1105 W 73RD ST 90044

Certificate Information: 1105 W 73RD ST 90044

Application / Permit
21010-10000-01701
Plan Check / Job No.
B21LA06431
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW TWO STORY ADU AT REAR OF LOT.
Permit Issued
Issued on 8/26/2021
Issuing Office
Current Status
CofO Issued on 5/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 JOE VO
Corrections Issued 4/24/2021 JOE VO
Quality Review Completed 5/4/2021 MICHAEL PEREZ
Applicant returned to address corrections 6/7/2021 JOE VO
Applicant returned to address corrections 8/17/2021 JOE VO
Plan Check Approved 8/18/2021 JOE VO
Issued 8/26/2021 APPLICANT
CofO in Progress 3/10/2022 LILIANA PORTILLO
Permit Finaled 5/7/2022 DEROLD HAUFF
CofO Issued 5/7/2022 DEROLD HAUFF
Permit Finaled 5/7/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/11/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 6/23/2021 STEVE MELGAR
Sewer availability Cleared 6/23/2021 STEVE MELGAR
Hydrant and Access approval Cleared 6/24/2021 JOHN CONNEALLY
Low Impact Development Cleared 8/5/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/9/2021 STEVE MELGAR

Contact Information

Contractor Monroy M W Construction Inc; Lic. No.: 1066342-B 710 W 66TH ST      LOS ANGELES, CA 90044
Engineer Li,, Dacheng David; Lic. No.: NA58075       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/31/2021 Partial Approval ANSON MAGLASANG
Footing/Foundation/Slab 9/3/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Corrections Issued DAVID FEILER
Deputy Wood Construction 9/27/2021 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Approved ALAN MORELOS
ELECTRICAL-Rough 10/8/2021 Approved ALIZAH MAYAGOITIA
HVAC-Rough 10/8/2021 Corrections Issued ALIZAH MAYAGOITIA
Insulation 10/8/2021 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/8/2021 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 10/8/2021 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/18/2021 Partial Approval HORACE FULTZ
Insulation 10/18/2021 Approved HORACE FULTZ
Verify Sprinkler Sign Off 10/18/2021 Not Ready for Inspection HORACE FULTZ
Drywall Nailing 10/21/2021 Approved AMY COLIN
HVAC-Rough 10/21/2021 Approved AMY COLIN
Shower Pan 10/21/2021 Approved AMY COLIN
Interior/Exterior Lathing 10/25/2021 Approved FREDDIE RIVERA
Underground Mechanical 12/13/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/23/2021 Corrections Issued HORACE FULTZ
Final 12/23/2021 Not Ready for Inspection HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 12/23/2021 SGSOV Not Ready HORACE FULTZ
Service/Power Release 12/23/2021 Not Ready for Inspection HORACE FULTZ
Smoke Detectors 12/23/2021 Approved HORACE FULTZ
BUILDING-Rough-Frame 12/29/2021 Corrections Issued SABAS ALONSO
Final 12/29/2021 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/29/2021 SGSOV Not Ready SABAS ALONSO
Service/Power Release 12/29/2021 Not Required SABAS ALONSO
BUILDING-Rough-Frame 1/20/2022 Approved ANTHONY EGSON
Final 1/20/2022 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Approved ANTHONY EGSON
ELECTRICAL-Final 1/25/2022 Approved LILIANA PORTILLO
HVAC-Final 1/25/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 1/25/2022 Approved LILIANA PORTILLO
Final 2/10/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 2/10/2022 Approved ALIZAH MAYAGOITIA
Final 3/9/2022 OK to Issue CofO LILIANA PORTILLO