3724 1/2 N PASADENA AVE 90031

Certificate Information: 3724 1/2 N PASADENA AVE 90031

Application / Permit
21010-10000-01705
Plan Check / Job No.
B21LA06463
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 1-story, Detached Accessory Dwelling Unit at rear of lot
Permit Issued
Issued on 8/19/2021
Issuing Office
Current Status
CofO Issued on 3/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/10/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 PRANITA SHAH
Corrections Issued 4/23/2021 PRANITA SHAH
Quality Review Completed 4/28/2021 MICHAEL PEREZ
Applicant returned to address corrections 6/30/2021 PRANITA SHAH
Applicant returned to address corrections 7/8/2021 PRANITA SHAH
Plan Check Approved 8/4/2021 PRANITA SHAH
Issued 8/19/2021 APPLICANT
CofO in Progress 3/20/2026 LILIANA PORTILLO
CofO Issued 3/21/2026 DEROLD HAUFF
Permit Finaled 3/21/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/4/2021 WALLIE JONG
HPOZ Cleared 5/5/2021 KATIE DEBIASE
Eng Process Fee Ord 176,300 Cleared 5/10/2021 WALLIE JONG
Highway dedication Cleared 5/10/2021 WALLIE JONG
Sewer availability Cleared 5/10/2021 WALLIE JONG
"Q" conditions Cleared 5/24/2021 JOE LUCKEY
"T" removal Cleared 5/24/2021 JOE LUCKEY
Grading Pre-Inspection Cleared 6/7/2021 BRIAN MILLER
Hydrant and Access approval Cleared 6/23/2021 KURT CORRAL
Metro Rail approval Cleared 6/29/2021 PRANITA SHAH
Low Impact Development Cleared 6/30/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 6/30/2021 WALLIE JONG
GPI Written Notices Cleared 8/4/2021 PRANITA SHAH

Contact Information

Architect Chhan,, Danny; Lic. No.: NA37636       ,
Contractor Owner-Builder       ,
Engineer Galbreath,, Sean Martin; Lic. No.: NA5653       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/26/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 6/9/2022 Partial Approval AMY COLIN
Footing/Foundation/Slab 6/17/2022 Conditional Approval AMY COLIN
BUILDING-Rough-Frame 11/21/2022 Corrections Issued AMY COLIN
Green Building Rough 11/21/2022 Not Ready for Inspection AMY COLIN
MERV13>=Rough 11/21/2022 Approved AMY COLIN
Verify Sprinkler Sign Off 11/21/2022 Not Ready for Inspection AMY COLIN
Deputy Wood Construction 12/2/2022 Conditional Approval AMY COLIN
BUILDING-Rough-Frame 6/8/2023 Corrections Issued AMY COLIN
Green Building Rough 6/8/2023 Approved AMY COLIN
Verify Sprinkler Sign Off 6/8/2023 Approved AMY COLIN
ELECTRICAL-Final 6/13/2023 Corrections Issued AMY COLIN
Insulation 6/13/2023 Corrections Issued AMY COLIN
Rough-Elec/Plmb/HVAC 6/13/2023 Approved AMY COLIN
Insulation 7/25/2023 Approved AMY COLIN
Drywall Nailing 8/2/2023 Approved AMY COLIN
Drywall Nailing 8/4/2023 Approved AMY COLIN
Pre-Inspection 8/7/2024 Not Ready for Inspection LILIANA PORTILLO
Final 10/15/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 12/18/2024 Approved LILIANA PORTILLO
Final 12/18/2024 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 12/18/2024 Approved LILIANA PORTILLO
Green Building Final 12/18/2024 Not Ready for Inspection LILIANA PORTILLO
MERV13>=Final 12/18/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/18/2024 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 12/18/2024 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 12/18/2024 Approved LILIANA PORTILLO
Final 1/28/2025 Not Ready for Inspection LILIANA PORTILLO
Gas Test 1/28/2025 Approved LILIANA PORTILLO
Green Building Final 1/28/2025 Approved LILIANA PORTILLO
HVAC-Final 1/28/2025 Approved LILIANA PORTILLO
PLUMBING-Final 1/28/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 1/28/2025 Approved LILIANA PORTILLO
Final 3/4/2025 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Final 3/4/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Service/Power Release 3/4/2025 Corrections Issued HAMIK HARTOUNIAN
Final 4/1/2025 Not Ready for Inspection LILIANA PORTILLO
MERV13>=Final 4/1/2025 Approved LILIANA PORTILLO
Service/Power Release 4/1/2025 Not Ready for Inspection LILIANA PORTILLO
Final 7/14/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 7/14/2025 Not Ready for Inspection LILIANA PORTILLO
Final 2/25/2026 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 2/25/2026 Approved LILIANA PORTILLO
Final 2/27/2026 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 3/19/2026 Approved LILIANA PORTILLO
Final 3/19/2026 OK to Issue CofO LILIANA PORTILLO