1439-1441 W 37TH DR 90018

Certificate Information: 1439-1441 W 37TH DR 90018

Application / Permit
21010-10000-01517
Plan Check / Job No.
B21LA05910
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH ATTACHED 4 CAR GARAGE.
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
CofO Issued on 5/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 ZAW HAN
Corrections Issued 5/5/2021 ZAW HAN
Quality Review Completed 5/12/2021 WING SUEN
Applicant returned to address corrections 12/15/2021 ZAW HAN
Plan Check Approved 3/1/2022 ZAW HAN
Issued 3/10/2022 APPLICANT
Building Plans Picked Up 4/14/2022 APPLICANT
CofO in Progress 5/19/2023 SABAS ALONSO
Permit Finaled 5/21/2023 DEROLD HAUFF
CofO Issued 5/21/2023 DEROLD HAUFF
Permit Finaled 5/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/20/2021 WALLIE JONG
Address approval Cleared 7/20/2021 WALLIE JONG
Highway dedication Cleared 7/20/2021 WALLIE JONG
Permit Cleared 7/20/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/21/2021 WALLIE JONG
Hydrant and Access approval Cleared 9/20/2021 MATTHEW CRAIG
Low Impact Development Cleared 10/19/2021 ANDRES COVARRUBIAS
Sewer availability Cleared 12/1/2021 WALLIE JONG
Abandoned oil well Cleared 1/4/2022 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 2/2/2022 WALLIE JONG
Trees in Parkway Cleared 2/2/2022 ADALBERTO VERA

Contact Information

Contractor Tre Development Llc; Lic. No.: 1075573-B 2905 S VERMONT AVE #204      LOS ANGELES, CA 90007
Engineer Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 PO BOX 5044      PASADENA, CA 91117

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/20/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 4/28/2022 Partial Approval SABAS ALONSO
Deputy Reinf. Concrete 5/5/2022 Conditional Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 5/6/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 5/6/2022 Approved SABAS ALONSO
Deputy Steel/Welding 5/24/2022 Conditional Approval SABAS ALONSO
Deputy Wood Construction 6/3/2022 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Partial Approval HORACE FULTZ
Deputy Wood Construction 6/15/2022 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Partial Approval SABAS ALONSO
Deputy Wood Construction 6/28/2022 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Not Ready for Inspection SABAS ALONSO
Deputy Wood Construction 7/18/2022 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/22/2022 Approved SABAS ALONSO
PLUMBING-Rough 8/24/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 8/26/2022 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 8/26/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/30/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 9/1/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 9/1/2022 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 9/6/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/6/2022 Approved RYAN SALAZAR
Deputy Other (see comments) 9/9/2022 Conditional Approval SABAS ALONSO
Green Building Rough 9/9/2022 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 9/21/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 9/28/2022 Corrections Issued HORACE FULTZ
Interior/Exterior Lathing 10/18/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/24/2022 Not Ready for Inspection SABAS ALONSO
Green Building Rough 10/24/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 10/24/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/1/2022 Approved SABAS ALONSO
Insulation 11/1/2022 Not Ready for Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 11/2/2022 Off-Hour Fees Due
Insulation 11/2/2022 Approved SABAS ALONSO
Piling/Pier/Caisson 11/2/2022 Off-Hour Fees Due
Drywall Nailing 11/14/2022 Approved SABAS ALONSO
Service/Power Release 1/20/2023 Not Ready for Inspection SABAS ALONSO
Sewer 1/20/2023 Approved SABAS ALONSO
Gas Test 3/1/2023 Approved SABAS ALONSO
Service/Power Release 3/1/2023 Corrections Issued SABAS ALONSO
Service/Power Release 3/7/2023 Corrections Issued STUART CHAPMAN
Final 3/14/2023 Corrections Issued SABAS ALONSO
Green Building Final 3/14/2023 Corrections Issued SABAS ALONSO
HVAC-Final 3/14/2023 Approved SABAS ALONSO
PLUMBING-Final 3/14/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 3/14/2023 Approved SABAS ALONSO
Final 3/21/2023 Corrections Issued STUART CHAPMAN
Service/Power Release 3/21/2023 Not Ready for Inspection STUART CHAPMAN
Final 4/18/2023 Conditional Approval SABAS ALONSO
Green Building Final 4/18/2023 Approved SABAS ALONSO
Service/Power Release 4/18/2023 Approved SABAS ALONSO
Final 4/20/2023 Corrections Issued SABAS ALONSO
Final 5/18/2023 OK to Issue CofO SABAS ALONSO