11234-11236 N PHILLIPPI AVE 91331

Certificate Information: 11234-11236 N PHILLIPPI AVE 91331

Application / Permit
21010-10000-01698
Plan Check / Job No.
B21LA06428
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADU ADDITION TO (E) SFD TO CREATE ATTACHED ADU (2-STORY) PER ORDINANCE and New covered portch at rear and east side of the building.
Permit Issued
Issued on 2/8/2022
Issuing Office
Current Status
CofO Issued on 12/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 CARLOS MONTES
Corrections Issued 5/15/2021 CARLOS MONTES
Quality Review Completed 5/20/2021 WING SUEN
Plan Check Approved 2/2/2022 CARLOS MONTES
Issued 2/8/2022 APPLICANT
CofO in Progress 9/29/2023 MICHEL ABAJAN
Permit Finaled 12/4/2023 RUBEN SALAS
CofO Issued 12/4/2023 RUBEN SALAS
Permit Finaled 12/4/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/16/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/16/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 6/28/2021 BRIAN MILLER
Sewer availability Cleared 8/4/2021 ABDULLAH SADOZAI
Low Impact Development Cleared 10/22/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/17/2021 DAGOVERTO GUERRERO
GPI Written Notices Cleared 2/2/2022 CARLOS MONTES

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/22/2022 No Access for Inspection MICHEL ABAJAN
Pre-Inspection 4/8/2022 Corrections Issued MICHEL ABAJAN
Deputy Drilled-In Anchors 4/18/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 4/26/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 5/5/2022 Approved MICHEL ABAJAN
Deputy Reinf. Concrete 5/11/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Partial Approval MISAEL ESPARZA
Green Building Rough 7/27/2022 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 8/2/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/14/2022 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 9/14/2022 Approved MICHEL ABAJAN
Green Building Rough 9/14/2022 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 9/14/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 9/14/2022 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 10/4/2022 Conditional Approval MICHEL ABAJAN
Green Building Rough 10/4/2022 Approved MICHEL ABAJAN
HVAC-Rough 10/4/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 10/4/2022 Approved MICHEL ABAJAN
Insulation 11/7/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/7/2022 Approved MICHEL ABAJAN
Drywall Nailing 11/10/2022 Approved MICHEL ABAJAN
Shower Pan 12/2/2022 Corrections Issued JENNIFER RABUCHIN
Shower Pan 12/20/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/21/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/26/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/26/2023 Corrections Issued MICHEL ABAJAN
Final 6/26/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 6/26/2023 Approved MICHEL ABAJAN
HVAC-Final 6/26/2023 Corrections Issued MICHEL ABAJAN
PLUMBING-Final 6/26/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 6/26/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 6/26/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 9/22/2023 Approved MICHEL ABAJAN
Final 9/22/2023 Corrections Issued MICHEL ABAJAN
HVAC-Final 9/22/2023 Approved MICHEL ABAJAN
Final 9/29/2023 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 9/29/2023 Approved MICHEL ABAJAN