927 S KENISTON AVE 90019
Certificate Information: 927 S KENISTON AVE 90019
- Application / Permit
- 21010-10000-01479
- Plan Check / Job No.
- B21LA05784
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU PER GCS 65852.2 (e)(1)(B) AND LAMC 12.22 A.33 (c) , (d) &(g) WITH ATTACHED GARAGE
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Current Status
- CofO Issued on 8/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/29/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/8/2021 | JASON HEALEY |
| Building Plans Picked Up | 7/28/2021 | APPLICANT |
| Applicant returned to address corrections | 11/5/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 5/4/2022 | MAHNAZ NOURHASHEMI |
| Issued | 5/16/2022 | APPLICANT |
| CofO in Progress | 8/3/2023 | LILIANA PORTILLO |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
| CofO Issued | 8/6/2023 | DEROLD HAUFF |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 11/3/2021 | ANACANY HURTADO |
| Address approval | Cleared | 11/18/2021 | KHOUNG LE |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2021 | KHOUNG LE |
| Sewer availability | Cleared | 12/15/2021 | KHOUNG LE |
| Hydrant and Access approval | Cleared | 1/13/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 3/4/2022 | ANTHONY VARGAS |
| Permit | Cleared | 3/9/2022 | KHOUNG LE |
| Roof/Waste drainage to street | Cleared | 3/9/2022 | KHOUNG LE |
Contact Information
| Contractor | Kreative Design Construction; Lic. No.: 904727-B | 13419 GARDENIA AVE GARDEN GROVE, CA 92840 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/9/2022 | Partial Inspection | ADAM ESCOTO |
| Footing/Foundation/Slab | 6/23/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Barrier | 6/23/2022 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 6/23/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/23/2022 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Corrections Issued | ADAM ESCOTO |
| Footing/Foundation/Slab | 6/27/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 6/28/2022 | Approved | ADAM ESCOTO |
| Footing/Foundation/Slab | 6/28/2022 | Approved | ADAM ESCOTO |
| BUILDING-Rough-Frame | 7/13/2022 | Partial Approval | ADAM ESCOTO |
| Green Building Rough | 7/13/2022 | Not Ready for Inspection | ADAM ESCOTO |
| METHANE-Rough | 7/13/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Verify Sprinkler Sign Off | 7/13/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Wood Frame | 7/26/2022 | Corrections Issued | STUART CHAPMAN |
| Deputy Wood Construction | 7/28/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Rough | 8/16/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/16/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/16/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Sewer | 8/16/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 9/7/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 9/7/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/12/2022 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Rough | 9/12/2022 | Approved | JOSEPH MCGARRY |
| METHANE-Rough | 9/12/2022 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 9/12/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Gas Test | 9/22/2022 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 9/22/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/19/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 10/19/2022 | Approved | MICHAEL LEWIS |
| Insulation | 11/17/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 11/17/2022 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 12/1/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 12/21/2022 | Partial Inspection | RICHARD DOCKUS |
| Gas Test | 12/21/2022 | Approved | RICHARD DOCKUS |
| Final | 5/1/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 5/1/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/1/2023 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 5/1/2023 | Approved | RICHARD DOCKUS |
| Final | 6/28/2023 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/28/2023 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 6/28/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 7/13/2023 | Approved | LILIANA PORTILLO |
| Final | 7/13/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 7/13/2023 | Approved | LILIANA PORTILLO |
| HVAC-Final | 7/13/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 7/13/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 7/13/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 7/13/2023 | Approved | LILIANA PORTILLO |
| Final | 8/2/2023 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 8/2/2023 | Approved | LILIANA PORTILLO |