10154 N HADDON AVE 91331
Certificate Information: 10154 N HADDON AVE 91331
- Application / Permit
- 21010-10000-01425
- Plan Check / Job No.
- B21LA05528
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) CARPORT FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) & (e)
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Current Status
- CofO Issued on 3/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | LAMAR DAVIS |
| Corrections Issued | 5/12/2021 | LAMAR DAVIS |
| Quality Review Completed | 5/12/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 9/20/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 3/2/2022 | LAMAR DAVIS |
| Plan Check Approved | 7/25/2022 | LAMAR DAVIS |
| No Progress | 8/2/2022 | LAMAR DAVIS |
| Plan Check Approved | 8/2/2022 | LAMAR DAVIS |
| Issued | 8/2/2022 | APPLICANT |
| CofO in Progress | 3/14/2023 | MICHEL ABAJAN |
| CofO Issued | 3/16/2023 | MICHAEL SMITH |
| Permit Finaled | 3/16/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/20/2021 | LAMAR DAVIS |
| Address approval | Cleared | 9/21/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/21/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/23/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 2/2/2022 | JONATAN VELASQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/16/2022 | Partial Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 9/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 9/16/2022 | Partial Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 9/20/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 9/20/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/27/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/27/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 10/27/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 10/27/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 10/27/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/27/2022 | Approved | MICHEL ABAJAN |
| Insulation | 11/2/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/2/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 11/2/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/8/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/8/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/18/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 12/8/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/10/2023 | No Access for Inspection | MICHEL ABAJAN |
| Final | 1/10/2023 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Final | 1/10/2023 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 1/10/2023 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 1/10/2023 | No Access for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/10/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 1/10/2023 | No Access for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/13/2023 | Approved | MICHEL ABAJAN |
| Final | 1/13/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 1/13/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 1/13/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/13/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/13/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 1/13/2023 | Approved | MICHEL ABAJAN |
| Final | 1/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 3/14/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 3/14/2023 | Approved | MICHEL ABAJAN |