2698 W WAVERLY DR 90039

Certificate Information: 2698 W WAVERLY DR 90039

Application / Permit
21010-10000-01656
Plan Check / Job No.
B21LA06270
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY ADU PER LAMC 12.22A.33 (c)-(d) WITH ROOF DECK
Permit Issued
Issued on 1/14/2022
Issuing Office
Current Status
CofO Issued on 10/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 MAHNAZ NOURHASHEMI
Corrections Issued 5/14/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 5/18/2021 JASON HEALEY
Plan Check Approved 12/17/2021 MAHNAZ NOURHASHEMI
Issued 1/14/2022 APPLICANT
CofO in Progress 10/4/2023 THOMAS LOGRASSO
Permit Finaled 10/8/2023 DEROLD HAUFF
CofO Issued 10/8/2023 DEROLD HAUFF
Permit Finaled 10/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/22/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/23/2021 STEVE MELGAR
Sewer availability Cleared 6/23/2021 STEVE MELGAR
Hydrant and Access approval Cleared 10/22/2021 KURT CORRAL
Low Impact Development Cleared 11/30/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 12/8/2021 TREVOR QUAN
Grading Pre-Inspection Cleared 12/9/2021 BRIAN MILLER

Contact Information

Contractor Ground Up Builders And Design Inc; Lic. No.: 911849-B 14545 VICTORY BLVD STE 601      VAN NUYS, CA 91411

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/17/2022 Partial Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 5/6/2022 Not Ready for Inspection THOMAS LOGRASSO
Special/Order Compliance 5/13/2022 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 7/15/2022 Partial Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 8/26/2022 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 8/26/2022 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 9/7/2022 Conditional Approval THOMAS LOGRASSO
PLUMBING-Rough 9/16/2022 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 9/21/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 10/27/2022 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 10/27/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 10/27/2022 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 10/31/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Corrections Issued THOMAS LOGRASSO
Deputy Wood Construction 11/22/2022 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 12/12/2022 Approved THOMAS LOGRASSO
HVAC-Rough 12/12/2022 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 12/28/2022 Approved THOMAS LOGRASSO
Green Building Rough 12/28/2022 Approved THOMAS LOGRASSO
HVAC-Rough 12/28/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 12/28/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 12/28/2022 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 12/28/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 1/13/2023 Partial Approval THOMAS LOGRASSO
Shower Pan 1/13/2023 Approved THOMAS LOGRASSO
Insulation 1/18/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 1/18/2023 Approved THOMAS LOGRASSO
Drywall Nailing 1/31/2023 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 4/25/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 4/25/2023 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 4/25/2023 Not Ready for Inspection THOMAS LOGRASSO
Underground Mechanical 6/15/2023 Partial Approval THOMAS LOGRASSO
Pre-Inspection 8/2/2023 Partial Inspection THOMAS LOGRASSO
ELECTRICAL-Final 8/24/2023 Corrections Issued THOMAS LOGRASSO
Final 9/12/2023 Corrections Issued THOMAS LOGRASSO
Green Building Final 9/12/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Not Ready THOMAS LOGRASSO
Service/Power Release 9/12/2023 Not Required THOMAS LOGRASSO
Smoke Detectors 9/12/2023 Approved THOMAS LOGRASSO
Final 9/20/2023 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 9/20/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 9/20/2023 SGSOV Approved THOMAS LOGRASSO
Deputy Drilled-In Anchors 9/28/2023 Conditional Approval THOMAS LOGRASSO
Final 10/4/2023 OK to Issue CofO THOMAS LOGRASSO