5365 N PENFIELD AVE 91364

Certificate Information: 5365 N PENFIELD AVE 91364

Application / Permit
21010-10000-01615
Plan Check / Job No.
B21LA06092
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEw ADU. New 529 s.f. ADU.
Permit Issued
Issued on 8/5/2022
Issuing Office
Current Status
Issued on 5/5/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 JOE VO
Corrections Issued 4/25/2021 JOE VO
Plans on Hold 5/4/2021 MICHAEL PEREZ
Hold Released 5/5/2021 MICHAEL PEREZ
Quality Review Completed 5/5/2021 MICHAEL PEREZ
Applicant returned to address corrections 7/13/2021 JOE VO
Applicant returned to address corrections 8/31/2021 JOE VO
Applicant returned to address corrections 7/18/2022 JOE VO
Plan Check Approved 7/28/2022 JOE VO
Issued 8/5/2022 APPLICANT
CofO in Progress 1/31/2023 PETER FOLLING
No Progress 5/5/2023 JOHN JANSON

Permit Application Clearance Information

Hold Cleared 5/5/2021 JASON SHEETS
Address approval Cleared 6/1/2021 CARLOS AGUILERA
Watercourse Cleared 6/1/2021 CARLOS AGUILERA
Low Impact Development Cleared 7/14/2022 SUNG JOON WON
Sewer availability Cleared 7/18/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/20/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/27/2022 CARLOS AGUILERA
Miscellaneous Cleared 7/28/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/26/2022 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 9/7/2022 Approved DAVID SANDOVAL
Underground Mechanical 9/7/2022 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 9/30/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 9/30/2022 Partial Approval DAVID SANDOVAL
PLUMBING-Rough 9/30/2022 Approved DAVID SANDOVAL
Shower Pan 9/30/2022 Approved DAVID SANDOVAL
Underground Mechanical 9/30/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 10/7/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 10/7/2022 Partial Approval SEAN WIRCH
Wood Frame 10/7/2022 Approved SEAN WIRCH
Insulation 10/14/2022 Conditional Approval JESUS PINEDA
Interior/Exterior Lathing 10/14/2022 Approved JESUS PINEDA
Drywall Nailing 10/18/2022 Approved VINCENT HANLEY
Drywall Nailing 10/21/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 12/19/2022 Partial Approval PETER FOLLING
Final 12/19/2022 Corrections Issued PETER FOLLING
Green Building Final 12/19/2022 Approved PETER FOLLING
Green Building Rough 12/19/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Approved PETER FOLLING
Service/Power Release 12/19/2022 Not Ready for Inspection PETER FOLLING
Smoke Detectors 12/19/2022 Approved PETER FOLLING
Verify Sprinkler Sign Off 12/19/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 1/25/2023 Not Ready for Inspection DAVID SANDOVAL
Final 1/25/2023 Corrections Issued DAVID SANDOVAL
Service/Power Release 1/25/2023 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 1/30/2023 Approved PETER FOLLING
Final 1/30/2023 OK to Issue CofO PETER FOLLING
Service/Power Release 1/30/2023 Approved PETER FOLLING
Special/Order Compliance 2/16/2023 Corrections Issued PETER FOLLING