3594 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3594 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 21010-10000-01694
- Plan Check / Job No.
- B21LA06389
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING WITH BASEMENT
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 11/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | DANIEL YIP |
| Corrections Issued | 4/27/2021 | DANIEL YIP |
| Quality Review Completed | 4/28/2021 | JASON HEALEY |
| Applicant returned to address corrections | 7/9/2021 | DANIEL YIP |
| Applicant returned to address corrections | 7/21/2021 | DANIEL YIP |
| Plan Check Approved | 10/20/2021 | DANIEL YIP |
| Issued | 11/1/2021 | APPLICANT |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| CofO in Progress | 11/6/2023 | KENNETH NAGLE |
| Permit Finaled | 11/7/2023 | DANIEL ORRANTE |
| CofO Issued | 11/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hold | Cleared | 4/26/2021 | JASON SHEETS |
| Sewer availability | Cleared | 6/21/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2021 | DENNIS BRAGIN |
| GPI Written Notices | Cleared | 7/9/2021 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 7/9/2021 | DANIEL YIP |
| Permit | Cleared | 7/16/2021 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 7/27/2021 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 8/30/2021 | JOHN CONNEALLY |
| Specific Plan | Cleared | 8/31/2021 | PEDRO AYALA |
| Trees in Parkway | Cleared | 9/22/2021 | JOEL HERNANDEZ |
| Low Impact Development | Cleared | 9/29/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 10/19/2021 | OSCAR GUTIERREZ |
Contact Information
| Contractor | Onmark Builders; Lic. No.: 1061309-B | 5907 RHODES AVE VALLEY VILLAGE, CA 91607 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
| Engineer | Rowlands,, James; Lic. No.: C21818 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Engineer | Vondra,, Thomas Edwin; Lic. No.: L8761 | 4717 W AVE M-8 QUARTZ HILL, CA 93536 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/2/2021 | Conditional Approval | JOHNNY MIRANDA |
| Piling/Pier/Caisson | 11/4/2021 | Partial Approval | JOHNNY MIRANDA |
| Pre-Inspection | 11/4/2021 | Approved | JOHNNY MIRANDA |
| Deputy Steel/Welding | 11/15/2021 | Conditional Approval | JOHNNY MIRANDA |
| Grading Pre-Inspection | 11/18/2021 | Corrections Issued | JOHNNY MIRANDA |
| Special/Order Compliance | 11/18/2021 | Corrections Issued | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 11/22/2021 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 2/1/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 2/1/2022 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 2/1/2022 | Corrections Issued | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 2/9/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 2/11/2022 | No Access for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/24/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/28/2022 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/17/2022 | Partial Approval | KENNETH NAGLE |
| Reinforced Concrete Frame | 3/17/2022 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 4/4/2022 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 4/4/2022 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 6/21/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/21/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 6/23/2022 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 6/23/2022 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 6/24/2022 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 7/1/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 7/26/2022 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 1/13/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 1/13/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/13/2023 | Conditional Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 1/17/2023 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 1/17/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/17/2023 | Approved | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 1/17/2023 | Approved | JOHNNY MIRANDA |
| Shower Pan | 1/20/2023 | Approved | JOHNNY MIRANDA |
| Deputy Steel/Welding | 1/23/2023 | Conditional Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/25/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 1/26/2023 | Not Ready for Inspection | JULIAN AMAYA |
| Insulation | 1/26/2023 | Not Ready for Inspection | JULIAN AMAYA |
| Insulation | 1/30/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 1/31/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 2/9/2023 | Approved | JESUS RODRIGUEZ |
| Final | 2/9/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Sewer | 4/11/2023 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 4/11/2023 | Approved | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 6/22/2023 | Partial Approval | JOHNNY MIRANDA |
| Reinforced Masonry Frame | 6/22/2023 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 6/28/2023 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/28/2023 | Approved | JOHNNY MIRANDA |
| Reinforced Masonry Frame | 7/11/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 8/4/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/4/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 8/8/2023 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 8/8/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 9/5/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 9/5/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/2/2023 | Approved | KENNETH NAGLE |
| Final | 10/2/2023 | Corrections Issued | KENNETH NAGLE |
| Green Building Final | 10/2/2023 | Approved | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 10/2/2023 | SGSOV Approved | KENNETH NAGLE |
| Service/Power Release | 10/2/2023 | Approved | KENNETH NAGLE |
| Smoke Detectors | 10/2/2023 | Approved | KENNETH NAGLE |
| Final | 11/6/2023 | OK to Issue CofO | KENNETH NAGLE |