|
Pre-Inspection
|
1/17/2023
|
Partial Inspection
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
3/29/2023
|
Conditional Approval
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
4/3/2023
|
Approved
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
4/4/2023
|
Conditional Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
4/14/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
4/19/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
4/25/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
5/2/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Special/Order Compliance
|
5/17/2023
|
Partial Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/9/2023
|
Partial Inspection
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
6/12/2023
|
Approved
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/12/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/13/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
6/14/2023
|
Approved
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/27/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/28/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
7/5/2023
|
Partial Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
7/10/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
7/11/2023
|
Partial Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
7/13/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
8/11/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
8/15/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
8/15/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
8/15/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
8/15/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
8/22/2023
|
Conditional Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
8/23/2023
|
Partial Inspection
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
9/8/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/11/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/12/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Shotcrete
|
9/13/2023
|
Approved
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
9/14/2023
|
Conditional Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/14/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Shotcrete
|
9/15/2023
|
Approved
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
9/20/2023
|
Approved
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/21/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
10/24/2023
|
Partial Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
11/6/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
11/7/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
11/8/2023
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
12/5/2023
|
Approved
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/5/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
12/5/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
12/5/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/5/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/11/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
12/11/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
12/11/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/11/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/2/2024
|
Conditional Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
1/2/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
1/2/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
1/2/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/29/2024
|
Conditional Approval
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
2/15/2024
|
Approved
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
2/15/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
2/20/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Reinf. Masonry
|
2/29/2024
|
Approved
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/29/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
2/29/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
2/29/2024
|
Approved
|
JOHN KITCKO
|
|
Wood Frame
|
2/29/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Masonry Wall/Backfill
|
3/4/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
3/8/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
3/8/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
3/14/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
3/14/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
3/14/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Insulation
|
3/18/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
3/22/2024
|
Approved
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
3/22/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
3/26/2024
|
Conditional Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/9/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
4/18/2024
|
Partial Approval
|
DANIEL VARNUM
|
|
Insulation
|
4/18/2024
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Deputy Wood Construction
|
4/25/2024
|
Approved
|
JOHN KITCKO
|
|
Insulation
|
4/29/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
5/3/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
5/3/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
5/3/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/8/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
5/8/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
5/8/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
5/13/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
5/13/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
5/13/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
5/20/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
5/20/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
5/20/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
5/22/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
5/28/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
6/4/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
6/4/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/6/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
6/6/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Deputy Wood Construction
|
6/11/2024
|
Conditional Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/11/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
6/11/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
6/13/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
6/13/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
6/13/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/17/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
6/17/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
6/18/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Wood Construction
|
6/26/2024
|
Conditional Approval
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
6/27/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
7/2/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/8/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/17/2024
|
Corrections Issued
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/23/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
7/29/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Wood Frame
|
7/29/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
Insulation
|
8/1/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
8/5/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
8/5/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Insulation
|
8/6/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Interior/Exterior Lathing
|
8/6/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Wood Construction
|
8/7/2024
|
Conditional Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
8/7/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
8/7/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
8/8/2024
|
Conditional Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
8/12/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Insulation
|
8/12/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
8/14/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
8/14/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
8/15/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
8/19/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Insulation
|
8/19/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
8/23/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
8/29/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/29/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
8/29/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
8/29/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
8/30/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
9/4/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
9/4/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
9/6/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
9/10/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
9/10/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
9/13/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
9/16/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
9/16/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
9/17/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
9/19/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
9/25/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
10/2/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
10/3/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
10/7/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
10/8/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/16/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
10/22/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
10/23/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
10/25/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Insulation
|
10/28/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Insulation
|
10/31/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/5/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
11/12/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
11/18/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
11/20/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
11/27/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
11/27/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
12/13/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
12/16/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/16/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
12/20/2024
|
Approved
|
JOHN KITCKO
|
|
Wood Frame
|
12/20/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
12/27/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
1/8/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
1/21/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Light Gage Steel Frame
|
1/23/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
1/28/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
1/30/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
2/3/2025
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
2/4/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
2/5/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
2/6/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Special/Order Compliance
|
2/11/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
2/19/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
2/20/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
2/21/2025
|
Conditional Approval
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
3/4/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
3/7/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
3/13/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
3/14/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
3/27/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
4/4/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
4/10/2025
|
Conditional Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
4/14/2025
|
Partial Approval
|
CHRISTOPHER BLACKWOOD
|
|
Light Gage Steel Frame
|
4/28/2025
|
Partial Approval
|
CHRISTOPHER BLACKWOOD
|
|
Drywall Nailing
|
4/29/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
5/1/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
5/6/2025
|
Approved
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
5/22/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
5/28/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
5/30/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/3/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
6/5/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
6/5/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Drilled-In Anchors
|
6/10/2025
|
Conditional Approval
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
6/25/2025
|
Conditional Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/27/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
7/1/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
7/3/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
7/9/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Special/Order Compliance
|
8/21/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Green Building Final
|
9/5/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Smoke Detectors
|
9/5/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
12/8/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Smoke Detectors
|
12/8/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Rec and Parks Fee Memo
|
12/8/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
12/10/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
12/17/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
12/24/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Final
|
12/29/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
12/29/2025
|
Approved
|
JOHN KITCKO
|
|
Green Building Final
|
12/29/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Reinforced Concrete Frame
|
12/29/2025
|
Approved
|
JOHN KITCKO
|
|
SGSOV-Seismic Gas S/O Valve
|
12/29/2025
|
SGSOV Approved
|
JOHN KITCKO
|
|
Smoke Detectors
|
12/29/2025
|
Approved
|
JOHN KITCKO
|
|
Wood Frame
|
12/29/2025
|
Approved
|
JOHN KITCKO
|
|
Special/Order Compliance
|
1/13/2026
|
Partial Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
1/21/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Final
|
1/27/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Green Building Final
|
1/27/2026
|
Approved
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
1/27/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
1/27/2026
|
Partial Inspection
|
JOHN KITCKO
|
|
Final
|
6/8/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
6/30/2026
|
Not Ready for Inspection
|
DEANDRE HOFFMAN
|
|
Final
|
7/7/2026
|
OK to Issue CofO
|
DEANDRE HOFFMAN
|