5409 N MORELLA AVE 91607

Certificate Information: 5409 N MORELLA AVE 91607

Application / Permit
21010-10000-01628
Plan Check / Job No.
B21LA06157
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3 STORY SFD WITH ATTACHED GARAGE. CONSTRUCTION IS PART OF SMALL LOT SUBDIVISION FOR 4 UNITS. MODEL A
Permit Issued
Issued on 12/15/2021
Issuing Office
Metro
Current Status
CofO Issued on 3/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 JOE VO
Corrections Issued 5/3/2021 JOE VO
Quality Review Completed 5/10/2021 MICHAEL PEREZ
Building Plans Picked Up 6/24/2021 APPLICANT
Applicant returned to address corrections 7/12/2021 JOE VO
Plan Check Approved 11/18/2021 JOE VO
Issued 12/15/2021 APPLICANT
CofO in Progress 1/9/2024 KIRK SANDERS
Permit Finaled 3/23/2024 RUBEN SALAS
CofO Issued 3/23/2024 RUBEN SALAS
Permit Finaled 3/23/2024 RUBEN SALAS

Permit Application Clearance Information

"Q" conditions Cleared 5/18/2021 LAUREN PADICK
Miscellaneous Cleared 5/18/2021 LAUREN PADICK
Specific Plan Cleared 5/18/2021 LAUREN PADICK
ZA Case Cleared 5/18/2021 LAUREN PADICK
Address approval Cleared 5/24/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/24/2021 LEE GUILBEAUX
Permit Cleared 5/24/2021 LEE GUILBEAUX
Sewer availability Cleared 5/24/2021 LEE GUILBEAUX
Low Impact Development Cleared 7/12/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/16/2021 JOHN LIN
Hydrant and Access approval Cleared 7/27/2021 MATTHEW CRAIG
Trees in Parkway Cleared 8/12/2021 JOHN KIM
Construction near power lines Cleared 10/29/2021 RIDWAN HARDY
Construction near power lines Cleared 10/29/2021 RIDWAN HARDY

Contact Information

Architect Tsang,, Eric Chi Wang; Lic. No.: C38568 2550 CASALERO DR      LA HABRA HEIGHTS, CA 90631
Contractor Owner-Builder       ,
Engineer Bharil,, Rajneesh Kumar; Lic. No.: S6069 8835 EAST FALLBROOK WAY      ANAHEIM, CA 92808
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/16/2022 Partial Approval HENRY KIM
Sewer 3/16/2022 Corrections Issued HENRY KIM
Reinforced Concrete Frame 4/4/2022 Not Ready for Inspection THOMAS FINNILA
Reinforced Concrete Frame 4/8/2022 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 4/19/2022 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 4/27/2022 Partial Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 4/29/2022 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 5/5/2022 Conditional Approval DAVID MATSON
Deputy Reinf. Concrete 5/19/2022 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 5/19/2022 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 5/23/2022 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 6/24/2022 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 6/28/2022 Conditional Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 7/1/2022 Partial Approval THOMAS FINNILA
Deputy Wood Construction 7/7/2022 Partial Approval MATT KELLERMAN
Deputy Wood Construction 7/15/2022 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Partial Approval THOMAS FINNILA
Deputy Wood Construction 7/21/2022 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Partial Approval THOMAS FINNILA
Deputy Wood Construction 9/2/2022 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/6/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Partial Approval ALAN MORELOS
Interior/Exterior Lathing 10/6/2022 Corrections Issued DEANDRE HOFFMAN
Interior/Exterior Lathing 10/7/2022 Partial Inspection DEANDRE HOFFMAN
BUILDING-Rough-Frame 10/17/2022 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 10/17/2022 Approved JACK KARGODORIAN
Green Building Rough 10/17/2022 Approved JACK KARGODORIAN
HVAC-Rough 10/17/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 10/17/2022 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 10/17/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 11/15/2022 Not Ready for Inspection JACK KARGODORIAN
Shower Pan 11/15/2022 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 11/29/2022 Approved JACK KARGODORIAN
Shower Pan 11/29/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 12/5/2022 Approved JACK KARGODORIAN
Insulation 12/5/2022 Approved JACK KARGODORIAN
Drywall Nailing 12/16/2022 Approved JACK KARGODORIAN
Insulation 12/16/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/16/2022 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 12/21/2022 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 12/27/2022 Partial Approval JACK KARGODORIAN
Gas Test 5/5/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 5/5/2023 Approved MISAEL ESPARZA
Sewer 5/5/2023 Approved MISAEL ESPARZA
Pre-Inspection 7/3/2023 Partial Inspection DAVID MATSON
Service/Power Release 7/7/2023 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/25/2023 SGSOV Approved JUAN VALENZUELA
ELECTRICAL-Final 11/22/2023 Corrections Issued JOHN COLEMAN
ELECTRICAL-Final 11/28/2023 Approved KEVIN BERBERYAN
PLUMBING-Final 11/28/2023 Approved KEVIN BERBERYAN
HVAC-Final 11/30/2023 Approved OGANES TARAKHCHYAN
Final 12/11/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 12/11/2023 Approved KIRK SANDERS
Green Building Final 12/11/2023 Approved KIRK SANDERS
Service/Power Release 12/11/2023 Approved KIRK SANDERS
Smoke Detectors 12/11/2023 Approved KIRK SANDERS
Final 1/8/2024 OK to Issue CofO KIRK SANDERS