4143 S MARCASEL AVE 90066

Certificate Information: 4143 S MARCASEL AVE 90066

Application / Permit
21010-10000-01440
Plan Check / Job No.
B21LA05614
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 2 STORY ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE 2 OF 2
Permit Issued
Issued on 2/7/2022
Issuing Office
Current Status
CofO Issued on 5/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 ARSALAN SHABESTARI
Corrections Issued 4/8/2021 ARSALAN SHABESTARI
Quality Review Completed 4/13/2021 MICHAEL PEREZ
Applicant returned to address corrections 6/15/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 10/8/2021 ARSALAN SHABESTARI
Plan Check Approved 10/14/2021 ARSALAN SHABESTARI
Building Plans Picked Up 1/13/2022 APPLICANT
Issued 2/7/2022 APPLICANT
CofO in Progress 5/18/2023 JESUS RODRIGUEZ
Permit Finaled 5/20/2023 DANIEL ORRANTE
CofO Issued 5/20/2023 DANIEL ORRANTE
Permit Finaled 5/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 5/3/2021 PETE EYRE
Address approval Cleared 5/21/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/21/2021 JEANIE LAM
Sewer availability Cleared 5/21/2021 JEANIE LAM
Hydrant and Access approval Cleared 6/27/2021 JOHN CONNEALLY
Low Impact Development Cleared 9/21/2021 CHRIS VONG
Roof/Waste drainage to street Cleared 10/6/2021 CATHERINE ADROVER

Contact Information

Contractor Ganpat Properties; Lic. No.: 778755-B 2606 FOOTHILL BLVD SUITE #E      LA CRESCENTA, CA 91214

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/5/2022 Approved PATRICK QUALEY
PLUMBING-Rough 5/5/2022 Not Ready for Inspection PATRICK QUALEY
Footing/Foundation/Slab 5/18/2022 Approved PATRICK QUALEY
Pre-Inspection 5/19/2022 Partial Inspection PATRICK QUALEY
Sewer 6/14/2022 Approved PATRICK QUALEY
Gas Test 6/16/2022 Partial Approval EVAN COOPER
Underground Mechanical 6/22/2022 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 8/9/2022 Not Ready for Inspection JESUS RODRIGUEZ
Verify Sprinkler Sign Off 8/9/2022 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/26/2022 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 8/26/2022 Not Ready for Inspection JESUS RODRIGUEZ
Verify Sprinkler Sign Off 8/26/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 9/6/2022 Corrections Issued JESUS RODRIGUEZ
Special/Order Compliance 9/6/2022 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Final 10/5/2022 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 10/5/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 10/5/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 10/5/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 10/5/2022 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 10/11/2022 Partial Approval CLAYTON GRAHAM
PLUMBING-Rough 10/11/2022 Conditional Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 10/17/2022 Not Ready for Inspection RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Corrections Issued RICHARD STEINBACH
Green Building Rough 10/17/2022 Not Ready for Inspection RICHARD STEINBACH
Verify Sprinkler Sign Off 10/17/2022 Approved RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/14/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/23/2022 Approved JESUS RODRIGUEZ
Green Building Rough 11/23/2022 Approved JESUS RODRIGUEZ
Insulation 11/23/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 11/23/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 12/5/2022 Approved JESUS RODRIGUEZ
Gas Test 2/14/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 2/14/2023 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Final 2/22/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Final 3/8/2023 Partial Approval JESUS RODRIGUEZ
HVAC-Final 3/8/2023 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 3/8/2023 Approved JESUS RODRIGUEZ
Special/Order Compliance 3/8/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Final 4/27/2023 Corrections Issued JESUS RODRIGUEZ
Final 4/27/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 4/27/2023 Approved JESUS RODRIGUEZ
HVAC-Final 4/27/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 4/27/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/27/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 4/27/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 5/4/2023 Approved JESUS RODRIGUEZ
Final 5/4/2023 Not Ready for Inspection JESUS RODRIGUEZ
Smoke Detectors 5/4/2023 Approved JESUS RODRIGUEZ
Final 5/18/2023 OK to Issue CofO JESUS RODRIGUEZ