11234-11236 N PHILLIPPI AVE 91331
Certificate Information: 11234-11236 N PHILLIPPI AVE 91331
- Application / Permit
- 21010-10000-01698
- Plan Check / Job No.
- B21LA06428
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADU ADDITION TO (E) SFD TO CREATE ATTACHED ADU (2-STORY) PER ORDINANCE and New covered portch at rear and east side of the building.
- Permit Issued
- Issued on 2/8/2022
- Issuing Office
- Current Status
- CofO Issued on 12/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | CARLOS MONTES |
| Corrections Issued | 5/15/2021 | CARLOS MONTES |
| Quality Review Completed | 5/20/2021 | WING SUEN |
| Plan Check Approved | 2/2/2022 | CARLOS MONTES |
| Issued | 2/8/2022 | APPLICANT |
| CofO in Progress | 9/29/2023 | MICHEL ABAJAN |
| Permit Finaled | 12/4/2023 | RUBEN SALAS |
| CofO Issued | 12/4/2023 | RUBEN SALAS |
| Permit Finaled | 12/4/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 6/28/2021 | BRIAN MILLER |
| Sewer availability | Cleared | 8/4/2021 | ABDULLAH SADOZAI |
| Low Impact Development | Cleared | 10/22/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 2/2/2022 | CARLOS MONTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/22/2022 | No Access for Inspection | MICHEL ABAJAN |
| Pre-Inspection | 4/8/2022 | Corrections Issued | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 4/18/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/26/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/5/2022 | Approved | MICHEL ABAJAN |
| Deputy Reinf. Concrete | 5/11/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 7/27/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Wood Construction | 8/2/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/14/2022 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/14/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/14/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 9/14/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 9/14/2022 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/4/2022 | Conditional Approval | MICHEL ABAJAN |
| Green Building Rough | 10/4/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 10/4/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/4/2022 | Approved | MICHEL ABAJAN |
| Insulation | 11/7/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/7/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/10/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 12/2/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 12/20/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/21/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/26/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/26/2023 | Corrections Issued | MICHEL ABAJAN |
| Final | 6/26/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 6/26/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/26/2023 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Final | 6/26/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/26/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 6/26/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 6/26/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 9/22/2023 | Approved | MICHEL ABAJAN |
| Final | 9/22/2023 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 9/22/2023 | Approved | MICHEL ABAJAN |
| Final | 9/29/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 9/29/2023 | Approved | MICHEL ABAJAN |