8408 S MCCONNELL AVE 90045
Certificate Information: 8408 S MCCONNELL AVE 90045
- Application / Permit
- 21010-10000-01474
- Plan Check / Job No.
- B21LA05741
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO DETACHED ADU PER STATE LAW
- Permit Issued
- Issued on 8/23/2021
- Issuing Office
- Current Status
- CofO Issued on 5/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2021 | CARLOS MONTES |
| Corrections Issued | 4/9/2021 | CARLOS MONTES |
| Plan Check Approved | 8/13/2021 | PRANITA SHAH |
| Issued | 8/23/2021 | APPLICANT |
| CofO in Progress | 5/19/2022 | BOBBY KEY |
| Permit Finaled | 5/27/2022 | DANIEL ORRANTE |
| CofO Issued | 5/27/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/27/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 5/3/2021 | HISASHI KOBAYAKAWA |
| Construction near power lines | Cleared | 7/19/2021 | RIDWAN HARDY |
| Specific Plan | Cleared | 8/5/2021 | PEDRO AYALA |
Contact Information
| Contractor | Jno Construction And Design Inc; Lic. No.: 1051923-B | 750 N SAN VICENTE STE 800 WEST RED WEST HOLLYWOOD, CA 90069 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/15/2021 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 11/22/2021 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 11/22/2021 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 12/17/2021 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 12/17/2021 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 12/21/2021 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/21/2021 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 1/20/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/31/2022 | Approved | BOBBY KEY |
| Green Building Rough | 1/31/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/31/2022 | Partial Approval | BOBBY KEY |
| Shower Pan | 1/31/2022 | Approved | BOBBY KEY |
| Insulation | 2/2/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 2/7/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 2/7/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/5/2022 | Corrections Issued | BOBBY KEY |
| Final | 5/5/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 5/5/2022 | Approved | BOBBY KEY |
| HVAC-Final | 5/5/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 5/5/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/5/2022 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 5/5/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/19/2022 | Approved | BOBBY KEY |
| Final | 5/19/2022 | OK to Issue CofO | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 5/19/2022 | Approved | BOBBY KEY |