2106 E 105TH ST 90002
Certificate Information: 2106 E 105TH ST 90002
- Application / Permit
- 21010-10000-01472
- Plan Check / Job No.
- B21LA05736
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-PLAN: Proposed detached 15x30 ADU per ordinance.
- Permit Issued
- Issued on 8/5/2021
- Issuing Office
- Current Status
- CofO Issued on 5/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2021 | APPLICANT |
| Corrections Issued | 4/3/2021 | MICHAEL LOPEZ |
| Assigned to Plan Check Engineer | 4/4/2021 | MICHAEL LOPEZ |
| Corrections Issued | 5/19/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/4/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/10/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/23/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/14/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 8/4/2021 | HERNAN ARREOLA |
| Issued | 8/5/2021 | APPLICANT |
| CofO in Progress | 7/27/2022 | JOHN KLARIN |
| Permit Finaled | 5/11/2023 | DANIEL ORRANTE |
| CofO Issued | 5/11/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/11/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2021 | WALLIE JONG |
| Tract Map conditions | Cleared | 4/29/2021 | STEVEN WECHSLER |
| ZA Case | Cleared | 4/29/2021 | STEVEN WECHSLER |
| ZA Case | Cleared | 4/29/2021 | STEVEN WECHSLER |
| ZA Case | Cleared | 4/29/2021 | STEVEN WECHSLER |
| Hydrant and Access approval | Cleared | 5/21/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/27/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/1/2021 | WALLIE JONG |
| Sewer availability | Cleared | 7/22/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/5/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/28/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 11/30/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 12/17/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 1/11/2022 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2022 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/22/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 3/22/2022 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 3/22/2022 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 4/14/2022 | Approved | JOHN KLARIN |
| Insulation | 4/19/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 5/2/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 6/9/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 6/23/2022 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 6/23/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/5/2022 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 7/5/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/5/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 7/5/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 7/5/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 7/5/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/5/2022 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 7/5/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/8/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 7/8/2022 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | Approved | JOHN KLARIN |
| Service/Power Release | 7/8/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 7/26/2022 | Approved | JOHN KLARIN |
| Final | 7/26/2022 | OK to Issue CofO | JOHN KLARIN |
| Green Building Final | 7/26/2022 | Approved | JOHN KLARIN |
| HVAC-Final | 7/26/2022 | Approved | JOHN KLARIN |
| PLUMBING-Final | 7/26/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 7/26/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 8/25/2022 | Approved | JOHN KLARIN |