618 W 77TH ST 90044
Certificate Information: 618 W 77TH ST 90044
- Application / Permit
- 21010-10000-01487
- Plan Check / Job No.
- B21LA05802
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD 3 OF 3
- Permit Issued
- Issued on 3/1/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 5/10/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 5/13/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 7/13/2021 | APPLICANT |
| Plan Check Approved | 2/3/2022 | ARSALAN SHABESTARI |
| Issued | 3/1/2022 | APPLICANT |
| CofO in Progress | 12/17/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 12/17/2022 | DEROLD HAUFF |
| CofO Issued | 12/17/2022 | DEROLD HAUFF |
| Permit Finaled | 12/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 10/9/2021 | ROBERT DUFF |
| Sewer availability | Cleared | 10/28/2021 | JEANETTE VONG |
| Low Impact Development | Cleared | 12/2/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/7/2021 | JEANETTE VONG |
| Frnt yard landscape/Water mgmt | Cleared | 1/10/2022 | RUBEN VASQUEZ |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/10/2022 | Corrections Issued | RUBEN SALAS |
| Underground Mechanical | 3/10/2022 | Partial Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 3/17/2022 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/17/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/25/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/25/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 5/25/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 5/25/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 5/25/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 5/25/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 5/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/31/2022 | Approved | LILIANA PORTILLO |
| Insulation | 5/31/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 6/7/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/7/2022 | Approved | LILIANA PORTILLO |
| Gas Test | 7/27/2022 | Approved | LILIANA PORTILLO |
| Sewer | 7/27/2022 | Approved | LILIANA PORTILLO |
| Verify Rec and Parks Fee Memo | 7/27/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/2/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/2/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/2/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/14/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/14/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/16/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |