13441 W VANOWEN ST 1-2 91405

Certificate Information: 13441 W VANOWEN ST 1-2 91405

Application / Permit
21010-10000-01476
Plan Check / Job No.
B21LA05768
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1- STORY ADU DUPLEX AT REAR OF LOT.
Permit Issued
Issued on 10/6/2022
Issuing Office
Current Status
CofO in Progress on 5/21/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 JOE VO
Corrections Issued 4/18/2021 JOE VO
Quality Review Completed 4/23/2021 MICHAEL PEREZ
Applicant returned to address corrections 9/10/2021 JOE VO
Plan Check Approved 8/10/2022 JOE VO
Issued 10/6/2022 APPLICANT
CofO in Progress 5/21/2026 WAYNE REGESTER

Permit Application Clearance Information

Construction near power lines Cleared 6/29/2021 RIDWAN HARDY
Address approval Cleared 9/13/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 11/29/2021 MATTHEW CRAIG
Low Impact Development Cleared 5/16/2022 TA ANH
Roof/Waste drainage to street Cleared 5/27/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/2/2022 CARLOS AGUILERA
Sewer availability Cleared 6/2/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/28/2023 Corrections Issued MATTHEW NELSON
Underground Mechanical 3/6/2023 Approved KIRK SANDERS
Excavation/Setback/Form/Re-Bar 3/31/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 4/11/2023 Corrections Issued JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/13/2023 Approved KIRK SANDERS
PLUMBING-Rough 7/21/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/3/2023 Corrections Issued KIRK SANDERS
Sewer 8/3/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 8/11/2023 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 8/11/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 8/21/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 8/21/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/21/2023 Approved KIRK SANDERS
Green Building Rough 8/21/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 8/21/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 8/21/2023 Partial Approval KIRK SANDERS
PLUMBING-Rough 8/21/2023 Corrections Issued KIRK SANDERS
Verify Sprinkler Sign Off 8/21/2023 Conditional Approval KIRK SANDERS
ELECTRICAL-Rough 8/29/2023 Partial Approval KIRK SANDERS
HVAC-Rough 8/29/2023 Conditional Approval KIRK SANDERS
PLUMBING-Rough 8/29/2023 Conditional Approval KIRK SANDERS
BUILDING-Rough-Frame 9/1/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 9/1/2023 Conditional Approval KIRK SANDERS
Green Building Rough 9/1/2023 Approved KIRK SANDERS
Verify Sprinkler Sign Off 9/1/2023 Approved KIRK SANDERS
Insulation 9/19/2023 Approved JUAN VALENZUELA
Drywall Nailing 9/28/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 10/4/2023 Partial Approval CHRISTOPHER ROJAS
Final 4/30/2024 Corrections Issued JOSE AVILA
Underground Mechanical 4/30/2024 Corrections Issued JOSE AVILA
Final 7/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 7/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 7/5/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 7/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 7/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/9/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Final 8/22/2024 Not Ready for Inspection SALVADOR MARTINEZ
Footing/Foundation/Slab 8/22/2024 Not Ready for Inspection SALVADOR MARTINEZ
Green Building Final 8/22/2024 Not Ready for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 8/22/2024 SGSOV Not Ready SALVADOR MARTINEZ
Service/Power Release 8/22/2024 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 8/22/2024 Not Ready for Inspection SALVADOR MARTINEZ
Final 9/27/2024 No Access for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/27/2024 No Access for Inspection OGANES TARAKHCHYAN
Green Building Final 9/27/2024 No Access for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Service/Power Release 9/27/2024 No Access for Inspection OGANES TARAKHCHYAN
Smoke Detectors 9/27/2024 No Access for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV Not Ready WAYNE REGESTER
Final 5/13/2026 Not Ready for Inspection WAYNE REGESTER
Footing/Foundation/Slab 5/13/2026 Approved WAYNE REGESTER
Green Building Final 5/13/2026 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 5/13/2026 SGSOV Not Required WAYNE REGESTER
Service/Power Release 5/13/2026 Approved WAYNE REGESTER
Smoke Detectors 5/13/2026 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Final 5/15/2026 Approved WAYNE REGESTER
HVAC-Final 5/15/2026 Approved WAYNE REGESTER
PLUMBING-Final 5/15/2026 Approved WAYNE REGESTER
Service/Power Release 5/15/2026 Approved WAYNE REGESTER
Final 5/20/2026 OK to Issue CofO WAYNE REGESTER
Smoke Detectors 5/20/2026 Approved WAYNE REGESTER