5365 N PENFIELD AVE 91364
Certificate Information: 5365 N PENFIELD AVE 91364
- Application / Permit
- 21010-10000-01615
- Plan Check / Job No.
- B21LA06092
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEw ADU. New 529 s.f. ADU.
- Permit Issued
- Issued on 8/5/2022
- Issuing Office
- Current Status
- Issued on 5/5/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | JOE VO |
| Corrections Issued | 4/25/2021 | JOE VO |
| Plans on Hold | 5/4/2021 | MICHAEL PEREZ |
| Hold Released | 5/5/2021 | MICHAEL PEREZ |
| Quality Review Completed | 5/5/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 7/13/2021 | JOE VO |
| Applicant returned to address corrections | 8/31/2021 | JOE VO |
| Applicant returned to address corrections | 7/18/2022 | JOE VO |
| Plan Check Approved | 7/28/2022 | JOE VO |
| Issued | 8/5/2022 | APPLICANT |
| CofO in Progress | 1/31/2023 | PETER FOLLING |
| No Progress | 5/5/2023 | JOHN JANSON |
Permit Application Clearance Information
| Hold | Cleared | 5/5/2021 | JASON SHEETS |
| Address approval | Cleared | 6/1/2021 | CARLOS AGUILERA |
| Watercourse | Cleared | 6/1/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 7/14/2022 | SUNG JOON WON |
| Sewer availability | Cleared | 7/18/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/20/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 7/28/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/26/2022 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/7/2022 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 9/7/2022 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 9/30/2022 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 9/30/2022 | Approved | DAVID SANDOVAL |
| Shower Pan | 9/30/2022 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 9/30/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 10/7/2022 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 10/7/2022 | Partial Approval | SEAN WIRCH |
| Wood Frame | 10/7/2022 | Approved | SEAN WIRCH |
| Insulation | 10/14/2022 | Conditional Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 10/14/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 10/18/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 10/21/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 12/19/2022 | Partial Approval | PETER FOLLING |
| Final | 12/19/2022 | Corrections Issued | PETER FOLLING |
| Green Building Final | 12/19/2022 | Approved | PETER FOLLING |
| Green Building Rough | 12/19/2022 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Approved | PETER FOLLING |
| Service/Power Release | 12/19/2022 | Not Ready for Inspection | PETER FOLLING |
| Smoke Detectors | 12/19/2022 | Approved | PETER FOLLING |
| Verify Sprinkler Sign Off | 12/19/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 1/25/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 1/25/2023 | Corrections Issued | DAVID SANDOVAL |
| Service/Power Release | 1/25/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 1/30/2023 | Approved | PETER FOLLING |
| Final | 1/30/2023 | OK to Issue CofO | PETER FOLLING |
| Service/Power Release | 1/30/2023 | Approved | PETER FOLLING |
| Special/Order Compliance | 2/16/2023 | Corrections Issued | PETER FOLLING |