7333 N LEMONA AVE 91405
Certificate Information: 7333 N LEMONA AVE 91405
- Application / Permit
- 21010-10000-01524
- Plan Check / Job No.
- B21LA05932
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ACCESSORY DWELLING UNIT (2-STORY) PER ORDINANCE
- Permit Issued
- Issued on 2/28/2022
- Issuing Office
- Current Status
- CofO Issued on 5/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | CARLOS MONTES |
| Corrections Issued | 5/12/2021 | CARLOS MONTES |
| Quality Review Completed | 5/20/2021 | WING SUEN |
| Applicant returned to address corrections | 2/16/2022 | CARLOS MONTES |
| Plan Check Approved | 2/18/2022 | CARLOS MONTES |
| Issued | 2/28/2022 | APPLICANT |
| CofO in Progress | 5/8/2024 | KIRK SANDERS |
| Permit Finaled | 5/18/2024 | RUBEN SALAS |
| CofO Issued | 5/18/2024 | RUBEN SALAS |
| Permit Finaled | 5/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/28/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 9/7/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/19/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 1/31/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 2/1/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/1/2022 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 6/15/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/8/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/8/2022 | Approved | GREGG CUMMINGS |
| Special/Order Compliance | 7/8/2022 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Partial Approval | GREGG CUMMINGS |
| Deputy Wood Construction | 10/19/2022 | Conditional Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/11/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 1/11/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 1/11/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 1/11/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 1/25/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/25/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/9/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 2/9/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/9/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 2/9/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/11/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/11/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/11/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/11/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/11/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/28/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/28/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 5/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 5/15/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 10/3/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 10/3/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/3/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 10/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 10/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 2/15/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 2/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 2/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 3/20/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/20/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 3/20/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/20/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 4/17/2024 | Corrections Issued | GREGG CUMMINGS |
| Service/Power Release | 4/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 5/7/2024 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 5/7/2024 | Approved | KIRK SANDERS |