11007 N LEOLANG AVE 91040
Certificate Information: 11007 N LEOLANG AVE 91040
- Application / Permit
- 21010-10000-01419
- Plan Check / Job No.
- B21LA05493
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED TWO STORY A.D.U.
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- CofO Issued on 8/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | JOE VO |
| Corrections Issued | 4/24/2021 | JOE VO |
| Quality Review Completed | 4/30/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 5/15/2021 | JOE VO |
| Plan Check Approved | 8/31/2021 | JOE VO |
| Issued | 9/15/2021 | APPLICANT |
| CofO in Progress | 7/26/2024 | MATTHEW NELSON |
| Permit Finaled | 8/1/2024 | RUBEN SALAS |
| Permit Finaled | 8/1/2024 | RUBEN SALAS |
| CofO Issued | 8/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/4/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 6/11/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 8/11/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 8/19/2021 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 8/31/2021 | JOE VO |
Contact Information
| Contractor | Valencia Construction; Lic. No.: 864109-B | 6901 ENFIELD AVE RESEDA, CA 91335 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2022 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 2/25/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Partial Approval | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 4/22/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 4/28/2022 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/26/2022 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/23/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/23/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/23/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/23/2022 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 6/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 6/23/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/11/2022 | Approved | MATTHEW NELSON |
| Sewer | 7/11/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/28/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/15/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 10/13/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 7/19/2023 | Corrections Issued | MATTHEW NELSON |
| Final | 7/19/2023 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 7/19/2023 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 7/19/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 7/19/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 7/19/2023 | Approved | MATTHEW NELSON |
| Final | 10/26/2023 | Not Ready for Inspection | WILLIAM WREN |
| Service/Power Release | 10/26/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Final | 3/14/2024 | Partial Inspection | WILLIAM WREN |
| Final | 4/17/2024 | Corrections Issued | WILLIAM WREN |
| Service/Power Release | 4/17/2024 | Not Ready for Inspection | WILLIAM WREN |
| Final | 7/26/2024 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 7/26/2024 | Approved | MATTHEW NELSON |