13246 N DE FOE AVE 91342
Certificate Information: 13246 N DE FOE AVE 91342
- Application / Permit
- 21010-10000-01568
- Plan Check / Job No.
- B21LA06038
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c)-(d)
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Current Status
- CofO Issued on 3/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | LAMAR DAVIS |
| Corrections Issued | 5/20/2021 | LAMAR DAVIS |
| Quality Review Completed | 5/26/2021 | HERNAN ARREOLA |
| Plan Check Approved | 8/10/2022 | LAMAR DAVIS |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 3/13/2024 | KEVIN BERBERYAN |
| Permit Finaled | 3/28/2024 | DANIEL ORRANTE |
| CofO Issued | 3/28/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/28/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2021 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 2/3/2022 | JOHN CONNEALLY |
| Sewer availability | Cleared | 5/31/2022 | JOSE DUARTE-DIAZ |
| Tract Map conditions | Cleared | 6/1/2022 | NELSON RODRIGUEZ |
| ZI | Cleared | 6/1/2022 | NELSON RODRIGUEZ |
| Low Impact Development | Cleared | 7/11/2022 | CHRIS VONG |
| Miscellaneous | Cleared | 7/27/2022 | LAMAR DAVIS |
| Roof/Waste drainage to street | Cleared | 8/2/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/17/2022 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/17/2022 | Corrections Issued | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 11/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 11/1/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 11/1/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 11/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 12/20/2022 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 12/20/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/8/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/8/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Gas Test | 2/8/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/8/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/8/2023 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/14/2023 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/14/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/1/2023 | Conditional Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/1/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 3/1/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 3/1/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 3/9/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 3/9/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/9/2023 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 3/9/2023 | Approved | ARAM AVEDISIAN |
| Sewer | 5/16/2023 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 5/16/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/24/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 1/24/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 1/24/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 1/24/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/24/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 1/24/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/22/2024 | Approved | ROBERT GOLD |
| Final | 2/22/2024 | Not Ready for Inspection | ROBERT GOLD |
| Service/Power Release | 2/22/2024 | Not Ready for Inspection | ROBERT GOLD |
| Smoke Detectors | 2/22/2024 | Not Ready for Inspection | ROBERT GOLD |
| Final | 3/12/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| Service/Power Release | 3/12/2024 | Not Required | KEVIN BERBERYAN |
| Smoke Detectors | 3/12/2024 | Approved | KEVIN BERBERYAN |