check / Job No.
B21LA06600
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADU ADDITION TO (E) GARAGE. PROPOSED DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 2/24/2023
Issuing Office
Current Status
CofO in Progress on 1/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/14/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 CARLOS MONTES
Corrections Issued 5/28/2021 MICHAEL LOPEZ
Quality Review Completed 6/6/2021 HERNAN ARREOLA
Applicant returned to address corrections 1/11/2023 CARLOS MONTES
Plan Check Approved 2/7/2023 CARLOS MONTES
Issued 2/24/2023 APPLICANT
CofO in Progress 1/30/2024 JEFFREY BULL
No Progress 1/13/2025 SEAN WIRCH
CofO in Progress 1/13/2025 SEAN WIRCH

Permit Application Clearance Information

ZI Cleared 11/15/2021 RUBEN VASQUEZ
Low Impact Development Cleared 6/2/2022 ANDRES COVARRUBIAS
Hydrant and Access approval Cleared 8/8/2022 LAVEON RIDER
Eng Process Fee Ord 176,300 Cleared 8/17/2022 COLIN LOREDO
Address approval Cleared 11/17/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 11/17/2022 COLIN LOREDO
Sewer availability Cleared 11/17/2022 COLIN LOREDO

Contact Information

Contractor Sauer Paul Construction; Lic. No.: 1079869-B       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/3/2023 Not Ready for Inspection JEFFREY BULL
Pre-Inspection 4/3/2023 Approved JEFFREY BULL
Deputy Drilled-In Anchors 4/4/2023 Conditional Approval JEFFREY BULL
Deputy Drilled-In Anchors 4/4/2023 Conditional Approval MORRIS JACKSON
Sewer 4/6/2023 Not Ready for Inspection JEFFREY BULL
Footing/Foundation/Slab 4/17/2023 Approved JEFFREY BULL
Wood Frame 6/14/2023 Partial Approval JEFFREY BULL
ELECTRICAL-Rough 7/7/2023 Not Ready for Inspection JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 7/7/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 7/20/2023 Approved JUSTIN HAWLEY
Green Building Rough 7/20/2023 Approved JUSTIN HAWLEY
HVAC-Rough 7/20/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 7/20/2023 Partial Approval JUSTIN HAWLEY
PLUMBING-Rough 7/20/2023 Approved JUSTIN HAWLEY
Insulation 7/26/2023 Not Ready for Inspection JEFFREY BULL
Drywall Nailing 8/8/2023 Corrections Issued JUSTIN HAWLEY
Insulation 8/8/2023 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 8/10/2023 Approved JUSTIN HAWLEY
Drywall Nailing 8/10/2023 Approved JUSTIN HAWLEY
Shower Pan 8/25/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 8/29/2023 Approved JUSTIN HAWLEY
Underground Mechanical 9/12/2023 Partial Approval JEFFREY BULL
Sewer 9/18/2023 Corrections Issued HENRY KIM
Underground Mechanical 9/18/2023 Partial Approval HENRY KIM
Sewer 9/21/2023 Approved JEFFREY BULL
Service/Power Release 10/30/2023 Corrections Issued JEFFREY BULL
Service/Power Release 11/3/2023 Approved JEFFREY BULL
Final 12/8/2023 Corrections Issued JEFFREY BULL
Green Building Final 12/8/2023 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 12/8/2023 SGSOV Not Ready JEFFREY BULL
Smoke Detectors 12/8/2023 Approved JEFFREY BULL
Final 1/29/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 1/29/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 1/29/2024 SGSOV Approved JEFFREY BULL
Special/Order Compliance 12/30/2024 Corrections Issued SEAN WIRCH