300 S SANTA FE AVE 90012
Certificate Information: 300 S SANTA FE AVE 90012
- Application / Permit
- 21010-10000-01737
- Plan Check / Job No.
- B21LA06581
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Patio Cover
- Work Description
- INSTALL NEW DETACHED ( 34' X11') TRELLIS AT TEH (E) POOL AREA OF MIXED USE APT BUILDING ( FOR RESIDENTAIL USE ONLY)
- Permit Issued
- Issued on 2/14/2022
- Issuing Office
- Current Status
- CofO Issued on 10/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | GARO TELMI |
| Corrections Issued | 6/4/2021 | GARO TELMI |
| Quality Review Completed | 6/15/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 6/24/2021 | GARO TELMI |
| Applicant returned to address corrections | 7/26/2021 | GARO TELMI |
| Applicant returned to address corrections | 10/8/2021 | GARO TELMI |
| Applicant returned to address corrections | 10/13/2021 | GARO TELMI |
| Applicant returned to address corrections | 1/12/2022 | GARO TELMI |
| Disabled Access Plans Picked Up | 1/24/2022 | APPLICANT |
| Plan Check Approved | 1/26/2022 | GARO TELMI |
| Issued | 2/14/2022 | APPLICANT |
| Building Plans Picked Up | 2/17/2022 | APPLICANT |
| CofO in Progress | 10/5/2023 | RAFAEL ESPINOZA |
| Permit Finaled | 10/6/2023 | TED RIES |
| CofO Issued | 10/6/2023 | TED RIES |
| Permit Finaled | 10/6/2023 | TED RIES |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 6/28/2021 | MELISSA JONES |
| City owned building/parcel | Cleared | 6/28/2021 | GARO TELMI |
| Green Code | Cleared | 6/28/2021 | GARO TELMI |
| Historic monument | Cleared | 6/28/2021 | MELISSA JONES |
| "D" conditions | Cleared | 7/1/2021 | JOE LUCKEY |
| "Q" conditions | Cleared | 7/14/2021 | JOE LUCKEY |
| CPC | Cleared | 7/14/2021 | JOE LUCKEY |
| Miscellaneous | Cleared | 7/14/2021 | JOE LUCKEY |
| Miscellaneous | Cleared | 7/14/2021 | JOE LUCKEY |
| Site Plan review | Cleared | 7/14/2021 | JOE LUCKEY |
| ZA Case | Cleared | 7/14/2021 | JOE LUCKEY |
| ZI | Cleared | 7/14/2021 | JOE LUCKEY |
| ZI | Cleared | 7/14/2021 | JOE LUCKEY |
| DAS Clearance | Cleared | 7/19/2021 | GARO TELMI |
| Metro Rail approval | Cleared | 8/17/2021 | GARO TELMI |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2021 | CECILIO NAVARRO |
| Address approval | Cleared | 9/14/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 9/14/2021 | WALLIE JONG |
| Sewer availability | Cleared | 9/14/2021 | WALLIE JONG |
| Highway dedication | Cleared | 9/15/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 9/19/2021 | ROBERT DUFF |
Contact Information
| Architect | Pickard,, David Waldon; Lic. No.: C16822 | 13215 PENN ST SUITE 300 WHITTIER, CA 90602 |
| Contractor | Amida Resources Inc; Lic. No.: 490295-B | 18340 YORBA LINDA BLVD STE 107-404 YORBA LINDA, CA 92886 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 7/13/2023 | Corrections Issued | RAFAEL ESPINOZA |
| Pre-Inspection | 7/18/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 8/21/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/21/2023 | Approved | RAFAEL ESPINOZA |
| Green Building Final | 8/21/2023 | Approved | RAFAEL ESPINOZA |
| Green Building Rough | 8/21/2023 | Approved | RAFAEL ESPINOZA |
| METHANE-Barrier | 8/21/2023 | Approved | RAFAEL ESPINOZA |
| METHANE-Final | 8/21/2023 | Approved | RAFAEL ESPINOZA |
| METHANE-Rough | 8/21/2023 | Approved | RAFAEL ESPINOZA |
| METHANE-Subgrade | 8/21/2023 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV No Gas | RAFAEL ESPINOZA |
| Smoke Detectors | 8/21/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 8/21/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 8/21/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 10/2/2023 | Conditional Approval | RAFAEL ESPINOZA |
| Smoke Detectors | 10/2/2023 | Approved | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 10/2/2023 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 10/2/2023 | Approved | RAFAEL ESPINOZA |