14811 W ERWIN ST 1-33 91411

Certificate Information: 14811 W ERWIN ST 1-33 91411

Application / Permit
21010-10000-01571
Plan Check / Job No.
B21LA06041
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5 STORY 33 UNITS (4 EXTREMELY LOW INCOME UNITS) AFFORDABLE HOUSING APARTMENT TO INCLUDE 4 STORY TYPE VA APARTMENT OVER 1 STORY TYPE 1A PARKING GARAGE, TOC TIER 3 WITH ADDITIONAL INCENTIVES
Permit Issued
Issued on 11/15/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 2/17/2023 VU NGUYEN
Issued 11/15/2023 APPLICANT
CofO in Progress 7/14/2025 ROBERT DAVIS
Permit Finaled 8/5/2025 RICKEY JACKSON
CofO Issued 8/5/2025 RICKEY JACKSON
Permit Finaled 8/5/2025 RICKEY JACKSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/5/2021 ROBERT DUFF
Address approval Cleared 10/28/2021 DAGOVERTO GUERRERO
Highway dedication Cleared 2/11/2022 DAGOVERTO GUERRERO
Permit Cleared 2/11/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/26/2022 DAGOVERTO GUERRERO
Density Bonus 12.22.A.31 Cleared 4/27/2022 NICHOLAS KAWAZOE
Sewer availability Cleared 5/3/2022 DAGOVERTO GUERRERO
Trees in Parkway Cleared 5/4/2022 ADALBERTO VERA
Fire Marshal Fire Life Safety Cleared 5/20/2022 DOMINIQUE MEDINA
Low Impact Development Cleared 8/17/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 8/18/2022 DAGOVERTO GUERRERO
"Q" conditions Cleared 8/23/2022 SHASHA YU
CPC Cleared 8/23/2022 SHASHA YU
APC Cleared 8/24/2022 SHASHA YU
Frnt yard landscape/Water mgmt Cleared 8/24/2022 SHASHA YU
Miscellaneous Cleared 8/24/2022 SHASHA YU
Miscellaneous Cleared 8/24/2022 SHASHA YU
Opn space landscape/Water mgmt Cleared 8/24/2022 SHASHA YU
Building over 36-ft Cleared 9/7/2022 CALOSHA APPROVED
Green Code Cleared 9/7/2022 VU NGUYEN
DAS Clearance Cleared 9/13/2022 VU NGUYEN
Bicycle Parking Cleared 2/7/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Jb Home Builders Co; Lic. No.: 619281-B 6745 DARBY AVENUE      RESEDA, CA 91335
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/16/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 11/17/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 11/28/2023 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 11/28/2023 Partial Approval CAMERON CHABAN
Masonry Wall/Backfill 11/28/2023 Partial Approval CAMERON CHABAN
Masonry Wall/Backfill 12/1/2023 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 12/5/2023 Partial Approval CAMERON CHABAN
Masonry Wall/Backfill 12/13/2023 Not Ready for Inspection ANDREW DORSO
Reinforced Masonry Frame 12/13/2023 Not Ready for Inspection ANDREW DORSO
Reinforced Masonry Frame 12/14/2023 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 1/19/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 2/28/2024 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 3/18/2024 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 3/19/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 3/26/2024 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Corrections Issued ROBERT DAVIS
Deputy Wood Construction 4/12/2024 Approved ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Partial Approval ROBERT DAVIS
Deputy Wood Construction 4/18/2024 Conditional Approval ROBERT DAVIS
Deputy Wood Construction 4/23/2024 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/24/2024 Partial Approval ROBERT DAVIS
Deputy Wood Construction 5/6/2024 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Corrections Issued ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/8/2024 Partial Approval ROBERT DAVIS
Deputy Wood Construction 5/31/2024 Approved ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval ROBERT DAVIS
Deputy Wood Construction 6/10/2024 Conditional Approval JOHN KITCKO
Deputy Wood Construction 6/17/2024 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Partial Approval ROBERT DAVIS
Deputy Wood Construction 7/9/2024 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Approval ROBERT DAVIS
Green Building Rough 7/23/2024 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 7/23/2024 Not Ready for Inspection ROBERT DAVIS
Wood Frame 7/23/2024 No Access for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 7/25/2024 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 7/25/2024 Approved KENNETH ROBERTS
Verify Sprinkler Sign Off 7/25/2024 Not Ready for Inspection ROBERT DAVIS
Wood Frame 7/25/2024 Partial Approval ROBERT DAVIS
Green Building Rough 7/30/2024 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 7/30/2024 Not Ready for Inspection ROBERT DAVIS
Wood Frame 7/30/2024 Partial Approval ROBERT DAVIS
Deputy Wood Construction 8/6/2024 Conditional Approval ROBERT DAVIS
Deputy Wood Construction 8/7/2024 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Partial Approval ROBERT DAVIS
Green Building Rough 8/9/2024 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 8/9/2024 Approved ROBERT DAVIS
Wood Frame 8/9/2024 Partial Approval ROBERT DAVIS
Deputy Wood Construction 8/14/2024 Conditional Approval CAMERON CHABAN
Green Building Rough 9/3/2024 Approved ROBERT DAVIS
Wood Frame 9/3/2024 Corrections Issued ROBERT DAVIS
Drywall Nailing 9/9/2024 Partial Approval ROBERT DAVIS
Insulation 9/9/2024 Partial Approval ROBERT DAVIS
Wood Frame 9/9/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 9/20/2024 Not Ready for Inspection ROBERT DAVIS
Insulation 9/20/2024 Partial Approval ROBERT DAVIS
Wood Frame 9/20/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 9/27/2024 Partial Approval ROBERT DAVIS
Insulation 9/27/2024 Partial Approval ROBERT DAVIS
Wood Frame 9/27/2024 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 10/15/2024 Partial Approval ROBERT DAVIS
Special/Order Compliance 2/12/2025 Partial Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV Not Ready ROBERT DAVIS
Wood Frame 4/25/2025 Not Ready for Inspection ROBERT DAVIS
Final 6/18/2025 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 6/18/2025 Approved ROBERT DAVIS
Green Building Final 6/18/2025 Approved ROBERT DAVIS
Reinforced Concrete Frame 6/18/2025 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 6/18/2025 SGSOV Approved ROBERT DAVIS
Smoke Detectors 6/18/2025 Approved ROBERT DAVIS
Wood Frame 6/18/2025 Approved ROBERT DAVIS
Final 7/2/2025 OK to Issue CofO ROBERT DAVIS