927 S KENISTON AVE 90019

Certificate Information: 927 S KENISTON AVE 90019

Application / Permit
21010-10000-01479
Plan Check / Job No.
B21LA05784
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADU PER GCS 65852.2 (e)(1)(B) AND LAMC 12.22 A.33 (c) , (d) &(g) WITH ATTACHED GARAGE
Permit Issued
Issued on 5/16/2022
Issuing Office
Current Status
CofO Issued on 8/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 MAHNAZ NOURHASHEMI
Corrections Issued 6/29/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 7/8/2021 JASON HEALEY
Building Plans Picked Up 7/28/2021 APPLICANT
Applicant returned to address corrections 11/5/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 5/4/2022 MAHNAZ NOURHASHEMI
Issued 5/16/2022 APPLICANT
CofO in Progress 8/3/2023 LILIANA PORTILLO
Permit Finaled 8/6/2023 DEROLD HAUFF
CofO Issued 8/6/2023 DEROLD HAUFF
Permit Finaled 8/6/2023 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 11/3/2021 ANACANY HURTADO
Address approval Cleared 11/18/2021 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 12/15/2021 KHOUNG LE
Sewer availability Cleared 12/15/2021 KHOUNG LE
Hydrant and Access approval Cleared 1/13/2022 MATTHEW CRAIG
Low Impact Development Cleared 3/4/2022 ANTHONY VARGAS
Permit Cleared 3/9/2022 KHOUNG LE
Roof/Waste drainage to street Cleared 3/9/2022 KHOUNG LE

Contact Information

Contractor Kreative Design Construction; Lic. No.: 904727-B 13419 GARDENIA AVE      GARDEN GROVE, CA 92840
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/9/2022 Partial Inspection ADAM ESCOTO
Footing/Foundation/Slab 6/23/2022 Not Ready for Inspection JOSEPH MCGARRY
METHANE-Barrier 6/23/2022 Approved JOSEPH MCGARRY
METHANE-Subgrade 6/23/2022 Approved JOSEPH MCGARRY
PLUMBING-Rough 6/23/2022 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 6/27/2022 Corrections Issued ADAM ESCOTO
Footing/Foundation/Slab 6/27/2022 Not Ready for Inspection ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 6/28/2022 Approved ADAM ESCOTO
Footing/Foundation/Slab 6/28/2022 Approved ADAM ESCOTO
BUILDING-Rough-Frame 7/13/2022 Partial Approval ADAM ESCOTO
Green Building Rough 7/13/2022 Not Ready for Inspection ADAM ESCOTO
METHANE-Rough 7/13/2022 Not Ready for Inspection ADAM ESCOTO
Verify Sprinkler Sign Off 7/13/2022 Not Ready for Inspection ADAM ESCOTO
Wood Frame 7/26/2022 Corrections Issued STUART CHAPMAN
Deputy Wood Construction 7/28/2022 Approved ADAM ESCOTO
ELECTRICAL-Rough 8/16/2022 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Rough 8/16/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 8/16/2022 Corrections Issued ALIZAH MAYAGOITIA
Sewer 8/16/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/7/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 9/7/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/12/2022 Corrections Issued JOSEPH MCGARRY
Green Building Rough 9/12/2022 Approved JOSEPH MCGARRY
METHANE-Rough 9/12/2022 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 9/12/2022 Not Ready for Inspection JOSEPH MCGARRY
Gas Test 9/22/2022 Approved MICHAEL LEWIS
Underground Mechanical 9/22/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/19/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 10/19/2022 Approved MICHAEL LEWIS
Insulation 11/17/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 11/17/2022 Approved MICHAEL LEWIS
Drywall Nailing 12/1/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 12/21/2022 Partial Inspection RICHARD DOCKUS
Gas Test 12/21/2022 Approved RICHARD DOCKUS
Final 5/1/2023 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 5/1/2023 Not Ready for Inspection RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 5/1/2023 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 5/1/2023 Approved RICHARD DOCKUS
Final 6/28/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/28/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 6/28/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 7/13/2023 Approved LILIANA PORTILLO
Final 7/13/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 7/13/2023 Approved LILIANA PORTILLO
HVAC-Final 7/13/2023 Approved LILIANA PORTILLO
PLUMBING-Final 7/13/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 7/13/2023 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 7/13/2023 Approved LILIANA PORTILLO
Final 8/2/2023 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 8/2/2023 Approved LILIANA PORTILLO