630-630 1/2 W 95TH ST 90044

Certificate Information: 630-630 1/2 W 95TH ST 90044

Application / Permit
21010-10000-01446
Plan Check / Job No.
B21LA05648
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
1 OF 2 NEW 2-STORY DUPLEX WITH ATTACHED GARAGE (FRONT BUILDING)
Permit Issued
Issued on 8/31/2021
Issuing Office
Current Status
CofO Issued on 5/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 CARLOS MONTES
Corrections Issued 4/5/2021 CARLOS MONTES
Quality Review Completed 4/12/2021 KEN GILL
Building Plans Picked Up 4/15/2021 APPLICANT
Applicant returned to address corrections 6/16/2021 CARLOS MONTES
Plan Check Approved 8/17/2021 CARLOS MONTES
Issued 8/31/2021 APPLICANT
CofO in Progress 4/14/2022 ALEJANDRO DE ARTOLA
Permit Finaled 5/10/2022 DEROLD HAUFF
Permit Finaled 5/10/2022 DEROLD HAUFF
CofO Issued 5/10/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/12/2021 WALLIE JONG
Highway dedication Cleared 5/12/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/13/2021 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 5/17/2021 RICHARD REASER
Hydrant and Access approval Cleared 6/3/2021 ROBERT DUFF
Low Impact Development Cleared 6/7/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/7/2021 CELINA MORENO
Sewer availability Cleared 7/21/2021 WALLIE JONG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/5/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/18/2021 Partial Approval EUGENE CASSIDY
Underground Mechanical 11/18/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Partial Approval EUGENE CASSIDY
Insulation 11/19/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/21/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 1/21/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 1/21/2022 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 1/21/2022 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 1/21/2022 Approved ALIZAH MAYAGOITIA
Insulation 1/24/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/2/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 2/2/2022 Not Ready for Inspection JOHN KLARIN
Interior/Exterior Lathing 2/3/2022 Partial Approval JOHN KLARIN
Underground Mechanical 3/4/2022 Approved JOHN KLARIN
ELECTRICAL-Final 3/29/2022 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 4/1/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 4/1/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 4/1/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 4/1/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 4/1/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 4/1/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 4/1/2022 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 4/1/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 4/1/2022 Approved ALIZAH MAYAGOITIA
Final 4/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 4/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/13/2022 Approved ALEJANDRO DE ARTOLA
Final 4/13/2022 OK to Issue CofO ALEJANDRO DE ARTOLA
Service/Power Release 4/13/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/14/2022 Approved ALEJANDRO DE ARTOLA
Service/Power Release 4/14/2022 Approved ALEJANDRO DE ARTOLA