1301 N TULAROSA DR 90026
Certificate Information: 1301 N TULAROSA DR 90026
- Application / Permit
- 21010-10000-01481
- Plan Check / Job No.
- B21LA05791
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPSOED 3-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 2-CAR GARAGE AND A ROOF TOP DECK. 1 OF 3
- Permit Issued
- Issued on 8/24/2023
- Issuing Office
- Metro
- Current Status
- Issued on 8/24/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | MICHAEL LOPEZ |
| Corrections Issued | 4/22/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 4/29/2021 | KEN GILL |
| Building Plans Picked Up | 5/4/2021 | APPLICANT |
| Applicant returned to address corrections | 11/15/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/16/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/3/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 8/11/2023 | MICHAEL LOPEZ |
| Issued | 8/24/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/9/2021 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 6/9/2021 | STEVE MELGAR |
| Highway dedication | Cleared | 6/9/2021 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 9/2/2021 | VASIL MIHALEV |
| Address approval | Cleared | 10/4/2021 | STEVE MELGAR |
| Encroachment in public way | Cleared | 11/9/2021 | JEREMY CHOK |
| Trees in Parkway | Cleared | 12/17/2021 | ADALBERTO VERA |
| Frnt yard landscape/Water mgmt | Cleared | 1/14/2022 | MAYELA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 1/18/2022 | STEVE MELGAR |
| Work Adjacent to Public Way | Cleared | 1/20/2022 | ARMEN SARKISIAN |
| BHO/Hillside ordinance | Cleared | 3/4/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 3/5/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 4/19/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 4/20/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 3/7/2023 | MATIAS FARFAN |
| Permit | Cleared | 3/7/2023 | MATIAS FARFAN |
| BHO/Hillside ordinance | Cleared | 3/22/2023 | MATIAS FARFAN |
| GPI Written Notices | Cleared | 8/3/2023 | ROBERT HUGHES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/19/2025 | Approved | FREDDIE RIVERA |
| Piling/Pier/Caisson | 11/5/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| Piling/Pier/Caisson | 1/16/2026 | Partial Approval | FREDDIE RIVERA |
| Deputy Reinf. Concrete | 1/26/2026 | Conditional Approval | FREDDIE RIVERA |
| Deputy Other (see comments) | 1/30/2026 | Conditional Approval | OSVALDO PARAMO |
| Special/Order Compliance | 5/15/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 5/15/2026 | Partial Inspection | FREDDIE RIVERA |