13246 N DE FOE AVE 91342

Certificate Information: 13246 N DE FOE AVE 91342

Application / Permit
21010-10000-01568
Plan Check / Job No.
B21LA06038
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c)-(d)
Permit Issued
Issued on 8/25/2022
Issuing Office
Current Status
CofO Issued on 3/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 LAMAR DAVIS
Corrections Issued 5/20/2021 LAMAR DAVIS
Quality Review Completed 5/26/2021 HERNAN ARREOLA
Plan Check Approved 8/10/2022 LAMAR DAVIS
Issued 8/25/2022 APPLICANT
CofO in Progress 3/13/2024 KEVIN BERBERYAN
Permit Finaled 3/28/2024 DANIEL ORRANTE
CofO Issued 3/28/2024 DANIEL ORRANTE
Permit Finaled 3/28/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/17/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 11/22/2021 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 2/3/2022 JOHN CONNEALLY
Sewer availability Cleared 5/31/2022 JOSE DUARTE-DIAZ
Tract Map conditions Cleared 6/1/2022 NELSON RODRIGUEZ
ZI Cleared 6/1/2022 NELSON RODRIGUEZ
Low Impact Development Cleared 7/11/2022 CHRIS VONG
Miscellaneous Cleared 7/27/2022 LAMAR DAVIS
Roof/Waste drainage to street Cleared 8/2/2022 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 10/17/2022 Corrections Issued ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 11/1/2022 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 11/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 11/1/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 11/4/2022 Approved CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 12/20/2022 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 12/20/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Conditional Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 2/8/2023 Conditional Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 2/8/2023 Conditional Approval CHRISTOPHER DELLEFIELD
Gas Test 2/8/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 2/8/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 2/8/2023 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Not Ready CHRISTOPHER DELLEFIELD
HVAC-Rough 2/14/2023 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 2/14/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/1/2023 Conditional Approval ARAM AVEDISIAN
ELECTRICAL-Rough 3/1/2023 Approved ARAM AVEDISIAN
HVAC-Rough 3/1/2023 Approved ARAM AVEDISIAN
Insulation 3/1/2023 Approved ARAM AVEDISIAN
Drywall Nailing 3/9/2023 Approved ARAM AVEDISIAN
Green Building Rough 3/9/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 3/9/2023 Partial Approval ARAM AVEDISIAN
Shower Pan 3/9/2023 Approved ARAM AVEDISIAN
Sewer 5/16/2023 Approved ARAM AVEDISIAN
Underground Mechanical 5/16/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 1/24/2024 Corrections Issued CHRISTOPHER ROJAS
Final 1/24/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 1/24/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/24/2024 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 1/24/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 1/24/2024 Corrections Issued CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 1/24/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/22/2024 Approved ROBERT GOLD
Final 2/22/2024 Not Ready for Inspection ROBERT GOLD
Service/Power Release 2/22/2024 Not Ready for Inspection ROBERT GOLD
Smoke Detectors 2/22/2024 Not Ready for Inspection ROBERT GOLD
Final 3/12/2024 OK to Issue CofO KEVIN BERBERYAN
Service/Power Release 3/12/2024 Not Required KEVIN BERBERYAN
Smoke Detectors 3/12/2024 Approved KEVIN BERBERYAN