10154 N HADDON AVE 91331

Certificate Information: 10154 N HADDON AVE 91331

Application / Permit
21010-10000-01425
Plan Check / Job No.
B21LA05528
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) CARPORT FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) & (e)
Permit Issued
Issued on 8/2/2022
Issuing Office
Current Status
CofO Issued on 3/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 LAMAR DAVIS
Corrections Issued 5/12/2021 LAMAR DAVIS
Quality Review Completed 5/12/2021 HERNAN ARREOLA
Applicant returned to address corrections 9/20/2021 LAMAR DAVIS
Applicant returned to address corrections 3/2/2022 LAMAR DAVIS
Plan Check Approved 7/25/2022 LAMAR DAVIS
No Progress 8/2/2022 LAMAR DAVIS
Plan Check Approved 8/2/2022 LAMAR DAVIS
Issued 8/2/2022 APPLICANT
CofO in Progress 3/14/2023 MICHEL ABAJAN
CofO Issued 3/16/2023 MICHAEL SMITH
Permit Finaled 3/16/2023 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 9/20/2021 LAMAR DAVIS
Address approval Cleared 9/21/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/21/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/23/2021 CARLOS AGUILERA
Sewer availability Cleared 9/23/2021 CARLOS AGUILERA
Low Impact Development Cleared 2/2/2022 JONATAN VELASQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/16/2022 Partial Approval CALEB MEISTER
Footing/Foundation/Slab 9/16/2022 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 9/16/2022 Partial Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 9/20/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 9/20/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 10/27/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 10/27/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Partial Approval MICHEL ABAJAN
Green Building Rough 10/27/2022 Approved MICHEL ABAJAN
HVAC-Rough 10/27/2022 Approved MICHEL ABAJAN
METHANE-Rough 10/27/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 10/27/2022 Approved MICHEL ABAJAN
Insulation 11/2/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/2/2022 Approved MICHEL ABAJAN
Shower Pan 11/2/2022 Approved MICHEL ABAJAN
Drywall Nailing 11/8/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/8/2022 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 11/18/2022 Approved MICHEL ABAJAN
Underground Mechanical 12/8/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/10/2023 No Access for Inspection MICHEL ABAJAN
Final 1/10/2023 No Access for Inspection MICHEL ABAJAN
Green Building Final 1/10/2023 No Access for Inspection MICHEL ABAJAN
HVAC-Final 1/10/2023 No Access for Inspection MICHEL ABAJAN
PLUMBING-Final 1/10/2023 No Access for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/10/2023 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 1/10/2023 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Final 1/13/2023 Approved MICHEL ABAJAN
Final 1/13/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 1/13/2023 Approved MICHEL ABAJAN
HVAC-Final 1/13/2023 Approved MICHEL ABAJAN
PLUMBING-Final 1/13/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/13/2023 Approved MICHEL ABAJAN
Final 1/27/2023 Corrections Issued JENNIFER RABUCHIN
Final 3/14/2023 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 3/14/2023 Approved MICHEL ABAJAN