5107 S 5TH AVE 90043

Certificate Information: 5107 S 5TH AVE 90043

Application / Permit
21010-10000-01463
Plan Check / Job No.
B21LA05705
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
. ePlan NEW ADU.
Permit Issued
Issued on 8/24/2022
Issuing Office
Current Status
CofO Issued on 6/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 ARSALAN SHABESTARI
Corrections Issued 5/18/2021 ARSALAN SHABESTARI
Quality Review Completed 5/21/2021 MICHAEL PEREZ
Applicant returned to address corrections 11/13/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 6/3/2022 ARSALAN SHABESTARI
Plan Check Approved 6/28/2022 ARSALAN SHABESTARI
Issued 8/24/2022 APPLICANT
Refund in Progress 10/28/2022 TERENCE SHIA
Refund Closed 10/28/2022 TERENCE SHIA
Issued 10/28/2022 TERENCE SHIA
CofO in Progress 6/3/2024 ANTHONY EGSON
Permit Finaled 6/10/2024 DEROLD HAUFF
CofO Issued 6/10/2024 DEROLD HAUFF
Permit Finaled 6/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/6/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/8/2021 WALLIE JONG
Sewer availability Cleared 7/8/2021 WALLIE JONG
Hydrant and Access approval Cleared 9/12/2021 RUEL COLE
Construction near power lines Cleared 11/13/2021 RIDWAN HARDY
Construction within easement Cleared 11/13/2021 RIDWAN HARDY
Low Impact Development Cleared 2/1/2022 TA ANH
Roof/Waste drainage to street Cleared 3/21/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: NA41697       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/12/2023 Not Ready for Inspection ANTHONY EGSON
Underground Mechanical 4/12/2023 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 4/24/2023 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 4/24/2023 Corrections Issued ANTHONY EGSON
Piling/Pier/Caisson 4/24/2023 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 4/27/2023 Approved ANTHONY EGSON
Footing/Foundation/Slab 4/27/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 6/8/2023 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Corrections Issued ANTHONY EGSON
Green Building Rough 6/8/2023 Not Ready for Inspection ANTHONY EGSON
Verify Sprinkler Sign Off 6/8/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 8/9/2023 Corrections Issued ANTHONY EGSON
HVAC-Rough 8/9/2023 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 8/9/2023 Approved ANTHONY EGSON
ELECTRICAL-Rough 8/10/2023 Approved ANTHONY EGSON
HVAC-Rough 8/10/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 8/14/2023 Approved ANTHONY EGSON
Gas Test 8/14/2023 Approved ANTHONY EGSON
Green Building Rough 8/14/2023 Approved ANTHONY EGSON
Underground Mechanical 8/14/2023 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 8/22/2023 Partial Approval STUART CHAPMAN
Insulation 8/28/2023 Corrections Issued ANTHONY EGSON
Underground Mechanical 9/15/2023 Partial Inspection ANTHONY EGSON
Insulation 10/2/2023 Conditional Approval BRENDAN MORELLI
Underground Mechanical 10/2/2023 Partial Approval BRENDAN MORELLI
Drywall Nailing 10/16/2023 Approved ANTHONY EGSON
Shower Pan 10/16/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 10/30/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 2/22/2024 Corrections Issued ANTHONY EGSON
Final 2/22/2024 Corrections Issued ANTHONY EGSON
Green Building Final 2/22/2024 Approved ANTHONY EGSON
HVAC-Final 2/22/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 2/22/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 2/22/2024 SGSOV Approved ANTHONY EGSON
Service/Power Release 2/22/2024 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 2/22/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 5/8/2024 Approved ANTHONY EGSON
Final 5/8/2024 Corrections Issued ANTHONY EGSON
Service/Power Release 5/8/2024 Corrections Issued ANTHONY EGSON
Final 5/31/2024 OK to Issue CofO ANTHONY EGSON
Service/Power Release 5/31/2024 Approved ANTHONY EGSON