14811 W ERWIN ST 1-33 91411
Certificate Information: 14811 W ERWIN ST 1-33 91411
- Application / Permit
- 21010-10000-01571
- Plan Check / Job No.
- B21LA06041
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 5 STORY 33 UNITS (4 EXTREMELY LOW INCOME UNITS) AFFORDABLE HOUSING APARTMENT TO INCLUDE 4 STORY TYPE VA APARTMENT OVER 1 STORY TYPE 1A PARKING GARAGE, TOC TIER 3 WITH ADDITIONAL INCENTIVES
- Permit Issued
- Issued on 11/15/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 2/17/2023 | VU NGUYEN |
| Issued | 11/15/2023 | APPLICANT |
| CofO in Progress | 7/14/2025 | ROBERT DAVIS |
| Permit Finaled | 8/5/2025 | RICKEY JACKSON |
| CofO Issued | 8/5/2025 | RICKEY JACKSON |
| Permit Finaled | 8/5/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/5/2021 | ROBERT DUFF |
| Address approval | Cleared | 10/28/2021 | DAGOVERTO GUERRERO |
| Highway dedication | Cleared | 2/11/2022 | DAGOVERTO GUERRERO |
| Permit | Cleared | 2/11/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2022 | DAGOVERTO GUERRERO |
| Density Bonus 12.22.A.31 | Cleared | 4/27/2022 | NICHOLAS KAWAZOE |
| Sewer availability | Cleared | 5/3/2022 | DAGOVERTO GUERRERO |
| Trees in Parkway | Cleared | 5/4/2022 | ADALBERTO VERA |
| Fire Marshal Fire Life Safety | Cleared | 5/20/2022 | DOMINIQUE MEDINA |
| Low Impact Development | Cleared | 8/17/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 8/18/2022 | DAGOVERTO GUERRERO |
| "Q" conditions | Cleared | 8/23/2022 | SHASHA YU |
| CPC | Cleared | 8/23/2022 | SHASHA YU |
| APC | Cleared | 8/24/2022 | SHASHA YU |
| Frnt yard landscape/Water mgmt | Cleared | 8/24/2022 | SHASHA YU |
| Miscellaneous | Cleared | 8/24/2022 | SHASHA YU |
| Miscellaneous | Cleared | 8/24/2022 | SHASHA YU |
| Opn space landscape/Water mgmt | Cleared | 8/24/2022 | SHASHA YU |
| Building over 36-ft | Cleared | 9/7/2022 | CALOSHA APPROVED |
| Green Code | Cleared | 9/7/2022 | VU NGUYEN |
| DAS Clearance | Cleared | 9/13/2022 | VU NGUYEN |
| Bicycle Parking | Cleared | 2/7/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Jb Home Builders Co; Lic. No.: 619281-B | 6745 DARBY AVENUE RESEDA, CA 91335 |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/16/2023 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 11/17/2023 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 11/28/2023 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 11/28/2023 | Partial Approval | CAMERON CHABAN |
| Masonry Wall/Backfill | 11/28/2023 | Partial Approval | CAMERON CHABAN |
| Masonry Wall/Backfill | 12/1/2023 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 12/5/2023 | Partial Approval | CAMERON CHABAN |
| Masonry Wall/Backfill | 12/13/2023 | Not Ready for Inspection | ANDREW DORSO |
| Reinforced Masonry Frame | 12/13/2023 | Not Ready for Inspection | ANDREW DORSO |
| Reinforced Masonry Frame | 12/14/2023 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 1/19/2024 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 2/28/2024 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 3/18/2024 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 3/19/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 3/26/2024 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Corrections Issued | ROBERT DAVIS |
| Deputy Wood Construction | 4/12/2024 | Approved | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 4/18/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Wood Construction | 4/23/2024 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 5/6/2024 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Corrections Issued | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 5/31/2024 | Approved | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 6/10/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Wood Construction | 6/17/2024 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 7/9/2024 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Partial Approval | ROBERT DAVIS |
| Green Building Rough | 7/23/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 7/23/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 7/23/2024 | No Access for Inspection | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Rough | 7/25/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Special/Order Compliance | 7/25/2024 | Approved | KENNETH ROBERTS |
| Verify Sprinkler Sign Off | 7/25/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 7/25/2024 | Partial Approval | ROBERT DAVIS |
| Green Building Rough | 7/30/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 7/30/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 7/30/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 8/6/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Wood Construction | 8/7/2024 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Partial Approval | ROBERT DAVIS |
| Green Building Rough | 8/9/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 8/9/2024 | Approved | ROBERT DAVIS |
| Wood Frame | 8/9/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 8/14/2024 | Conditional Approval | CAMERON CHABAN |
| Green Building Rough | 9/3/2024 | Approved | ROBERT DAVIS |
| Wood Frame | 9/3/2024 | Corrections Issued | ROBERT DAVIS |
| Drywall Nailing | 9/9/2024 | Partial Approval | ROBERT DAVIS |
| Insulation | 9/9/2024 | Partial Approval | ROBERT DAVIS |
| Wood Frame | 9/9/2024 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 9/20/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Insulation | 9/20/2024 | Partial Approval | ROBERT DAVIS |
| Wood Frame | 9/20/2024 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 9/27/2024 | Partial Approval | ROBERT DAVIS |
| Insulation | 9/27/2024 | Partial Approval | ROBERT DAVIS |
| Wood Frame | 9/27/2024 | Partial Approval | ROBERT DAVIS |
| Interior/Exterior Lathing | 10/15/2024 | Partial Approval | ROBERT DAVIS |
| Special/Order Compliance | 2/12/2025 | Partial Inspection | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/5/2025 | SGSOV Not Ready | ROBERT DAVIS |
| Wood Frame | 4/25/2025 | Not Ready for Inspection | ROBERT DAVIS |
| Final | 6/18/2025 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 6/18/2025 | Approved | ROBERT DAVIS |
| Green Building Final | 6/18/2025 | Approved | ROBERT DAVIS |
| Reinforced Concrete Frame | 6/18/2025 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 6/18/2025 | Approved | ROBERT DAVIS |
| Wood Frame | 6/18/2025 | Approved | ROBERT DAVIS |
| Final | 7/2/2025 | OK to Issue CofO | ROBERT DAVIS |