2453 N LANTERMAN TER 90039
Certificate Information: 2453 N LANTERMAN TER 90039
- Application / Permit
- 21010-10000-01451
- Plan Check / Job No.
- B21LA05668
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU PER GOVT. CODE 65852.2 (e)(1)(B) AND APPLICABLE PART OF LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 11/3/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 4/28/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 5/13/2021 | JASON HEALEY |
| Building Plans Picked Up | 5/25/2021 | APPLICANT |
| Applicant returned to address corrections | 4/20/2022 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 6/6/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 8/19/2022 | MAHNAZ NOURHASHEMI |
| Issued | 11/3/2022 | APPLICANT |
| CofO in Progress | 1/29/2025 | ENRIQUE MIRELES |
| Permit Finaled | 1/30/2025 | DEROLD HAUFF |
| CofO Issued | 1/30/2025 | DEROLD HAUFF |
| Permit Finaled | 1/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2022 | AMAAN MALIK |
| Street Frontage | Cleared | 6/8/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 6/14/2022 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 6/24/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 7/1/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/2/2022 | CINDY QI |
| GPI Written Notices | Cleared | 8/19/2022 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 8/19/2022 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Let Me Sleep Productions Inc; Lic. No.: 798325-B | PO BOX 16891 BEVERLY HILLS, CA 90209 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 11/13/2023 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 11/22/2023 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 11/22/2023 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/4/2023 | Conditional Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/11/2023 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 1/16/2024 | Partial Approval | JOAQUIN GREENOUGH |
| HVAC-Rough | 2/23/2024 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 2/23/2024 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 2/29/2024 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 3/5/2024 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 3/14/2024 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 4/4/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 4/4/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/8/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Partial Inspection | JOSEPH MCGARRY |
| Green Building Rough | 5/24/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 5/24/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 6/12/2024 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 6/18/2024 | Approved | RICHARD DOCKUS |
| Green Building Rough | 6/18/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Rough | 6/18/2024 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 6/18/2024 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/20/2024 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 6/20/2024 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 6/20/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 7/17/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/31/2024 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 8/16/2024 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 11/26/2024 | Approved | ENRIQUE MIRELES |
| Final | 11/26/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 11/26/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/26/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 11/26/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 11/26/2024 | Approved | ENRIQUE MIRELES |
| Final | 1/10/2025 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 1/10/2025 | Approved | ENRIQUE MIRELES |