11007 N LEOLANG AVE 91040

Certificate Information: 11007 N LEOLANG AVE 91040

Application / Permit
21010-10000-01419
Plan Check / Job No.
B21LA05493
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED TWO STORY A.D.U.
Permit Issued
Issued on 9/15/2021
Issuing Office
Current Status
CofO Issued on 8/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 JOE VO
Corrections Issued 4/24/2021 JOE VO
Quality Review Completed 4/30/2021 MICHAEL PEREZ
Applicant returned to address corrections 5/15/2021 JOE VO
Plan Check Approved 8/31/2021 JOE VO
Issued 9/15/2021 APPLICANT
CofO in Progress 7/26/2024 MATTHEW NELSON
Permit Finaled 8/1/2024 RUBEN SALAS
Permit Finaled 8/1/2024 RUBEN SALAS
CofO Issued 8/1/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/29/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/3/2021 ADRIAN CASTRO
Sewer availability Cleared 5/4/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 6/11/2021 KURT CORRAL
Low Impact Development Cleared 8/11/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/19/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 8/31/2021 JOE VO

Contact Information

Contractor Valencia Construction; Lic. No.: 864109-B 6901 ENFIELD AVE      RESEDA, CA 91335
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2022 Approved MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 2/25/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Partial Approval MATTHEW NELSON
Verify Sprinkler Sign Off 4/22/2022 Approved MATTHEW NELSON
Wood Frame 4/28/2022 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 5/26/2022 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 6/23/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 6/23/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 6/23/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/23/2022 Approved JENNIFER RABUCHIN
Special/Order Compliance 6/23/2022 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 6/23/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/11/2022 Approved MATTHEW NELSON
Sewer 7/11/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/28/2022 Approved MATTHEW NELSON
Drywall Nailing 9/15/2022 Approved MATTHEW NELSON
Shower Pan 10/13/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 7/19/2023 Corrections Issued MATTHEW NELSON
Final 7/19/2023 Corrections Issued MATTHEW NELSON
HVAC-Final 7/19/2023 Corrections Issued MATTHEW NELSON
PLUMBING-Final 7/19/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Approved MATTHEW NELSON
Service/Power Release 7/19/2023 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 7/19/2023 Approved MATTHEW NELSON
Final 10/26/2023 Not Ready for Inspection WILLIAM WREN
Service/Power Release 10/26/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Final 3/14/2024 Partial Inspection WILLIAM WREN
Final 4/17/2024 Corrections Issued WILLIAM WREN
Service/Power Release 4/17/2024 Not Ready for Inspection WILLIAM WREN
Final 7/26/2024 OK to Issue CofO MATTHEW NELSON
Service/Power Release 7/26/2024 Approved MATTHEW NELSON