733 1/2 E 32ND ST 90011
Certificate Information: 733 1/2 E 32ND ST 90011
- Application / Permit
- 21010-10000-01709
- Plan Check / Job No.
- B21LA06474
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO STORY ADU AT REAR OF LOT.
- Permit Issued
- Issued on 10/14/2021
- Issuing Office
- Current Status
- CofO Issued on 11/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | JOE VO |
| Corrections Issued | 4/24/2021 | JOE VO |
| Quality Review Completed | 4/28/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 6/7/2021 | JOE VO |
| Applicant returned to address corrections | 7/7/2021 | JOE VO |
| Plan Check Approved | 9/29/2021 | JOE VO |
| Issued | 10/14/2021 | APPLICANT |
| CofO in Progress | 11/8/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 11/10/2022 | DEROLD HAUFF |
| CofO Issued | 11/10/2022 | DEROLD HAUFF |
| Permit Finaled | 11/10/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2021 | CELINA MORENO |
| Sewer availability | Cleared | 5/13/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 8/27/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 9/21/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 9/22/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/17/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 12/8/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/28/2021 | Conditional Approval | HORACE FULTZ |
| Footing/Foundation/Slab | 12/28/2021 | Not Ready for Inspection | HORACE FULTZ |
| Excavation/Setback/Form/Re-Bar | 1/3/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 2/10/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Special/Order Compliance | 3/4/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 3/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 3/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/23/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Pre-Inspection | 3/23/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 3/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/11/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 5/11/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 5/11/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 5/11/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/11/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 5/11/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/31/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 5/31/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 5/31/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 5/31/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 5/31/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 6/1/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/16/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 6/16/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 6/16/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/16/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/16/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 7/5/2022 | Approved | HORACE FULTZ |
| Final | 8/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/15/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 8/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 8/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 8/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 9/27/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Green Building Final | 9/27/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Service/Power Release | 9/27/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Smoke Detectors | 9/27/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Final | 9/30/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 10/7/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Green Building Final | 10/7/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 10/7/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Service/Power Release | 10/7/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Smoke Detectors | 10/7/2022 | Approved | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 10/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 11/1/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 11/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 11/3/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/3/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/7/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 11/7/2022 | Approved | ALEJANDRO DE ARTOLA |