4606 W WASHINGTON BLVD 1-23 90016

Certificate Information: 4606 W WASHINGTON BLVD 1-23 90016

Application / Permit
21010-10000-01703
Plan Check / Job No.
B21LA06444
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 4 STORY APARTTMNET OVER PARKING GARAGE AND ART GALLERY PER DIR-2018-5417-TOC. 23 UNITS TOTAL (3 ELI, 20 LI UNITS)
Permit Issued
Issued on 10/22/2021
Issuing Office
Metro
Current Status
CofO Issued on 8/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 ARMEN JIVALAGIAN
Disabled Access Plans Picked Up 4/27/2021 APPLICANT
Corrections Issued 5/4/2021 ARMEN JIVALAGIAN
Quality Review Completed 5/10/2021 PETER KIM
Applicant returned to address corrections 7/2/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/22/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 10/14/2021 MANUEL MONTUFAR
Green Plans Picked Up 10/14/2021 APPLICANT
Plan Check Approved 10/22/2021 MANUEL MONTUFAR
Issued 10/22/2021 APPLICANT
Building Plans Picked Up 11/30/2021 APPLICANT
TCO Issued (Expire Date: 10-26-2024) 4/29/2024 ADAM BURGESS
CofO Issued 8/26/2024 ERNESTO CORRAL
Permit Finaled 8/26/2024 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/2/2021 RENZ SORIANO
Hydrant and Access approval Cleared 6/4/2021 ROBERT DUFF
Address approval Cleared 6/8/2021 WALLIE JONG
Sewer availability Cleared 6/16/2021 WALLIE JONG
Comm Cor/Mini-Mall Cleared 8/17/2021 JOE LUCKEY
Community Plan Implem. Overlay Cleared 8/18/2021 MOHAMMAD HASAN
Internal circulation Cleared 8/18/2021 MOHAMMAD HASAN
Trees in Parkway Cleared 8/19/2021 JOHN KIM
Historic Resource Verification Cleared 8/24/2021 MICAELA TORRES-GIL
Highway dedication Cleared 8/31/2021 RENZ SORIANO
Construction near power lines Cleared 9/7/2021 RIDWAN HARDY
Construction within easement Cleared 9/7/2021 RIDWAN HARDY
Public Housing Cleared 9/14/2021 SUNYOUNG KIM
Permit Cleared 9/16/2021 CELINA MORENO
DAS Clearance Cleared 9/27/2021 ARMEN JIVALAGIAN
City owned building/parcel Cleared 9/28/2021 ARMEN JIVALAGIAN
Comm Cor/Mini-Mall Cleared 9/28/2021 JOE LUCKEY
Comm Cor/Mini-Mall Cleared 9/28/2021 JOE LUCKEY
Community Plan Implem. Overlay Cleared 9/28/2021 JOE LUCKEY
Fire Marshal Fire Life Safety Cleared 9/28/2021 VIDAL GARCIA
Miscellaneous Cleared 9/28/2021 JOE LUCKEY
Opn space landscape/Water mgmt Cleared 9/28/2021 JOE LUCKEY
DCP conditions approval Cleared 9/30/2021 NICHOLAS KAWAZOE
Density Bonus 12.22.A.31 Cleared 9/30/2021 NICHOLAS KAWAZOE
Work Adjacent to Public Way Cleared 9/30/2021 ROSA SILVA
Community Plan Implem. Overlay Cleared 10/1/2021 RENZ SORIANO
Low Impact Development Cleared 10/7/2021 MARTIN FRAGOSO
Bicycle Parking Cleared 10/8/2021 JEREMY CHOK
Encroachment in public way Cleared 10/8/2021 JEREMY CHOK
Green Code Cleared 10/13/2021 AARON COSTA
Roof/Waste drainage to street Cleared 10/13/2021 THAN WIN
Building over 36-ft Cleared 10/14/2021 CALOSHA APPROVED
Redevelopment Project Area Cleared 10/14/2021 GRACIELA ACOSTA

Contact Information

Architect Maffris,, Kevin M; Lic. No.: C33104 724 S SPRING STREET # 304      LOS ANGELES, CA 90014
Contractor Raam Construction Inc; Lic. No.: 766767-B 140 S LAKE AVENUE SUITE 217      PASADENA, CA 91101
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Hahn,, Brandon Michael; Lic. No.: L7582 28368 CONSTELLATION RD UNIT 300      VALENCIA, CA 91355
Engineer Krief,, Dan Dov; Lic. No.: C76041 6420 WILSHIRE BLVD STE 1000      LOS ANGELES, CA 90048
Landscape Architect Paradowski,, Anthony; Lic. No.: LA6087 3032 PALMER DRIVE      LOS ANGELES, CA 90065

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2022 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 3/3/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/4/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 3/4/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 3/9/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 3/9/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/15/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 3/15/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 3/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/26/2022 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/4/2022 Partial Approval EDWIN GREGORYONA
Pre-Inspection 4/4/2022 Approved EDWIN GREGORYONA
Footing/Foundation/Slab 4/6/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/13/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/14/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/14/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/15/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/15/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/20/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/20/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/21/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/27/2022 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Masonry 5/16/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 6/7/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 6/8/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 6/8/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 6/9/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/10/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/14/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/15/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/16/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/17/2022 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 6/17/2022 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 6/17/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 6/22/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/24/2022 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 6/27/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/6/2022 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 7/6/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/7/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/8/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 7/8/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/11/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/12/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/13/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/14/2022 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 7/14/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/15/2022 Conditional Approval TED RIES
Deputy Reinf. Masonry 7/20/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/21/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 7/22/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 7/25/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/27/2022 Conditional Approval WINSTON DUNNING
Final 7/28/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 7/29/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 8/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 8/2/2022 Conditional Approval WINSTON DUNNING
Masonry Wall/Backfill 8/2/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 8/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/4/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/5/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/19/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 9/19/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 9/21/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 9/21/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 10/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 10/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 10/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 10/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 11/1/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 11/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/2/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/2/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 12/6/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/6/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/24/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/2/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 3/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 3/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Partial Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Partial Approval EDWIN GREGORYONA
Insulation 4/5/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 4/10/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/5/2023 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/9/2023 Conditional Approval MICHAEL ROSENBERG
Insulation 5/26/2023 Approved EDWIN GREGORYONA
T-Bar Ceiling 5/26/2023 Approved EDWIN GREGORYONA
Green Building Rough 6/2/2023 Approved EDWIN GREGORYONA
Interior/Exterior Lathing 6/2/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 6/2/2023 Approved EDWIN GREGORYONA
Wood Frame 6/2/2023 Approved EDWIN GREGORYONA
Insulation 6/12/2023 Partial Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 6/23/2023 Partial Approval GREGORY POMISH
Drywall Nailing 7/14/2023 Not Ready for Inspection ALAN MORELOS
Drywall Nailing 7/17/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 7/17/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 7/20/2023 Partial Approval JAMES POWERS
Drywall Nailing 7/25/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 7/25/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 8/4/2023 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 8/17/2023 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 8/18/2023 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 8/29/2023 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 8/31/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 9/5/2023 Approved EDWIN GREGORYONA
Drywall Nailing 9/7/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 9/15/2023 Partial Approval GREGORY POMISH
Drywall Nailing 9/27/2023 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 10/13/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 10/31/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/14/2023 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 11/20/2023 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 11/21/2023 Partial Inspection EDWIN GREGORYONA
Structural Steel Frame 11/27/2023 Not Ready for Inspection GREGORY POMISH
Light Gage Steel Frame 11/28/2023 Not Ready for Inspection RICARDO ROBLES
Light Gage Steel Frame 12/1/2023 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 12/15/2023 Partial Inspection EDWIN GREGORYONA
Special/Order Compliance 12/15/2023 Approved EDWIN GREGORYONA
Final 12/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 12/22/2023 Approved EDWIN GREGORYONA
Green Building Final 12/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 12/22/2023 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 12/22/2023 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 12/22/2023 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 12/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Special/Order Compliance 1/3/2024 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 1/10/2024 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 1/10/2024 Partial Approval EDWIN GREGORYONA
Pre-Inspection 3/7/2024 Approved EDWIN GREGORYONA
Special/Order Compliance 4/16/2024 Approved EDWIN GREGORYONA
Final 5/20/2024 Partial Inspection EDWIN GREGORYONA
Green Building Final 5/20/2024 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 5/20/2024 Approved EDWIN GREGORYONA
Final 8/21/2024 Conditional Approval EDWIN GREGORYONA