4143 S MARCASEL AVE 90066
Certificate Information: 4143 S MARCASEL AVE 90066
- Application / Permit
- 21010-10000-01440
- Plan Check / Job No.
- B21LA05614
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 2 STORY ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE 2 OF 2
- Permit Issued
- Issued on 2/7/2022
- Issuing Office
- Current Status
- CofO Issued on 5/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 4/8/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/13/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 6/15/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 10/8/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 10/14/2021 | ARSALAN SHABESTARI |
| Building Plans Picked Up | 1/13/2022 | APPLICANT |
| Issued | 2/7/2022 | APPLICANT |
| CofO in Progress | 5/18/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 5/20/2023 | DANIEL ORRANTE |
| CofO Issued | 5/20/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/20/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/3/2021 | PETE EYRE |
| Address approval | Cleared | 5/21/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2021 | JEANIE LAM |
| Sewer availability | Cleared | 5/21/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 6/27/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 9/21/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 10/6/2021 | CATHERINE ADROVER |
Contact Information
| Contractor | Ganpat Properties; Lic. No.: 778755-B | 2606 FOOTHILL BLVD SUITE #E LA CRESCENTA, CA 91214 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/5/2022 | Approved | PATRICK QUALEY |
| PLUMBING-Rough | 5/5/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Footing/Foundation/Slab | 5/18/2022 | Approved | PATRICK QUALEY |
| Pre-Inspection | 5/19/2022 | Partial Inspection | PATRICK QUALEY |
| Sewer | 6/14/2022 | Approved | PATRICK QUALEY |
| Gas Test | 6/16/2022 | Partial Approval | EVAN COOPER |
| Underground Mechanical | 6/22/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 8/9/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/9/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/26/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 8/26/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/26/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/6/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 9/6/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 10/5/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/5/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 10/5/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/5/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/5/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/11/2022 | Partial Approval | CLAYTON GRAHAM |
| PLUMBING-Rough | 10/11/2022 | Conditional Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 10/17/2022 | Not Ready for Inspection | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Corrections Issued | RICHARD STEINBACH |
| Green Building Rough | 10/17/2022 | Not Ready for Inspection | RICHARD STEINBACH |
| Verify Sprinkler Sign Off | 10/17/2022 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/14/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 11/23/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 11/23/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 11/23/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/23/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 12/5/2022 | Approved | JESUS RODRIGUEZ |
| Gas Test | 2/14/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 2/14/2023 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/22/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 3/8/2023 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Final | 3/8/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Service/Power Release | 3/8/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 3/8/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/27/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 4/27/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 4/27/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 4/27/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 4/27/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 4/27/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 5/4/2023 | Approved | JESUS RODRIGUEZ |
| Final | 5/4/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Smoke Detectors | 5/4/2023 | Approved | JESUS RODRIGUEZ |
| Final | 5/18/2023 | OK to Issue CofO | JESUS RODRIGUEZ |