1039 E 21ST ST 90011

Certificate Information: 1039 E 21ST ST 90011

Application / Permit
21010-10000-01469
Plan Check / Job No.
B21LA05727
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-PLAN:New DETACHED ADU
Permit Issued
Issued on 1/5/2022
Issuing Office
Current Status
CofO Issued on 8/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 ARSALAN SHABESTARI
Corrections Issued 5/15/2021 ARSALAN SHABESTARI
Quality Review Completed 5/19/2021 MICHAEL PEREZ
Applicant returned to address corrections 9/8/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 12/2/2021 ARSALAN SHABESTARI
Plan Check Approved 12/17/2021 ARSALAN SHABESTARI
Issued 1/5/2022 APPLICANT
CofO in Progress 8/1/2023 ALEJANDRO DE ARTOLA
Permit Finaled 8/6/2023 DEROLD HAUFF
Permit Finaled 8/6/2023 DEROLD HAUFF
CofO Issued 8/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/26/2021 JEANIE LAM
Sewer availability Cleared 7/26/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/9/2021 JEANIE LAM
Hydrant and Access approval Cleared 10/2/2021 GILBERT URREA
Low Impact Development Cleared 11/15/2021 TA ANH
Roof/Waste drainage to street Cleared 11/22/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/12/2022 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 6/2/2022 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 6/2/2022 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/13/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/20/2022 Approved SHAVONNE ESPINOZA
BUILDING-Rough-Frame 9/6/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Green Building Rough 9/6/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Verify Sprinkler Sign Off 9/6/2022 Approved SHAVONNE ESPINOZA
Underground Mechanical 9/12/2022 Partial Approval SHAVONNE ESPINOZA
Underground Mechanical 9/14/2022 Approved SHAVONNE ESPINOZA
Sewer 9/21/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 9/26/2022 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/26/2022 Partial Approval RYAN SALAZAR
PLUMBING-Rough 9/26/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/20/2022 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 10/31/2022 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 11/2/2022 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 11/7/2022 Approved ALEJANDRO DE ARTOLA
Green Building Rough 11/7/2022 Approved ALEJANDRO DE ARTOLA
Insulation 11/29/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 12/8/2022 Corrections Issued JULIAN AMAYA
Drywall Nailing 12/14/2022 Conditional Approval BRENDAN MORELLI
HVAC-Rough 12/19/2022 Conditional Approval BRENDAN MORELLI
Interior/Exterior Lathing 12/19/2022 Approved BRENDAN MORELLI
ELECTRICAL-Final 2/16/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 2/16/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 4/13/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 4/13/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 5/4/2023 Approved BRENDAN MORELLI
HVAC-Final 5/4/2023 Approved BRENDAN MORELLI
Final 7/31/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 7/31/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/31/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 7/31/2023 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 7/31/2023 Approved ALEJANDRO DE ARTOLA