4829 S 7TH AVE 90043
Certificate Information: 4829 S 7TH AVE 90043
- Application / Permit
- 21010-10000-01501
- Plan Check / Job No.
- B21LA05850
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY A.D.U. AT REAR OF LOT PER ORDINANCE.
- Permit Issued
- Issued on 10/1/2021
- Issuing Office
- Current Status
- CofO Issued on 3/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 4/8/2021 | LAWRENCE QUIRANTE |
| Plan Check Approved | 9/24/2021 | FERNANDO FLORES |
| Issued | 10/1/2021 | APPLICANT |
| Building Plans Picked Up | 10/5/2021 | APPLICANT |
| CofO in Progress | 3/7/2023 | ANTHONY EGSON |
| Permit Finaled | 3/16/2023 | DEROLD HAUFF |
| CofO Issued | 3/16/2023 | DEROLD HAUFF |
| Permit Finaled | 3/16/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2021 | JEANIE LAM |
| Sewer availability | Cleared | 5/5/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 9/17/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/20/2021 | JEANIE LAM |
Contact Information
| Contractor | C G S Home Improvement Inc; Lic. No.: 1037939-B | 7189 N FIGUEROA ST LOS ANGELES, CA 90042 |
| Engineer | Velasco,, Jose Luis; Lic. No.: C76091 | 100 SE 2ND STREET SUITE 2000 MIAMI, FL 33131 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/4/2021 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/4/2021 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 11/12/2021 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/12/2021 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/18/2021 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 12/1/2021 | Approved | ANTHONY EGSON |
| Insulation | 12/6/2021 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2021 | Partial Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/7/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 2/7/2022 | Approved | HORACE FULTZ |
| Green Building Rough | 2/7/2022 | Approved | HORACE FULTZ |
| HVAC-Rough | 2/7/2022 | Conditional Approval | HORACE FULTZ |
| PLUMBING-Rough | 2/7/2022 | Approved | HORACE FULTZ |
| Sewer | 2/7/2022 | Approved | HORACE FULTZ |
| Verify Sprinkler Sign Off | 2/7/2022 | Approved | HORACE FULTZ |
| Insulation | 2/15/2022 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 2/22/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 2/22/2022 | Partial Approval | HORACE FULTZ |
| Drywall Nailing | 3/3/2022 | Approved | HORACE FULTZ |
| Shower Pan | 3/18/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/4/2022 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/15/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/28/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 6/28/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 6/28/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 6/28/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 6/28/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/28/2022 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 6/28/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 6/28/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 7/14/2022 | Approved | ANTHONY EGSON |
| Final | 7/14/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 7/14/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 7/14/2022 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 7/14/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 7/20/2022 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 7/20/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 3/7/2023 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 3/7/2023 | Approved | ANTHONY EGSON |