2005 W 42ND PL 90062

Certificate Information: 2005 W 42ND PL 90062

Application / Permit
21010-10000-01614
Plan Check / Job No.
B21LA06091
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan ADU** New Accessory dwelling unit by Installing a RADCO Approved Factory Built Housing Unit over a raised floor foundation. FBH Per: RAD-31-1029. RADCO Stamped FBH Plans per Ordinance
Permit Issued
Issued on 8/13/2021
Issuing Office
Current Status
CofO Issued on 7/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2021 APPLICANT
Assigned to Plan Check Engineer 4/7/2021 MONICA RAMIREZ
Corrections Issued 4/7/2021 MONICA RAMIREZ
Applicant returned to address corrections 7/1/2021 CARLOS MONTES
Plan Check Approved 8/10/2021 MONICA RAMIREZ
Plan Check Approved 8/12/2021 MONICA RAMIREZ
Issued 8/13/2021 APPLICANT
CofO in Progress 6/29/2022 SABAS ALONSO
Permit Finaled 7/9/2022 DEROLD HAUFF
Permit Finaled 7/9/2022 DEROLD HAUFF
CofO Issued 7/9/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/13/2021 THOMAS LANG
Sewer availability Cleared 4/15/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 6/24/2021 THOMAS LANG
Low Impact Development Cleared 6/24/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/24/2021 THOMAS LANG
Construction near power lines Cleared 8/9/2021 TORI CHEN

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B       ,
Engineer Farish,, William Crawford; Lic. No.: C30123 19432 CASTLEWOOD CR      HUNTINGTON BEACH, CA 92648
Engineer Sveiven,, Shane; Lic. No.: C89133 5900 CANTERBURY DR APT A206      CULVER CITY, CA 90230

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/8/2021 Approved SABAS ALONSO
Sewer 9/17/2021 Approved HORACE FULTZ
Underground Mechanical 9/17/2021 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 9/24/2021 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 9/30/2021 Approved SABAS ALONSO
Underground Mechanical 9/30/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/19/2021 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 10/19/2021 Approved SABAS ALONSO
Wood Frame 10/21/2021 Approved SABAS ALONSO
HVAC-Rough 10/28/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/7/2021 Approved SABAS ALONSO
ELECTRICAL-Final 12/7/2021 Approved SABAS ALONSO
Final 12/7/2021 Corrections Issued SABAS ALONSO
HVAC-Final 12/7/2021 Approved SABAS ALONSO
PLUMBING-Final 12/7/2021 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/7/2021 SGSOV Approved SABAS ALONSO
Service/Power Release 12/7/2021 Not Required SABAS ALONSO
Smoke Detectors 12/7/2021 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 12/15/2021 Approved SABAS ALONSO
Final 12/15/2021 Conditional Approval SABAS ALONSO
Smoke Detectors 12/15/2021 Approved SABAS ALONSO
Final 4/15/2022 Not Ready for Inspection SABAS ALONSO
Final 6/28/2022 OK to Issue CofO SABAS ALONSO