4601 W WASHINGTON BLVD 90016

Certificate Information: 4601 W WASHINGTON BLVD 90016

Application / Permit
21010-10000-01702
Plan Check / Job No.
B21LA06440
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
NEW 4-STORY OF MIXED USE COMMERCIAL BUILDING. 1-STORY, TYPE 1A PODIUM PARKING & ART STUDIOS WITH 3-STORY, TYPE VA 33 UNIT TOC DWELLING UNITS ABOVE. PER DIR-2018-5415-TOC
Permit Issued
Issued on 10/22/2021
Issuing Office
Metro
Current Status
CofO Issued on 12/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 PRANITA SHAH
Disabled Access Plans Picked Up 4/27/2021 APPLICANT
Plans on Hold 5/21/2021 PRANITA SHAH
Hold Released 6/14/2021 PRANITA SHAH
Corrections Issued 6/15/2021 PRANITA SHAH
Quality Review Completed 6/17/2021 MICHAEL PEREZ
Applicant returned to address corrections 7/20/2021 PRANITA SHAH
Applicant returned to address corrections 8/3/2021 PRANITA SHAH
Applicant returned to address corrections 9/2/2021 PRANITA SHAH
Applicant returned to address corrections 10/4/2021 PRANITA SHAH
Building Plans Picked Up 10/6/2021 APPLICANT
Green Plans Picked Up 10/14/2021 APPLICANT
Plan Check Approved 10/18/2021 PRANITA SHAH
Issued 10/22/2021 APPLICANT
TCO Issued (Expire Date: 01-27-2025) 7/31/2024 ADAM BURGESS
CofO in Progress 10/24/2024 EDWIN GREGORYONA
Permit Finaled 12/4/2024 ERNESTO CORRAL
CofO Issued 12/4/2024 ERNESTO CORRAL
Permit Finaled 12/4/2024 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/2/2021 RENZ SORIANO
Hydrant and Access approval Cleared 6/4/2021 ROBERT DUFF
Address approval Cleared 6/8/2021 WALLIE JONG
Sewer availability Cleared 6/16/2021 WALLIE JONG
Permit Cleared 7/26/2021 CECILIO NAVARRO
Bicycle Parking Cleared 8/17/2021 JEREMY CHOK
Community Plan Implem. Overlay Cleared 8/18/2021 MOHAMMAD HASAN
Driveway location Cleared 8/18/2021 MOHAMMAD HASAN
Internal circulation Cleared 8/18/2021 MOHAMMAD HASAN
Highway dedication Cleared 9/3/2021 RENZ SORIANO
Public Housing Cleared 9/7/2021 SUNYOUNG KIM
DAS Clearance Cleared 9/27/2021 PRANITA SHAH
City owned building/parcel Cleared 9/28/2021 PRANITA SHAH
Community Plan Implem. Overlay Cleared 9/28/2021 JOE LUCKEY
Frnt yard landscape/Water mgmt Cleared 9/28/2021 JOE LUCKEY
Miscellaneous Cleared 9/28/2021 JOE LUCKEY
Miscellaneous Cleared 9/28/2021 JOE LUCKEY
Opn space landscape/Water mgmt Cleared 9/28/2021 JOE LUCKEY
Prkng lot landscape/Water mgmt Cleared 9/28/2021 JOE LUCKEY
ZA Case Cleared 9/28/2021 JOE LUCKEY
ZA Case Cleared 9/28/2021 JOE LUCKEY
ZA Case Cleared 9/28/2021 JOE LUCKEY
Density Bonus 12.22.A.31 Cleared 9/30/2021 NICHOLAS KAWAZOE
Work Adjacent to Public Way Cleared 9/30/2021 ROSA SILVA
Community Plan Implem. Overlay Cleared 10/4/2021 JEREMY CHOK
Low Impact Development Cleared 10/5/2021 ANDRES COVARRUBIAS
Community Plan Implem. Overlay Cleared 10/7/2021 ADALBERTO VERA
Roof/Waste drainage to street Cleared 10/7/2021 JEREMY CHOK
Trees in Parkway Cleared 10/7/2021 ADALBERTO VERA
Green Code Cleared 10/13/2021 AARON COSTA
Redevelopment Project Area Cleared 10/15/2021 GRACIELA ACOSTA
Fire Marshal Fire Life Safety Cleared 10/16/2021 ANDREW KO
Building over 36-ft Cleared 10/18/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/18/2021 CALOSHA APPROVED

Contact Information

Architect Maffris,, Kevin M; Lic. No.: C33104 724 S SPRING STREET # 304      LOS ANGELES, CA 90014
Contractor Raam Construction Inc; Lic. No.: 766767-B 140 S LAKE AVENUE SUITE 217      PASADENA, CA 91101
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/15/2022 Approved EDWIN GREGORYONA
Footing/Foundation/Slab 3/3/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 3/3/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 3/3/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 3/4/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 3/4/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 3/4/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 3/15/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 3/15/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 3/15/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 3/21/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 3/21/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 3/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 3/23/2022 Partial Approval EDWIN GREGORYONA
Pre-Inspection 4/4/2022 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 4/14/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/14/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 4/14/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 4/14/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 4/15/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/20/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/20/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 4/20/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 4/20/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 4/21/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/27/2022 Conditional Approval DAVID BURKHEAD
Deputy Grading 5/6/2022 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 5/9/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 5/19/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 5/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 5/24/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 5/25/2022 Conditional Approval TERRY HERR
Deputy Reinf. Masonry 5/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 5/27/2022 Conditional Approval TED RIES
Masonry Wall/Backfill 5/27/2022 Partial Approval TED RIES
Deputy Reinf. Masonry 5/31/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 6/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/2/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/6/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/7/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 6/23/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 6/23/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 6/23/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 6/24/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 6/27/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 6/28/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/29/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/30/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 6/30/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 6/30/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 6/30/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 7/1/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 7/14/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 7/14/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 7/14/2022 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 7/28/2022 Approved EDWIN GREGORYONA
Footing/Foundation/Slab 8/3/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 8/3/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 8/3/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 8/9/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 8/10/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/11/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/11/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 8/11/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 8/11/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 8/12/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/15/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/15/2022 Partial Approval JAMES POWERS
METHANE-Barrier 8/15/2022 Partial Approval JAMES POWERS
METHANE-Subgrade 8/15/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 8/16/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/17/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/18/2022 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 8/18/2022 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Masonry 8/19/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/23/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/23/2022 Partial Approval JAMES POWERS
METHANE-Barrier 8/23/2022 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 8/23/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 8/24/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 8/25/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 8/26/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 8/29/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 8/30/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 8/31/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 9/1/2022 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 9/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 9/2/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 9/7/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 9/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/15/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/20/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 9/20/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 9/20/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 9/20/2022 Not Ready for Inspection EDWIN GREGORYONA
Masonry Wall/Backfill 9/22/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 9/23/2022 Partial Approval JAMES POWERS
Masonry Wall/Backfill 9/23/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/26/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/27/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 9/28/2022 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 9/28/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 9/30/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/11/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 10/12/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 10/12/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 10/12/2022 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 10/12/2022 No Access for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 10/12/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 10/14/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 10/14/2022 Approved EDWIN GREGORYONA
METHANE-Subgrade 10/14/2022 Approved EDWIN GREGORYONA
Pre-Inspection 10/18/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 11/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 11/19/2022 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 11/19/2022 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 11/19/2022 Approved DAVID BURKHEAD
Reinforced Concrete Frame 11/19/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 11/19/2022 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Not Ready for Inspection GREGORY POMISH
Deputy Wood Construction 12/21/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 12/22/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 12/22/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 12/22/2022 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 12/22/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 12/22/2022 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/27/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 1/27/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 1/27/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 1/27/2023 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/19/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/5/2023 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/9/2023 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/15/2023 Partial Inspection EDWIN GREGORYONA
Deputy Steel/Welding 5/19/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/22/2023 Conditional Approval MICHAEL ROSENBERG
Interior/Exterior Lathing 6/29/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 6/30/2023 Approved EDWIN GREGORYONA
Insulation 6/30/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 6/30/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 6/30/2023 Approved EDWIN GREGORYONA
Wood Frame 6/30/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 7/14/2023 Not Ready for Inspection ALAN MORELOS
Wood Frame 7/17/2023 Partial Approval EDWIN GREGORYONA
Insulation 7/21/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/25/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 7/25/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 8/4/2023 Partial Approval JEROME BLACKWOOD
Insulation 8/4/2023 Partial Approval JEROME BLACKWOOD
Deputy Steel/Welding 8/14/2023 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/16/2023 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/17/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/18/2023 Partial Approval EDWIN GREGORYONA
Insulation 8/18/2023 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 8/28/2023 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/28/2023 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 8/30/2023 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/30/2023 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 9/5/2023 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/5/2023 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 9/6/2023 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/6/2023 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 9/7/2023 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/7/2023 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 9/8/2023 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/8/2023 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 9/11/2023 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 9/11/2023 Conditional Approval GREGORY POMISH
Drywall Nailing 9/15/2023 Partial Approval GREGORY POMISH
Drywall Nailing 10/6/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 10/13/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/19/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/1/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 11/16/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/17/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 11/21/2023 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 11/28/2023 Partial Approval RICARDO ROBLES
Drywall Nailing 12/13/2023 Partial Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 12/13/2023 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 12/14/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 12/27/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/3/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 1/5/2024 Partial Inspection JEROME BLACKWOOD
Interior/Exterior Lathing 1/5/2024 Approved JEROME BLACKWOOD
Drywall Nailing 1/18/2024 Partial Approval EDWIN GREGORYONA
Insulation 2/28/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/7/2024 Approved EDWIN GREGORYONA
Special/Order Compliance 6/24/2024 Approved EDWIN GREGORYONA
Special/Order Compliance 6/27/2024 Approved EDWIN GREGORYONA
Special/Order Compliance 7/3/2024 Approved EDWIN GREGORYONA
Special/Order Compliance 7/12/2024 Approved EDWIN GREGORYONA
Special/Order Compliance 7/17/2024 Approved EDWIN GREGORYONA
Final 9/3/2024 OK to Issue CofO EDWIN GREGORYONA
Footing/Foundation/Slab 9/3/2024 Approved EDWIN GREGORYONA
Green Building Final 9/3/2024 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 9/3/2024 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 9/3/2024 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 9/3/2024 Approved EDWIN GREGORYONA
Wood Frame 9/3/2024 Approved EDWIN GREGORYONA