979 E LAKE ST 90291

Certificate Information: 979 E LAKE ST 90291

Application / Permit
21010-10000-01599
Plan Check / Job No.
B21LA06076
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW CONSTRUCTION OF A 2-STORY 1170 SF ADU AT REAR YARD CONSISTING OF A 2BD/2BA. 2 OF 2
Permit Issued
Issued on 9/13/2022
Issuing Office
Current Status
CofO Issued on 1/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 SERGIO GUTIERREZ
Corrections Issued 4/20/2021 SERGIO GUTIERREZ
Quality Review Completed 4/22/2021 FARUK SEZER
Applicant returned to address corrections 3/18/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 8/23/2022 SERGIO GUTIERREZ
Plan Check Approved 8/30/2022 SERGIO GUTIERREZ
Issued 9/13/2022 APPLICANT
Building Plans Picked Up 9/15/2022 APPLICANT
CofO in Progress 1/24/2024 HERBERT GIRON
Permit Finaled 1/30/2024 DANIEL ORRANTE
CofO Issued 1/30/2024 DANIEL ORRANTE
Permit Finaled 1/30/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/22/2021 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 10/22/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 11/2/2021 ANTHONY MAINEZ
Sewer availability Cleared 11/2/2021 ANTHONY MAINEZ
Hydrant and Access approval Cleared 1/13/2022 KURT CORRAL
Specific Plan Cleared 1/24/2022 FREDDY GARCIA
Low Impact Development Cleared 7/28/2022 ROGELIO CORTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/4/2022 Not Ready for Inspection DAVID FEILER
Underground Mechanical 10/4/2022 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 10/12/2022 Approved DAVID FEILER
Footing/Foundation/Slab 10/12/2022 Approved DAVID FEILER
Underground Mechanical 10/12/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Partial Approval DAVID FEILER
Special/Order Compliance 10/26/2022 Partial Inspection CLAYTON GRAHAM
Deputy Wood Construction 12/8/2022 Conditional Approval EVAN COOPER
Pre-Inspection 2/2/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 3/16/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Partial Approval EVAN COOPER
Interior/Exterior Lathing 5/30/2023 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 8/9/2023 Corrections Issued HERBERT GIRON
Green Building Rough 8/9/2023 Approved HERBERT GIRON
Verify Sprinkler Sign Off 8/9/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 8/10/2023 Approved EVAN COOPER
PLUMBING-Rough 8/10/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 8/14/2023 Approved HERBERT GIRON
Final 8/14/2023 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 8/22/2023 Approved HERBERT GIRON
Shower Pan 8/22/2023 Approved HERBERT GIRON
Insulation 8/25/2023 Corrections Issued BEN MOLSTAD
Insulation 8/29/2023 Partial Approval TEMISTOCLES CAAL
Drywall Nailing 9/6/2023 Approved HERBERT GIRON
ELECTRICAL-Final 1/4/2024 Approved HERBERT GIRON
Final 1/4/2024 Corrections Issued HERBERT GIRON
Gas Test 1/4/2024 Approved HERBERT GIRON
Green Building Final 1/4/2024 Approved HERBERT GIRON
HVAC-Final 1/4/2024 Approved HERBERT GIRON
PLUMBING-Final 1/4/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/4/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 1/4/2024 Approved HERBERT GIRON
Final 1/23/2024 OK to Issue CofO HERBERT GIRON