2698 W WAVERLY DR 90039
Certificate Information: 2698 W WAVERLY DR 90039
- Application / Permit
- 21010-10000-01656
- Plan Check / Job No.
- B21LA06270
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1 STORY ADU PER LAMC 12.22A.33 (c)-(d) WITH ROOF DECK
- Permit Issued
- Issued on 1/14/2022
- Issuing Office
- Current Status
- CofO Issued on 10/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 5/14/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 5/18/2021 | JASON HEALEY |
| Plan Check Approved | 12/17/2021 | MAHNAZ NOURHASHEMI |
| Issued | 1/14/2022 | APPLICANT |
| CofO in Progress | 10/4/2023 | THOMAS LOGRASSO |
| Permit Finaled | 10/8/2023 | DEROLD HAUFF |
| CofO Issued | 10/8/2023 | DEROLD HAUFF |
| Permit Finaled | 10/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 6/23/2021 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 10/22/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 11/30/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 12/8/2021 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 12/9/2021 | BRIAN MILLER |
Contact Information
| Contractor | Ground Up Builders And Design Inc; Lic. No.: 911849-B | 14545 VICTORY BLVD STE 601 VAN NUYS, CA 91411 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/17/2022 | Partial Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/6/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 5/13/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/15/2022 | Partial Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 8/26/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/26/2022 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/7/2022 | Conditional Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/16/2022 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/21/2022 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/27/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/27/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/27/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/31/2022 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Wood Construction | 11/22/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 12/12/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 12/12/2022 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/28/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 12/28/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 12/28/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/28/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/28/2022 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 12/28/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/13/2023 | Partial Approval | THOMAS LOGRASSO |
| Shower Pan | 1/13/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 1/18/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/18/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 1/31/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 4/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 4/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Shower Pan | 4/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Underground Mechanical | 6/15/2023 | Partial Approval | THOMAS LOGRASSO |
| Pre-Inspection | 8/2/2023 | Partial Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 8/24/2023 | Corrections Issued | THOMAS LOGRASSO |
| Final | 9/12/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 9/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 9/12/2023 | Not Required | THOMAS LOGRASSO |
| Smoke Detectors | 9/12/2023 | Approved | THOMAS LOGRASSO |
| Final | 9/20/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 9/20/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 9/28/2023 | Conditional Approval | THOMAS LOGRASSO |
| Final | 10/4/2023 | OK to Issue CofO | THOMAS LOGRASSO |